8451 68/2024 14B EPF Appeal A-2034 Dindigul Co-operative House Building Society Ltd., APFC, Dindigul 08/08/2024
11/07/2024
18/09/2024
12/11/2024
23/12/2024
09/01/2025
10/03/2025
10/06/2025
Delay condoned. The Appellant deposited Rs. 1,84,622/- in pursuance to order dtd. 12.12.2023. Operation of Impugned order shall remain stayed & no coercive action shall be taken against appellant. For Counter/rejoinder.
8452 68/2024 14B EPF Appeal A-2034 Dindigul Co-operative House Building Society Ltd., APFC, Dindigul 08/08/2024
11/07/2024
18/09/2024
12/11/2024
23/12/2024
09/01/2025
10/03/2025
10/06/2025
Delay condoned. The Appellant deposited Rs. 1,84,622/- in pursuance to order dtd. 12.12.2023. Operation of Impugned order shall remain stayed & no coercive action shall be taken against appellant. For Counter/rejoinder.
8453 68/2024 14B EPF Appeal A-2034 Dindigul Co-operative House Building Society Ltd., APFC, Dindigul 08/08/2024
11/07/2024
18/09/2024
12/11/2024
23/12/2024
09/01/2025
10/03/2025
10/06/2025
Delay condoned. The Appellant deposited Rs. 1,84,622/- in pursuance to order dtd. 12.12.2023. Operation of Impugned order shall remain stayed & no coercive action shall be taken against appellant. For Counter/rejoinder.
8454 68/2024 14B EPF Appeal A-2034 Dindigul Co-operative House Building Society Ltd., APFC, Dindigul 08/08/2024
11/07/2024
18/09/2024
12/11/2024
23/12/2024
09/01/2025
10/03/2025
10/06/2025
Delay condoned. The Appellant deposited Rs. 1,84,622/- in pursuance to order dtd. 12.12.2023. Operation of Impugned order shall remain stayed & no coercive action shall be taken against appellant. For Counter/rejoinder.
8455 68/2024 14B EPF Appeal A-2034 Dindigul Co-operative House Building Society Ltd., APFC, Dindigul 08/08/2024
11/07/2024
18/09/2024
12/11/2024
23/12/2024
09/01/2025
10/03/2025
10/06/2025
Delay condoned. The Appellant deposited Rs. 1,84,622/- in pursuance to order dtd. 12.12.2023. Operation of Impugned order shall remain stayed & no coercive action shall be taken against appellant. For Counter/rejoinder.
8456 68/2024 14B EPF Appeal A-2034 Dindigul Co-operative House Building Society Ltd., APFC, Dindigul 08/08/2024
11/07/2024
18/09/2024
12/11/2024
23/12/2024
09/01/2025
10/03/2025
10/06/2025
Delay condoned. The Appellant deposited Rs. 1,84,622/- in pursuance to order dtd. 12.12.2023. Operation of Impugned order shall remain stayed & no coercive action shall be taken against appellant. For Counter/rejoinder.
8457 68/2024 14B EPF Appeal A-2034 Dindigul Co-operative House Building Society Ltd., APFC, Dindigul 08/08/2024
11/07/2024
18/09/2024
12/11/2024
23/12/2024
09/01/2025
10/03/2025
10/06/2025
Delay condoned. The Appellant deposited Rs. 1,84,622/- in pursuance to order dtd. 12.12.2023. Operation of Impugned order shall remain stayed & no coercive action shall be taken against appellant. For Counter/rejoinder.
