74151 293/2018 14B-7Q EPF Appeal Puliccar Mills Ltd RPFC, Salem 22/05/2024
08/08/2024
18/11/2024
25/02/2025
19/05/2025
08/08/2025
13/08/2025
(Camp)Final Order - The Appeal is partly allowed. The Respondent is directed to recover only 50% of the damages amount.
74152 293/2018 14B-7Q EPF Appeal Puliccar Mills Ltd RPFC, Salem 22/05/2024
08/08/2024
18/11/2024
25/02/2025
19/05/2025
08/08/2025
13/08/2025
(Camp)Final Order - The Appeal is partly allowed. The Respondent is directed to recover only 50% of the damages amount.
74153 293/2018 14B-7Q EPF Appeal Puliccar Mills Ltd RPFC, Salem 22/05/2024
08/08/2024
18/11/2024
25/02/2025
19/05/2025
08/08/2025
13/08/2025
(Camp)Final Order - The Appeal is partly allowed. The Respondent is directed to recover only 50% of the damages amount.
74154 293/2018 14B-7Q EPF Appeal Puliccar Mills Ltd RPFC, Salem 22/05/2024
08/08/2024
18/11/2024
25/02/2025
19/05/2025
08/08/2025
13/08/2025
(Camp)Final Order - The Appeal is partly allowed. The Respondent is directed to recover only 50% of the damages amount.
74155 293/2018 14B-7Q EPF Appeal Puliccar Mills Ltd RPFC, Salem 22/05/2024
08/08/2024
18/11/2024
25/02/2025
19/05/2025
08/08/2025
13/08/2025
(Camp)Final Order - The Appeal is partly allowed. The Respondent is directed to recover only 50% of the damages amount.
74156 293/2018 14B-7Q EPF Appeal Puliccar Mills Ltd RPFC, Salem 22/05/2024
08/08/2024
18/11/2024
25/02/2025
19/05/2025
08/08/2025
13/08/2025
(Camp)Final Order - The Appeal is partly allowed. The Respondent is directed to recover only 50% of the damages amount.
74157 293/2018 14B-7Q EPF Appeal Puliccar Mills Ltd RPFC, Salem 22/05/2024
08/08/2024
18/11/2024
25/02/2025
19/05/2025
08/08/2025
13/08/2025
(Camp)Final Order - The Appeal is partly allowed. The Respondent is directed to recover only 50% of the damages amount.
74158 254/2018 14B EPF Appeal Subramaniyasiva Co-op Sugar Mills Ltd APFC, Salem 06/02/2024
22/05/2024
08/08/2024
18/11/2024
25/02/2025
19/05/2025
08/08/2025
14/08/2025
(Camp)Final Order - The Appeal is partly allowed.
74159 254/2018 14B EPF Appeal Subramaniyasiva Co-op Sugar Mills Ltd APFC, Salem 06/02/2024
22/05/2024
08/08/2024
18/11/2024
25/02/2025
19/05/2025
08/08/2025
14/08/2025
(Camp)Final Order - The Appeal is partly allowed.
74160 254/2018 14B EPF Appeal Subramaniyasiva Co-op Sugar Mills Ltd APFC, Salem 06/02/2024
22/05/2024
08/08/2024
18/11/2024
25/02/2025
19/05/2025
08/08/2025
14/08/2025
(Camp)Final Order - The Appeal is partly allowed.
74161 254/2018 14B EPF Appeal Subramaniyasiva Co-op Sugar Mills Ltd APFC, Salem 06/02/2024
22/05/2024
08/08/2024
18/11/2024
25/02/2025
19/05/2025
08/08/2025
14/08/2025
(Camp)Final Order - The Appeal is partly allowed.
74162 254/2018 14B EPF Appeal Subramaniyasiva Co-op Sugar Mills Ltd APFC, Salem 06/02/2024
22/05/2024
08/08/2024
18/11/2024
25/02/2025
19/05/2025
08/08/2025
14/08/2025
(Camp)Final Order - The Appeal is partly allowed.
74163 254/2018 14B EPF Appeal Subramaniyasiva Co-op Sugar Mills Ltd APFC, Salem 06/02/2024
22/05/2024
08/08/2024
18/11/2024
25/02/2025
19/05/2025
08/08/2025
14/08/2025
(Camp)Final Order - The Appeal is partly allowed.
