Cause List

E.g., 05/04/2026
S.No. Case No. Subject Case Type Name of Appellant Respondent Next Date Details Order / Decision Edit
64751 132/2017 14B EPF Appeal Radha Krishna Mills Ltd. APFC, Coimbatore 10/09/2024
10/12/2024
13/02/2025
08/05/2025
06/08/2025
15/10/2025
16/01/2026
16/04/2026
None appeared on behalf of the Appellant. The Counsel on behalf of the Respondent is present. List to 16.04.2026 for hearing on Arguments/filing of written submission.
64752 132/2017 14B EPF Appeal Radha Krishna Mills Ltd. APFC, Coimbatore 10/09/2024
10/12/2024
13/02/2025
08/05/2025
06/08/2025
15/10/2025
16/01/2026
16/04/2026
None appeared on behalf of the Appellant. The Counsel on behalf of the Respondent is present. List to 16.04.2026 for hearing on Arguments/filing of written submission.
64753 132/2017 14B EPF Appeal Radha Krishna Mills Ltd. APFC, Coimbatore 10/09/2024
10/12/2024
13/02/2025
08/05/2025
06/08/2025
15/10/2025
16/01/2026
16/04/2026
None appeared on behalf of the Appellant. The Counsel on behalf of the Respondent is present. List to 16.04.2026 for hearing on Arguments/filing of written submission.
64754 132/2017 14B EPF Appeal Radha Krishna Mills Ltd. APFC, Coimbatore 10/09/2024
10/12/2024
13/02/2025
08/05/2025
06/08/2025
15/10/2025
16/01/2026
16/04/2026
None appeared on behalf of the Appellant. The Counsel on behalf of the Respondent is present. List to 16.04.2026 for hearing on Arguments/filing of written submission.
64755 132/2017 14B EPF Appeal Radha Krishna Mills Ltd. APFC, Coimbatore 10/09/2024
10/12/2024
13/02/2025
08/05/2025
06/08/2025
15/10/2025
16/01/2026
16/04/2026
None appeared on behalf of the Appellant. The Counsel on behalf of the Respondent is present. List to 16.04.2026 for hearing on Arguments/filing of written submission.
64756 149/2017 7Q EPF Appeal Radha Krishna Mills Ltd. APFC, Coimbatore 04/03/2025
02/05/2025
20/06/2025
13/08/2025
24/10/2025
16/02/2026
Final Order - The Appeal stands dismissed for want of prosecution.
64757 149/2017 7Q EPF Appeal Radha Krishna Mills Ltd. APFC, Coimbatore 04/03/2025
02/05/2025
20/06/2025
13/08/2025
24/10/2025
16/02/2026
Final Order - The Appeal stands dismissed for want of prosecution.
64758 149/2017 7Q EPF Appeal Radha Krishna Mills Ltd. APFC, Coimbatore 04/03/2025
02/05/2025
20/06/2025
13/08/2025
24/10/2025
16/02/2026
Final Order - The Appeal stands dismissed for want of prosecution.
64759 149/2017 7Q EPF Appeal Radha Krishna Mills Ltd. APFC, Coimbatore 04/03/2025
02/05/2025
20/06/2025
13/08/2025
24/10/2025
16/02/2026
Final Order - The Appeal stands dismissed for want of prosecution.
64760 149/2017 7Q EPF Appeal Radha Krishna Mills Ltd. APFC, Coimbatore 04/03/2025
02/05/2025
20/06/2025
13/08/2025
24/10/2025
16/02/2026
Final Order - The Appeal stands dismissed for want of prosecution.
64761 149/2017 7Q EPF Appeal Radha Krishna Mills Ltd. APFC, Coimbatore 04/03/2025
02/05/2025
20/06/2025
13/08/2025
24/10/2025
16/02/2026
Final Order - The Appeal stands dismissed for want of prosecution.