8458 67/2024 7A EPF Appeal Channel Bharat Entertainment Pvt. Ltd, RPFC, Chennai & Another 27/11/2024
27/12/2024
27/01/2025
27/02/2025
27/03/2025
28/04/2025
28/05/2025
Delay Condoned. Appeal is admitted. Stayed if appellant deposits Rs.2 Lakhs with in a period of 6 weeks from the date of receipt of the copy failing which the appellant is not entitled for the interim relief granted today. Counter reply ten weeks, rejoin
8459 67/2024 7A EPF Appeal Channel Bharat Entertainment Pvt. Ltd, RPFC, Chennai & Another 27/11/2024
27/12/2024
27/01/2025
27/02/2025
27/03/2025
28/04/2025
28/05/2025
Delay Condoned. Appeal is admitted. Stayed if appellant deposits Rs.2 Lakhs with in a period of 6 weeks from the date of receipt of the copy failing which the appellant is not entitled for the interim relief granted today. Counter reply ten weeks, rejoin
8460 67/2024 7A EPF Appeal Channel Bharat Entertainment Pvt. Ltd, RPFC, Chennai & Another 27/11/2024
27/12/2024
27/01/2025
27/02/2025
27/03/2025
28/04/2025
28/05/2025
Delay Condoned. Appeal is admitted. Stayed if appellant deposits Rs.2 Lakhs with in a period of 6 weeks from the date of receipt of the copy failing which the appellant is not entitled for the interim relief granted today. Counter reply ten weeks, rejoin
8461 67/2024 7A EPF Appeal Channel Bharat Entertainment Pvt. Ltd, RPFC, Chennai & Another 27/11/2024
27/12/2024
27/01/2025
27/02/2025
27/03/2025
28/04/2025
28/05/2025
Delay Condoned. Appeal is admitted. Stayed if appellant deposits Rs.2 Lakhs with in a period of 6 weeks from the date of receipt of the copy failing which the appellant is not entitled for the interim relief granted today. Counter reply ten weeks, rejoin
8462 67/2024 7A EPF Appeal Channel Bharat Entertainment Pvt. Ltd, RPFC, Chennai & Another 27/11/2024
27/12/2024
27/01/2025
27/02/2025
27/03/2025
28/04/2025
28/05/2025
Delay Condoned. Appeal is admitted. Stayed if appellant deposits Rs.2 Lakhs with in a period of 6 weeks from the date of receipt of the copy failing which the appellant is not entitled for the interim relief granted today. Counter reply ten weeks, rejoin
8463 67/2024 7A EPF Appeal Channel Bharat Entertainment Pvt. Ltd, RPFC, Chennai & Another 27/11/2024
27/12/2024
27/01/2025
27/02/2025
27/03/2025
28/04/2025
28/05/2025
Delay Condoned. Appeal is admitted. Stayed if appellant deposits Rs.2 Lakhs with in a period of 6 weeks from the date of receipt of the copy failing which the appellant is not entitled for the interim relief granted today. Counter reply ten weeks, rejoin
8464 67/2024 7A EPF Appeal Channel Bharat Entertainment Pvt. Ltd, RPFC, Chennai & Another 27/11/2024
27/12/2024
27/01/2025
27/02/2025
27/03/2025
28/04/2025
28/05/2025
Delay Condoned. Appeal is admitted. Stayed if appellant deposits Rs.2 Lakhs with in a period of 6 weeks from the date of receipt of the copy failing which the appellant is not entitled for the interim relief granted today. Counter reply ten weeks, rejoin
8465 62/2024 7A EPF Appeal DBS Bank India Ltd., RPFC-II, Tambaram 10/06/2024
07/08/2024
11/07/2024
18/09/2024
29/08/2024
20/11/2024
27/02/2025
21/05/2025
Delay condoned. Appeal is admitted. Imp. Order dated 16.12.2023 passed by RPFC-II, Chennai shall remain stayed until further order. For Counter.
8466 62/2024 7A EPF Appeal DBS Bank India Ltd., RPFC-II, Tambaram 10/06/2024
07/08/2024
11/07/2024
18/09/2024
29/08/2024
20/11/2024
27/02/2025
21/05/2025
Delay condoned. Appeal is admitted. Imp. Order dated 16.12.2023 passed by RPFC-II, Chennai shall remain stayed until further order. For Counter.
8467 62/2024 7A EPF Appeal DBS Bank India Ltd., RPFC-II, Tambaram 10/06/2024
07/08/2024
11/07/2024
18/09/2024
29/08/2024
20/11/2024
27/02/2025
21/05/2025
Delay condoned. Appeal is admitted. Imp. Order dated 16.12.2023 passed by RPFC-II, Chennai shall remain stayed until further order. For Counter.