74164 254/2018 14B EPF Appeal Subramaniyasiva Co-op Sugar Mills Ltd APFC, Salem 06/02/2024
22/05/2024
08/08/2024
18/11/2024
25/02/2025
19/05/2025
08/08/2025
14/08/2025
(Camp)Final Order - The Appeal is partly allowed.
74165 254/2018 14B EPF Appeal Subramaniyasiva Co-op Sugar Mills Ltd APFC, Salem 06/02/2024
22/05/2024
08/08/2024
18/11/2024
25/02/2025
19/05/2025
08/08/2025
14/08/2025
(Camp)Final Order - The Appeal is partly allowed.
74166 263/2018 14B EPF Appeal Krishiland Matriculation High Secondary School APFC, Salem 25/08/2020
04/01/2021
08/06/2021
11/11/2021
07/03/2022
21/03/2022
Final Order - The Appeal stands dismissed.
74167 263/2018 14B EPF Appeal Krishiland Matriculation High Secondary School APFC, Salem 25/08/2020
04/01/2021
08/06/2021
11/11/2021
07/03/2022
21/03/2022
Final Order - The Appeal stands dismissed.
74168 263/2018 14B EPF Appeal Krishiland Matriculation High Secondary School APFC, Salem 25/08/2020
04/01/2021
08/06/2021
11/11/2021
07/03/2022
21/03/2022
Final Order - The Appeal stands dismissed.
74169 263/2018 14B EPF Appeal Krishiland Matriculation High Secondary School APFC, Salem 25/08/2020
04/01/2021
08/06/2021
11/11/2021
07/03/2022
21/03/2022
Final Order - The Appeal stands dismissed.
74170 263/2018 14B EPF Appeal Krishiland Matriculation High Secondary School APFC, Salem 25/08/2020
04/01/2021
08/06/2021
11/11/2021
07/03/2022
21/03/2022
Final Order - The Appeal stands dismissed.
74171 263/2018 14B EPF Appeal Krishiland Matriculation High Secondary School APFC, Salem 25/08/2020
04/01/2021
08/06/2021
11/11/2021
07/03/2022
21/03/2022
Final Order - The Appeal stands dismissed.
74172 210/2017 14B EPF Appeal The Krishnagiri Spinning Mills Ltd. RPFC, Salem 05/09/2019
20/09/2019
30/10/2019
27/01/2020
29/01/2020
Appeal is allowed in part. The Appellant is not required to deposit rest of the balance dues, since waived.
74173 210/2017 14B EPF Appeal The Krishnagiri Spinning Mills Ltd. RPFC, Salem 05/09/2019
20/09/2019
30/10/2019
27/01/2020
29/01/2020
Appeal is allowed in part. The Appellant is not required to deposit rest of the balance dues, since waived.
74174 210/2017 14B EPF Appeal The Krishnagiri Spinning Mills Ltd. RPFC, Salem 05/09/2019
20/09/2019
30/10/2019
27/01/2020
29/01/2020
Appeal is allowed in part. The Appellant is not required to deposit rest of the balance dues, since waived.
74175 210/2017 14B EPF Appeal The Krishnagiri Spinning Mills Ltd. RPFC, Salem 05/09/2019
20/09/2019
30/10/2019
27/01/2020
29/01/2020
Appeal is allowed in part. The Appellant is not required to deposit rest of the balance dues, since waived.
74176 210/2017 14B EPF Appeal The Krishnagiri Spinning Mills Ltd. RPFC, Salem 05/09/2019
20/09/2019
30/10/2019
27/01/2020
29/01/2020
Appeal is allowed in part. The Appellant is not required to deposit rest of the balance dues, since waived.
74177 239/2017 7B EPF Appeal Nagercoil Municipality APFC, Nagercoil 10/09/2021
13/01/2022
12/11/2024
12/12/2024
28/01/2025
19/03/2025
15/05/2025
02/07/2025
01/09/2025
07/11/2025
The Learned Counsel on behalf of the Appellant is present. The Learned Counsel for the Respondent prays for time. Time granted. For hearing on Arguments/filing of written submission.