64762 CGIT/LC/EPFA/93/2017 SECTION-7A EPF Appeal ROCA BATHROOM PRODUCT APFC, INDORE 03/09/2025
13/01/2026
18/02/2026
04/05/2026
FOR ARGUMENT Download, Download, Download, Download, Download, Download
64763 CGIT/LC/EPFA/93/2017 SECTION-7A EPF Appeal ROCA BATHROOM PRODUCT APFC, INDORE 03/09/2025
13/01/2026
18/02/2026
04/05/2026
FOR ARGUMENT Download, Download, Download, Download, Download, Download
64764 CGIT/LC/EPFA/93/2017 SECTION-7A EPF Appeal ROCA BATHROOM PRODUCT APFC, INDORE 03/09/2025
13/01/2026
18/02/2026
04/05/2026
FOR ARGUMENT Download, Download, Download, Download, Download, Download
64765 CGIT/LC/EPFA/93/2017 SECTION-7A EPF Appeal ROCA BATHROOM PRODUCT APFC, INDORE 03/09/2025
13/01/2026
18/02/2026
04/05/2026
FOR ARGUMENT Download, Download, Download, Download, Download, Download
64766 285/2018 7A EPF Appeal Carolyn Estate RPFC, Coimbatore 10/12/2024
13/02/2025
08/05/2025
06/08/2025
15/10/2025
16/01/2026
16/04/2026
The Counsel on behalf of the Appellant prays time for Arguments. Time granted. The learned Counsel on behalf of the Respondent is present. List to 16.04.2026 for hearing on Arguments/filing of written submission.
64767 285/2018 7A EPF Appeal Carolyn Estate RPFC, Coimbatore 10/12/2024
13/02/2025
08/05/2025
06/08/2025
15/10/2025
16/01/2026
16/04/2026
The Counsel on behalf of the Appellant prays time for Arguments. Time granted. The learned Counsel on behalf of the Respondent is present. List to 16.04.2026 for hearing on Arguments/filing of written submission.
64768 285/2018 7A EPF Appeal Carolyn Estate RPFC, Coimbatore 10/12/2024
13/02/2025
08/05/2025
06/08/2025
15/10/2025
16/01/2026
16/04/2026
The Counsel on behalf of the Appellant prays time for Arguments. Time granted. The learned Counsel on behalf of the Respondent is present. List to 16.04.2026 for hearing on Arguments/filing of written submission.
64769 285/2018 7A EPF Appeal Carolyn Estate RPFC, Coimbatore 10/12/2024
13/02/2025
08/05/2025
06/08/2025
15/10/2025
16/01/2026
16/04/2026
The Counsel on behalf of the Appellant prays time for Arguments. Time granted. The learned Counsel on behalf of the Respondent is present. List to 16.04.2026 for hearing on Arguments/filing of written submission.
64770 285/2018 7A EPF Appeal Carolyn Estate RPFC, Coimbatore 10/12/2024
13/02/2025
08/05/2025
06/08/2025
15/10/2025
16/01/2026
16/04/2026
The Counsel on behalf of the Appellant prays time for Arguments. Time granted. The learned Counsel on behalf of the Respondent is present. List to 16.04.2026 for hearing on Arguments/filing of written submission.
64771 285/2018 7A EPF Appeal Carolyn Estate RPFC, Coimbatore 10/12/2024
13/02/2025
08/05/2025
06/08/2025
15/10/2025
16/01/2026
16/04/2026
The Counsel on behalf of the Appellant prays time for Arguments. Time granted. The learned Counsel on behalf of the Respondent is present. List to 16.04.2026 for hearing on Arguments/filing of written submission.
64772 285/2018 7A EPF Appeal Carolyn Estate RPFC, Coimbatore 10/12/2024
13/02/2025
08/05/2025
06/08/2025
15/10/2025
16/01/2026
16/04/2026
The Counsel on behalf of the Appellant prays time for Arguments. Time granted. The learned Counsel on behalf of the Respondent is present. List to 16.04.2026 for hearing on Arguments/filing of written submission.