8468 62/2024 7A EPF Appeal DBS Bank India Ltd., RPFC-II, Tambaram 10/06/2024
07/08/2024
11/07/2024
18/09/2024
29/08/2024
20/11/2024
27/02/2025
21/05/2025
Delay condoned. Appeal is admitted. Imp. Order dated 16.12.2023 passed by RPFC-II, Chennai shall remain stayed until further order. For Counter.
8469 62/2024 7A EPF Appeal DBS Bank India Ltd., RPFC-II, Tambaram 10/06/2024
07/08/2024
11/07/2024
18/09/2024
29/08/2024
20/11/2024
27/02/2025
21/05/2025
Delay condoned. Appeal is admitted. Imp. Order dated 16.12.2023 passed by RPFC-II, Chennai shall remain stayed until further order. For Counter.
8470 62/2024 7A EPF Appeal DBS Bank India Ltd., RPFC-II, Tambaram 10/06/2024
07/08/2024
11/07/2024
18/09/2024
29/08/2024
20/11/2024
27/02/2025
21/05/2025
Delay condoned. Appeal is admitted. Imp. Order dated 16.12.2023 passed by RPFC-II, Chennai shall remain stayed until further order. For Counter.
8471 62/2024 7A EPF Appeal DBS Bank India Ltd., RPFC-II, Tambaram 10/06/2024
07/08/2024
11/07/2024
18/09/2024
29/08/2024
20/11/2024
27/02/2025
21/05/2025
Delay condoned. Appeal is admitted. Imp. Order dated 16.12.2023 passed by RPFC-II, Chennai shall remain stayed until further order. For Counter.
8472 62/2024 7A EPF Appeal DBS Bank India Ltd., RPFC-II, Tambaram 10/06/2024
07/08/2024
11/07/2024
18/09/2024
29/08/2024
20/11/2024
27/02/2025
21/05/2025
Delay condoned. Appeal is admitted. Imp. Order dated 16.12.2023 passed by RPFC-II, Chennai shall remain stayed until further order. For Counter.
8473 66/2024 14B EPF Appeal Sri Raju Cotton Mills APFC, Sivakasi 14/10/2024
14/11/2024
16/12/2024
09/01/2025
07/03/2025
23/05/2025
Memo of compliance filed on behalf of appellant. Stay order dtd. 11.07.2024 shall continue until further orders. For rejoinder/counter.
8474 66/2024 14B EPF Appeal Sri Raju Cotton Mills APFC, Sivakasi 14/10/2024
14/11/2024
16/12/2024
09/01/2025
07/03/2025
23/05/2025
Memo of compliance filed on behalf of appellant. Stay order dtd. 11.07.2024 shall continue until further orders. For rejoinder/counter.
8475 66/2024 14B EPF Appeal Sri Raju Cotton Mills APFC, Sivakasi 14/10/2024
14/11/2024
16/12/2024
09/01/2025
07/03/2025
23/05/2025
Memo of compliance filed on behalf of appellant. Stay order dtd. 11.07.2024 shall continue until further orders. For rejoinder/counter.
8476 66/2024 14B EPF Appeal Sri Raju Cotton Mills APFC, Sivakasi 14/10/2024
14/11/2024
16/12/2024
09/01/2025
07/03/2025
23/05/2025
Memo of compliance filed on behalf of appellant. Stay order dtd. 11.07.2024 shall continue until further orders. For rejoinder/counter.
8477 66/2024 14B EPF Appeal Sri Raju Cotton Mills APFC, Sivakasi 14/10/2024
14/11/2024
16/12/2024
09/01/2025
07/03/2025
23/05/2025
Memo of compliance filed on behalf of appellant. Stay order dtd. 11.07.2024 shall continue until further orders. For rejoinder/counter.
8478 66/2024 14B EPF Appeal Sri Raju Cotton Mills APFC, Sivakasi 14/10/2024
14/11/2024
16/12/2024
09/01/2025
07/03/2025
23/05/2025
Memo of compliance filed on behalf of appellant. Stay order dtd. 11.07.2024 shall continue until further orders. For rejoinder/counter.