74178 239/2017 7B EPF Appeal Nagercoil Municipality APFC, Nagercoil 10/09/2021
13/01/2022
12/11/2024
12/12/2024
28/01/2025
19/03/2025
15/05/2025
02/07/2025
01/09/2025
07/11/2025
The Learned Counsel on behalf of the Appellant is present. The Learned Counsel for the Respondent prays for time. Time granted. For hearing on Arguments/filing of written submission.
74179 239/2017 7B EPF Appeal Nagercoil Municipality APFC, Nagercoil 10/09/2021
13/01/2022
12/11/2024
12/12/2024
28/01/2025
19/03/2025
15/05/2025
02/07/2025
01/09/2025
07/11/2025
The Learned Counsel on behalf of the Appellant is present. The Learned Counsel for the Respondent prays for time. Time granted. For hearing on Arguments/filing of written submission.
74180 239/2017 7B EPF Appeal Nagercoil Municipality APFC, Nagercoil 10/09/2021
13/01/2022
12/11/2024
12/12/2024
28/01/2025
19/03/2025
15/05/2025
02/07/2025
01/09/2025
07/11/2025
The Learned Counsel on behalf of the Appellant is present. The Learned Counsel for the Respondent prays for time. Time granted. For hearing on Arguments/filing of written submission.
74181 239/2017 7B EPF Appeal Nagercoil Municipality APFC, Nagercoil 10/09/2021
13/01/2022
12/11/2024
12/12/2024
28/01/2025
19/03/2025
15/05/2025
02/07/2025
01/09/2025
07/11/2025
The Learned Counsel on behalf of the Appellant is present. The Learned Counsel for the Respondent prays for time. Time granted. For hearing on Arguments/filing of written submission.
74182 239/2017 7B EPF Appeal Nagercoil Municipality APFC, Nagercoil 10/09/2021
13/01/2022
12/11/2024
12/12/2024
28/01/2025
19/03/2025
15/05/2025
02/07/2025
01/09/2025
07/11/2025
The Learned Counsel on behalf of the Appellant is present. The Learned Counsel for the Respondent prays for time. Time granted. For hearing on Arguments/filing of written submission.
74183 239/2017 7B EPF Appeal Nagercoil Municipality APFC, Nagercoil 10/09/2021
13/01/2022
12/11/2024
12/12/2024
28/01/2025
19/03/2025
15/05/2025
02/07/2025
01/09/2025
07/11/2025
The Learned Counsel on behalf of the Appellant is present. The Learned Counsel for the Respondent prays for time. Time granted. For hearing on Arguments/filing of written submission.
74184 239/2017 7B EPF Appeal Nagercoil Municipality APFC, Nagercoil 10/09/2021
13/01/2022
12/11/2024
12/12/2024
28/01/2025
19/03/2025
15/05/2025
02/07/2025
01/09/2025
07/11/2025
The Learned Counsel on behalf of the Appellant is present. The Learned Counsel for the Respondent prays for time. Time granted. For hearing on Arguments/filing of written submission.
74185 239/2017 7B EPF Appeal Nagercoil Municipality APFC, Nagercoil 10/09/2021
13/01/2022
12/11/2024
12/12/2024
28/01/2025
19/03/2025
15/05/2025
02/07/2025
01/09/2025
07/11/2025
The Learned Counsel on behalf of the Appellant is present. The Learned Counsel for the Respondent prays for time. Time granted. For hearing on Arguments/filing of written submission.
74186 239/2017 7B EPF Appeal Nagercoil Municipality APFC, Nagercoil 10/09/2021
13/01/2022
12/11/2024
12/12/2024
28/01/2025
19/03/2025
15/05/2025
02/07/2025
01/09/2025
07/11/2025
The Learned Counsel on behalf of the Appellant is present. The Learned Counsel for the Respondent prays for time. Time granted. For hearing on Arguments/filing of written submission.
74187 563/2018 14B EPF Appeal Bishiop Heber College APFC, Tiruchirappalli 04/04/2019 Admission
74188 529/2018 7Q EPF Appeal Bishop Heber College APFC, Trichirappalli 04/04/2019 Admission
74189 673/2018 14B EPF Appeal The Bharathi Co-operative Spinning Mills Ltd. RPFC - I, Tirunelveli 20/06/2024
07/10/2024
06/01/2025
07/04/2025
07/07/2025
02/09/2025
26/11/2025
The Counsel for the Appellant filed petition for adjournment. Petition allowed. The Learned Counsel on behalf of the Respondent is present. List to 26.11.2025 for hearing on Arguments/filing of written submission.