64773 599/2018 14B EPF Appeal Niranjan Enterprises APFC, Coimbatore 03/02/2025
02/04/2025
28/05/2025
16/07/2025
12/09/2025
26/12/2025
25/02/2026
(Special Campaign) Final Order - Waived 30% of assessed amount passed by Respondent order dtd 09.02.2018. Respondent will recover remaining 70% of assessed amount from Appellant in accordance with law
64774 599/2018 14B EPF Appeal Niranjan Enterprises APFC, Coimbatore 03/02/2025
02/04/2025
28/05/2025
16/07/2025
12/09/2025
26/12/2025
25/02/2026
(Special Campaign) Final Order - Waived 30% of assessed amount passed by Respondent order dtd 09.02.2018. Respondent will recover remaining 70% of assessed amount from Appellant in accordance with law
64775 599/2018 14B EPF Appeal Niranjan Enterprises APFC, Coimbatore 03/02/2025
02/04/2025
28/05/2025
16/07/2025
12/09/2025
26/12/2025
25/02/2026
(Special Campaign) Final Order - Waived 30% of assessed amount passed by Respondent order dtd 09.02.2018. Respondent will recover remaining 70% of assessed amount from Appellant in accordance with law
64776 599/2018 14B EPF Appeal Niranjan Enterprises APFC, Coimbatore 03/02/2025
02/04/2025
28/05/2025
16/07/2025
12/09/2025
26/12/2025
25/02/2026
(Special Campaign) Final Order - Waived 30% of assessed amount passed by Respondent order dtd 09.02.2018. Respondent will recover remaining 70% of assessed amount from Appellant in accordance with law
64777 599/2018 14B EPF Appeal Niranjan Enterprises APFC, Coimbatore 03/02/2025
02/04/2025
28/05/2025
16/07/2025
12/09/2025
26/12/2025
25/02/2026
(Special Campaign) Final Order - Waived 30% of assessed amount passed by Respondent order dtd 09.02.2018. Respondent will recover remaining 70% of assessed amount from Appellant in accordance with law
64778 599/2018 14B EPF Appeal Niranjan Enterprises APFC, Coimbatore 03/02/2025
02/04/2025
28/05/2025
16/07/2025
12/09/2025
26/12/2025
25/02/2026
(Special Campaign) Final Order - Waived 30% of assessed amount passed by Respondent order dtd 09.02.2018. Respondent will recover remaining 70% of assessed amount from Appellant in accordance with law
64779 599/2018 14B EPF Appeal Niranjan Enterprises APFC, Coimbatore 03/02/2025
02/04/2025
28/05/2025
16/07/2025
12/09/2025
26/12/2025
25/02/2026
(Special Campaign) Final Order - Waived 30% of assessed amount passed by Respondent order dtd 09.02.2018. Respondent will recover remaining 70% of assessed amount from Appellant in accordance with law
64780 612/2018 14B EPF Appeal Palani Andavar Cotton & Synthetic Spinners Ltd. APFC, Coimbatore 30/12/2024
28/03/2025
27/06/2025
28/08/2025
21/11/2025
06/02/2026
(Special Campaign) Final Order - The Appeal is partly allowed. 30% of the assessed amount is waived off. The Respondent is directed to recover only 70% of the assessed amount of damages u/s. 14B of the Act.
64781 612/2018 14B EPF Appeal Palani Andavar Cotton & Synthetic Spinners Ltd. APFC, Coimbatore 30/12/2024
28/03/2025
27/06/2025
28/08/2025
21/11/2025
06/02/2026
(Special Campaign) Final Order - The Appeal is partly allowed. 30% of the assessed amount is waived off. The Respondent is directed to recover only 70% of the assessed amount of damages u/s. 14B of the Act.