8479 65/2024 7A EPF Appeal Mayan Infrastructure Pvt. Ltd., RPFC-II, Chennai 24/10/2024
27/11/2024
27/12/2024
27/01/2025
27/02/2025
27/03/2025
28/04/2025
28/05/2025
Delay Condoned. Appeal is admitted. Stayed if appellant deposits Rs.30 Lakhs with in a period of 8 weeks from the date of receipt of the copy failing which the appellant is not entitled for the interim relief granted today. Counter reply ten weeks, rejoin
8480 65/2024 7A EPF Appeal Mayan Infrastructure Pvt. Ltd., RPFC-II, Chennai 24/10/2024
27/11/2024
27/12/2024
27/01/2025
27/02/2025
27/03/2025
28/04/2025
28/05/2025
Delay Condoned. Appeal is admitted. Stayed if appellant deposits Rs.30 Lakhs with in a period of 8 weeks from the date of receipt of the copy failing which the appellant is not entitled for the interim relief granted today. Counter reply ten weeks, rejoin
8481 65/2024 7A EPF Appeal Mayan Infrastructure Pvt. Ltd., RPFC-II, Chennai 24/10/2024
27/11/2024
27/12/2024
27/01/2025
27/02/2025
27/03/2025
28/04/2025
28/05/2025
Delay Condoned. Appeal is admitted. Stayed if appellant deposits Rs.30 Lakhs with in a period of 8 weeks from the date of receipt of the copy failing which the appellant is not entitled for the interim relief granted today. Counter reply ten weeks, rejoin
8482 65/2024 7A EPF Appeal Mayan Infrastructure Pvt. Ltd., RPFC-II, Chennai 24/10/2024
27/11/2024
27/12/2024
27/01/2025
27/02/2025
27/03/2025
28/04/2025
28/05/2025
Delay Condoned. Appeal is admitted. Stayed if appellant deposits Rs.30 Lakhs with in a period of 8 weeks from the date of receipt of the copy failing which the appellant is not entitled for the interim relief granted today. Counter reply ten weeks, rejoin
8483 65/2024 7A EPF Appeal Mayan Infrastructure Pvt. Ltd., RPFC-II, Chennai 24/10/2024
27/11/2024
27/12/2024
27/01/2025
27/02/2025
27/03/2025
28/04/2025
28/05/2025
Delay Condoned. Appeal is admitted. Stayed if appellant deposits Rs.30 Lakhs with in a period of 8 weeks from the date of receipt of the copy failing which the appellant is not entitled for the interim relief granted today. Counter reply ten weeks, rejoin
8484 65/2024 7A EPF Appeal Mayan Infrastructure Pvt. Ltd., RPFC-II, Chennai 24/10/2024
27/11/2024
27/12/2024
27/01/2025
27/02/2025
27/03/2025
28/04/2025
28/05/2025
Delay Condoned. Appeal is admitted. Stayed if appellant deposits Rs.30 Lakhs with in a period of 8 weeks from the date of receipt of the copy failing which the appellant is not entitled for the interim relief granted today. Counter reply ten weeks, rejoin
8485 65/2024 7A EPF Appeal Mayan Infrastructure Pvt. Ltd., RPFC-II, Chennai 24/10/2024
27/11/2024
27/12/2024
27/01/2025
27/02/2025
27/03/2025
28/04/2025
28/05/2025
Delay Condoned. Appeal is admitted. Stayed if appellant deposits Rs.30 Lakhs with in a period of 8 weeks from the date of receipt of the copy failing which the appellant is not entitled for the interim relief granted today. Counter reply ten weeks, rejoin
8486 65/2024 7A EPF Appeal Mayan Infrastructure Pvt. Ltd., RPFC-II, Chennai 24/10/2024
27/11/2024
27/12/2024
27/01/2025
27/02/2025
27/03/2025
28/04/2025
28/05/2025
Delay Condoned. Appeal is admitted. Stayed if appellant deposits Rs.30 Lakhs with in a period of 8 weeks from the date of receipt of the copy failing which the appellant is not entitled for the interim relief granted today. Counter reply ten weeks, rejoin
8487 64/2024 7A EPF Appeal Hi-tech Valves APFC, Ambattur 10/06/2024
07/08/2024
11/07/2024
12/09/2024
11/11/2024
11/12/2024
07/01/2025
Final Order - Appeal is dismissed for want of prosecution.