74190 673/2018 14B EPF Appeal The Bharathi Co-operative Spinning Mills Ltd. RPFC - I, Tirunelveli 20/06/2024
07/10/2024
06/01/2025
07/04/2025
07/07/2025
02/09/2025
26/11/2025
The Counsel for the Appellant filed petition for adjournment. Petition allowed. The Learned Counsel on behalf of the Respondent is present. List to 26.11.2025 for hearing on Arguments/filing of written submission.
74191 673/2018 14B EPF Appeal The Bharathi Co-operative Spinning Mills Ltd. RPFC - I, Tirunelveli 20/06/2024
07/10/2024
06/01/2025
07/04/2025
07/07/2025
02/09/2025
26/11/2025
The Counsel for the Appellant filed petition for adjournment. Petition allowed. The Learned Counsel on behalf of the Respondent is present. List to 26.11.2025 for hearing on Arguments/filing of written submission.
74192 673/2018 14B EPF Appeal The Bharathi Co-operative Spinning Mills Ltd. RPFC - I, Tirunelveli 20/06/2024
07/10/2024
06/01/2025
07/04/2025
07/07/2025
02/09/2025
26/11/2025
The Counsel for the Appellant filed petition for adjournment. Petition allowed. The Learned Counsel on behalf of the Respondent is present. List to 26.11.2025 for hearing on Arguments/filing of written submission.
74193 673/2018 14B EPF Appeal The Bharathi Co-operative Spinning Mills Ltd. RPFC - I, Tirunelveli 20/06/2024
07/10/2024
06/01/2025
07/04/2025
07/07/2025
02/09/2025
26/11/2025
The Counsel for the Appellant filed petition for adjournment. Petition allowed. The Learned Counsel on behalf of the Respondent is present. List to 26.11.2025 for hearing on Arguments/filing of written submission.
74194 673/2018 14B EPF Appeal The Bharathi Co-operative Spinning Mills Ltd. RPFC - I, Tirunelveli 20/06/2024
07/10/2024
06/01/2025
07/04/2025
07/07/2025
02/09/2025
26/11/2025
The Counsel for the Appellant filed petition for adjournment. Petition allowed. The Learned Counsel on behalf of the Respondent is present. List to 26.11.2025 for hearing on Arguments/filing of written submission.
74195 673/2018 14B EPF Appeal The Bharathi Co-operative Spinning Mills Ltd. RPFC - I, Tirunelveli 20/06/2024
07/10/2024
06/01/2025
07/04/2025
07/07/2025
02/09/2025
26/11/2025
The Counsel for the Appellant filed petition for adjournment. Petition allowed. The Learned Counsel on behalf of the Respondent is present. List to 26.11.2025 for hearing on Arguments/filing of written submission.
74196 105/2018 14B EPF Appeal Sahayamatha Salt Refinery APFC, Tirunelveli 03/12/2024
08/01/2025
03/03/2025
30/04/2025
18/06/2025
01/07/2025
31/07/2025
Final Order - The Appeal is partly allowed.
74197 105/2018 14B EPF Appeal Sahayamatha Salt Refinery APFC, Tirunelveli 03/12/2024
08/01/2025
03/03/2025
30/04/2025
18/06/2025
01/07/2025
31/07/2025
Final Order - The Appeal is partly allowed.
74198 105/2018 14B EPF Appeal Sahayamatha Salt Refinery APFC, Tirunelveli 03/12/2024
08/01/2025
03/03/2025
30/04/2025
18/06/2025
01/07/2025
31/07/2025
Final Order - The Appeal is partly allowed.
74199 105/2018 14B EPF Appeal Sahayamatha Salt Refinery APFC, Tirunelveli 03/12/2024
08/01/2025
03/03/2025
30/04/2025
18/06/2025
01/07/2025
31/07/2025
Final Order - The Appeal is partly allowed.
74200 105/2018 14B EPF Appeal Sahayamatha Salt Refinery APFC, Tirunelveli 03/12/2024
08/01/2025
03/03/2025
30/04/2025
18/06/2025
01/07/2025
31/07/2025
Final Order - The Appeal is partly allowed.