64782 612/2018 14B EPF Appeal Palani Andavar Cotton & Synthetic Spinners Ltd. APFC, Coimbatore 30/12/2024
28/03/2025
27/06/2025
28/08/2025
21/11/2025
06/02/2026
(Special Campaign) Final Order - The Appeal is partly allowed. 30% of the assessed amount is waived off. The Respondent is directed to recover only 70% of the assessed amount of damages u/s. 14B of the Act.
64783 612/2018 14B EPF Appeal Palani Andavar Cotton & Synthetic Spinners Ltd. APFC, Coimbatore 30/12/2024
28/03/2025
27/06/2025
28/08/2025
21/11/2025
06/02/2026
(Special Campaign) Final Order - The Appeal is partly allowed. 30% of the assessed amount is waived off. The Respondent is directed to recover only 70% of the assessed amount of damages u/s. 14B of the Act.
64784 612/2018 14B EPF Appeal Palani Andavar Cotton & Synthetic Spinners Ltd. APFC, Coimbatore 30/12/2024
28/03/2025
27/06/2025
28/08/2025
21/11/2025
06/02/2026
(Special Campaign) Final Order - The Appeal is partly allowed. 30% of the assessed amount is waived off. The Respondent is directed to recover only 70% of the assessed amount of damages u/s. 14B of the Act.
64785 612/2018 14B EPF Appeal Palani Andavar Cotton & Synthetic Spinners Ltd. APFC, Coimbatore 30/12/2024
28/03/2025
27/06/2025
28/08/2025
21/11/2025
06/02/2026
(Special Campaign) Final Order - The Appeal is partly allowed. 30% of the assessed amount is waived off. The Respondent is directed to recover only 70% of the assessed amount of damages u/s. 14B of the Act.
64786 CGIT/LC/EPFA/91/2017 SECTION-7A EPF Appeal SACHIDANAND STEEL SALES INDIA PVT.LTD. APFC, INDORE 02/09/2021
26/10/2021
DISMISS Download, Download
64787 CGIT/LC/EPFA/91/2017 SECTION-7A EPF Appeal SACHIDANAND STEEL SALES INDIA PVT.LTD. APFC, INDORE 02/09/2021
26/10/2021
DISMISS Download, Download
64788 620/2018 14B EPF Appeal Cotton Blossom (India) Pvt. Ltd. RPFC, Coimbatore 30/12/2024
28/03/2025
27/06/2025
28/08/2025
21/11/2025
25/02/2026
(Special Campaign) Final Order - Waived 35% of assessed amount passed by Respondent order dtd 27.04.2018. Respondent will recover remaining 65% of assessed amount from Appellant in accordance with law
64789 620/2018 14B EPF Appeal Cotton Blossom (India) Pvt. Ltd. RPFC, Coimbatore 30/12/2024
28/03/2025
27/06/2025
28/08/2025
21/11/2025
25/02/2026
(Special Campaign) Final Order - Waived 35% of assessed amount passed by Respondent order dtd 27.04.2018. Respondent will recover remaining 65% of assessed amount from Appellant in accordance with law
64790 620/2018 14B EPF Appeal Cotton Blossom (India) Pvt. Ltd. RPFC, Coimbatore 30/12/2024
28/03/2025
27/06/2025
28/08/2025
21/11/2025
25/02/2026
(Special Campaign) Final Order - Waived 35% of assessed amount passed by Respondent order dtd 27.04.2018. Respondent will recover remaining 65% of assessed amount from Appellant in accordance with law
64791 620/2018 14B EPF Appeal Cotton Blossom (India) Pvt. Ltd. RPFC, Coimbatore 30/12/2024
28/03/2025
27/06/2025
28/08/2025
21/11/2025
25/02/2026
(Special Campaign) Final Order - Waived 35% of assessed amount passed by Respondent order dtd 27.04.2018. Respondent will recover remaining 65% of assessed amount from Appellant in accordance with law
64792 620/2018 14B EPF Appeal Cotton Blossom (India) Pvt. Ltd. RPFC, Coimbatore 30/12/2024
28/03/2025
27/06/2025
28/08/2025
21/11/2025
25/02/2026
(Special Campaign) Final Order - Waived 35% of assessed amount passed by Respondent order dtd 27.04.2018. Respondent will recover remaining 65% of assessed amount from Appellant in accordance with law
64793 620/2018 14B EPF Appeal Cotton Blossom (India) Pvt. Ltd. RPFC, Coimbatore 30/12/2024
28/03/2025
27/06/2025
28/08/2025
21/11/2025
25/02/2026
(Special Campaign) Final Order - Waived 35% of assessed amount passed by Respondent order dtd 27.04.2018. Respondent will recover remaining 65% of assessed amount from Appellant in accordance with law
64794 654/2018 14B EPF Appeal Universal Heat Exchangers Ltd. APFC, Coimbatore 24/04/2024
24/07/2024
04/11/2024
10/02/2025
05/05/2025
25/07/2025
25/09/2025
01/01/2026
04/02/2026
(Special Campaign) Final Order - The Appeal is partly allowed. 30% of the assessed amount is waived off. The Respondent is directed to recover only 70% of the assessed amount of damages u/s. 14B of the Act.