8488 64/2024 7A EPF Appeal Hi-tech Valves APFC, Ambattur 10/06/2024
07/08/2024
11/07/2024
12/09/2024
11/11/2024
11/12/2024
07/01/2025
Final Order - Appeal is dismissed for want of prosecution.
8489 64/2024 7A EPF Appeal Hi-tech Valves APFC, Ambattur 10/06/2024
07/08/2024
11/07/2024
12/09/2024
11/11/2024
11/12/2024
07/01/2025
Final Order - Appeal is dismissed for want of prosecution.
8490 64/2024 7A EPF Appeal Hi-tech Valves APFC, Ambattur 10/06/2024
07/08/2024
11/07/2024
12/09/2024
11/11/2024
11/12/2024
07/01/2025
Final Order - Appeal is dismissed for want of prosecution.
8491 64/2024 7A EPF Appeal Hi-tech Valves APFC, Ambattur 10/06/2024
07/08/2024
11/07/2024
12/09/2024
11/11/2024
11/12/2024
07/01/2025
Final Order - Appeal is dismissed for want of prosecution.
8492 64/2024 7A EPF Appeal Hi-tech Valves APFC, Ambattur 10/06/2024
07/08/2024
11/07/2024
12/09/2024
11/11/2024
11/12/2024
07/01/2025
Final Order - Appeal is dismissed for want of prosecution.
8493 64/2024 7A EPF Appeal Hi-tech Valves APFC, Ambattur 10/06/2024
07/08/2024
11/07/2024
12/09/2024
11/11/2024
11/12/2024
07/01/2025
Final Order - Appeal is dismissed for want of prosecution.
8494 63/2024 7Q EPF Appeal The Professional Courier APFC, Trichy & Another 10/06/2024
07/08/2024
11/07/2024
18/09/2024
29/08/2024
11/11/2024
11/12/2024
07/01/2025
Final Order - Appeal is dismissed for want of prosecution.
8495 63/2024 7Q EPF Appeal The Professional Courier APFC, Trichy & Another 10/06/2024
07/08/2024
11/07/2024
18/09/2024
29/08/2024
11/11/2024
11/12/2024
07/01/2025
Final Order - Appeal is dismissed for want of prosecution.
8496 63/2024 7Q EPF Appeal The Professional Courier APFC, Trichy & Another 10/06/2024
07/08/2024
11/07/2024
18/09/2024
29/08/2024
11/11/2024
11/12/2024
07/01/2025
Final Order - Appeal is dismissed for want of prosecution.
8497 63/2024 7Q EPF Appeal The Professional Courier APFC, Trichy & Another 10/06/2024
07/08/2024
11/07/2024
18/09/2024
29/08/2024
11/11/2024
11/12/2024
07/01/2025
Final Order - Appeal is dismissed for want of prosecution.
8498 63/2024 7Q EPF Appeal The Professional Courier APFC, Trichy & Another 10/06/2024
07/08/2024
11/07/2024
18/09/2024
29/08/2024
11/11/2024
11/12/2024
07/01/2025
Final Order - Appeal is dismissed for want of prosecution.
8499 63/2024 7Q EPF Appeal The Professional Courier APFC, Trichy & Another 10/06/2024
07/08/2024
11/07/2024
18/09/2024
29/08/2024
11/11/2024
11/12/2024
07/01/2025
Final Order - Appeal is dismissed for want of prosecution.
8500 63/2024 7Q EPF Appeal The Professional Courier APFC, Trichy & Another 10/06/2024
07/08/2024
11/07/2024
18/09/2024
29/08/2024
11/11/2024
11/12/2024
07/01/2025
Final Order - Appeal is dismissed for want of prosecution.