64795 654/2018 14B EPF Appeal Universal Heat Exchangers Ltd. APFC, Coimbatore 24/04/2024
24/07/2024
04/11/2024
10/02/2025
05/05/2025
25/07/2025
25/09/2025
01/01/2026
04/02/2026
(Special Campaign) Final Order - The Appeal is partly allowed. 30% of the assessed amount is waived off. The Respondent is directed to recover only 70% of the assessed amount of damages u/s. 14B of the Act.
64796 654/2018 14B EPF Appeal Universal Heat Exchangers Ltd. APFC, Coimbatore 24/04/2024
24/07/2024
04/11/2024
10/02/2025
05/05/2025
25/07/2025
25/09/2025
01/01/2026
04/02/2026
(Special Campaign) Final Order - The Appeal is partly allowed. 30% of the assessed amount is waived off. The Respondent is directed to recover only 70% of the assessed amount of damages u/s. 14B of the Act.
64797 654/2018 14B EPF Appeal Universal Heat Exchangers Ltd. APFC, Coimbatore 24/04/2024
24/07/2024
04/11/2024
10/02/2025
05/05/2025
25/07/2025
25/09/2025
01/01/2026
04/02/2026
(Special Campaign) Final Order - The Appeal is partly allowed. 30% of the assessed amount is waived off. The Respondent is directed to recover only 70% of the assessed amount of damages u/s. 14B of the Act.
64798 654/2018 14B EPF Appeal Universal Heat Exchangers Ltd. APFC, Coimbatore 24/04/2024
24/07/2024
04/11/2024
10/02/2025
05/05/2025
25/07/2025
25/09/2025
01/01/2026
04/02/2026
(Special Campaign) Final Order - The Appeal is partly allowed. 30% of the assessed amount is waived off. The Respondent is directed to recover only 70% of the assessed amount of damages u/s. 14B of the Act.
64799 654/2018 14B EPF Appeal Universal Heat Exchangers Ltd. APFC, Coimbatore 24/04/2024
24/07/2024
04/11/2024
10/02/2025
05/05/2025
25/07/2025
25/09/2025
01/01/2026
04/02/2026
(Special Campaign) Final Order - The Appeal is partly allowed. 30% of the assessed amount is waived off. The Respondent is directed to recover only 70% of the assessed amount of damages u/s. 14B of the Act.
64800 654/2018 14B EPF Appeal Universal Heat Exchangers Ltd. APFC, Coimbatore 24/04/2024
24/07/2024
04/11/2024
10/02/2025
05/05/2025
25/07/2025
25/09/2025
01/01/2026
04/02/2026
(Special Campaign) Final Order - The Appeal is partly allowed. 30% of the assessed amount is waived off. The Respondent is directed to recover only 70% of the assessed amount of damages u/s. 14B of the Act.

Pages