| S.No. | Case No. | Subject | Case Type | Name of Appellant | Respondent | Next Date | Details | Order / Decision | Edit |
|---|---|---|---|---|---|---|---|---|---|
| 52601 | 7/14-15 | 21/11/2019 | ID | Ravi Kumar & others | Western Coalfield Limited |
22/08/2024 06/11/2024 06/03/2025 03/06/2025 17/10/2025 30/03/2026 04/08/2026 |
W.S and document | ||
| 52602 | EPFA/43/2018-2019 | 20/11/2019 | EPF Appeal | Shri Sant Muktabai Institute of Technology, Jalgaon | APFC NASIK |
19/12/2023 01/04/2024 03/07/2024 18/09/2024 10/12/2024 18/06/2025 26/11/2025 13/05/2026 23/09/2026 |
Reply by the Respondent | ||
| 52603 | EPFA/43/2018-2019 | 20/11/2019 | EPF Appeal | Shri Sant Muktabai Institute of Technology, Jalgaon | APFC NASIK |
19/12/2023 01/04/2024 03/07/2024 18/09/2024 10/12/2024 18/06/2025 26/11/2025 13/05/2026 23/09/2026 |
Reply by the Respondent | ||
| 52604 | EPFA/43/2018-2019 | 20/11/2019 | EPF Appeal | Shri Sant Muktabai Institute of Technology, Jalgaon | APFC NASIK |
19/12/2023 01/04/2024 03/07/2024 18/09/2024 10/12/2024 18/06/2025 26/11/2025 13/05/2026 23/09/2026 |
Reply by the Respondent | ||
| 52605 | EPFA/43/2018-2019 | 20/11/2019 | EPF Appeal | Shri Sant Muktabai Institute of Technology, Jalgaon | APFC NASIK |
19/12/2023 01/04/2024 03/07/2024 18/09/2024 10/12/2024 18/06/2025 26/11/2025 13/05/2026 23/09/2026 |
Reply by the Respondent | ||
| 52606 | EPFA/43/2018-2019 | 20/11/2019 | EPF Appeal | Shri Sant Muktabai Institute of Technology, Jalgaon | APFC NASIK |
19/12/2023 01/04/2024 03/07/2024 18/09/2024 10/12/2024 18/06/2025 26/11/2025 13/05/2026 23/09/2026 |
Reply by the Respondent | ||
| 52607 | EPFA/43/2018-2019 | 20/11/2019 | EPF Appeal | Shri Sant Muktabai Institute of Technology, Jalgaon | APFC NASIK |
19/12/2023 01/04/2024 03/07/2024 18/09/2024 10/12/2024 18/06/2025 26/11/2025 13/05/2026 23/09/2026 |
Reply by the Respondent | ||
| 52608 | EPFA/43/2018-2019 | 20/11/2019 | EPF Appeal | Shri Sant Muktabai Institute of Technology, Jalgaon | APFC NASIK |
19/12/2023 01/04/2024 03/07/2024 18/09/2024 10/12/2024 18/06/2025 26/11/2025 13/05/2026 23/09/2026 |
Reply by the Respondent | ||
| 52609 | EPFA/43/2018-2019 | 20/11/2019 | EPF Appeal | Shri Sant Muktabai Institute of Technology, Jalgaon | APFC NASIK |
19/12/2023 01/04/2024 03/07/2024 18/09/2024 10/12/2024 18/06/2025 26/11/2025 13/05/2026 23/09/2026 |
Reply by the Respondent | ||
| 52610 | EPFA/43/2018-2019 | 20/11/2019 | EPF Appeal | Shri Sant Muktabai Institute of Technology, Jalgaon | APFC NASIK |
19/12/2023 01/04/2024 03/07/2024 18/09/2024 10/12/2024 18/06/2025 26/11/2025 13/05/2026 23/09/2026 |
Reply by the Respondent | ||
| 52611 | Ref. No. 35/2019 | Wage Protection and Payment of SPRA | ID | Shri Jipu Nunia | New Kenda Colliery of M/s. ECL | Award Passed | |||
| 52612 | CGIT-2/EPFA/121 of 2019 | EPFA | EPF Appeal | Acropolis Purple Developers | RPFC, EPFO, Pune |
29/09/2025 02/02/2026 25/05/2026 08/09/2026 |
Final Arguments | ||
| 52613 | CGIT-2/EPFA/121 of 2019 | EPFA | EPF Appeal | Acropolis Purple Developers | RPFC, EPFO, Pune |
29/09/2025 02/02/2026 25/05/2026 08/09/2026 |
Final Arguments | ||
| 52614 | CGIT-2/EPFA/121 of 2019 | EPFA | EPF Appeal | Acropolis Purple Developers | RPFC, EPFO, Pune |
29/09/2025 02/02/2026 25/05/2026 08/09/2026 |
Final Arguments | ||
| 52615 | CGIT-2/EPFA/121 of 2019 | EPFA | EPF Appeal | Acropolis Purple Developers | RPFC, EPFO, Pune |
29/09/2025 02/02/2026 25/05/2026 08/09/2026 |
Final Arguments | ||
| 52616 | CR 27/2016 | Special Process Allowance | ID | Karumbaiah and others | H A L | 23/07/2026 | Evidence II | ||
| 52617 | 646/2018 | 14B | EPF Appeal | AJC English School & Junior College | APFC, Trichy |
09/09/2024 09/12/2024 21/01/2025 23/04/2025 23/07/2025 19/09/2025 11/12/2025 18/03/2026 |
Final Order - Waived 37% of assessed amount passed by Respondent order dtd 13.04.2018. Respondent will recover remaining 63% of assessed amount from Appellant in accordance with law | ||
| 52618 | 646/2018 | 14B | EPF Appeal | AJC English School & Junior College | APFC, Trichy |
09/09/2024 09/12/2024 21/01/2025 23/04/2025 23/07/2025 19/09/2025 11/12/2025 18/03/2026 |
Final Order - Waived 37% of assessed amount passed by Respondent order dtd 13.04.2018. Respondent will recover remaining 63% of assessed amount from Appellant in accordance with law | ||
| 52619 | 646/2018 | 14B | EPF Appeal | AJC English School & Junior College | APFC, Trichy |
09/09/2024 09/12/2024 21/01/2025 23/04/2025 23/07/2025 19/09/2025 11/12/2025 18/03/2026 |
Final Order - Waived 37% of assessed amount passed by Respondent order dtd 13.04.2018. Respondent will recover remaining 63% of assessed amount from Appellant in accordance with law | ||
| 52620 | 646/2018 | 14B | EPF Appeal | AJC English School & Junior College | APFC, Trichy |
09/09/2024 09/12/2024 21/01/2025 23/04/2025 23/07/2025 19/09/2025 11/12/2025 18/03/2026 |
Final Order - Waived 37% of assessed amount passed by Respondent order dtd 13.04.2018. Respondent will recover remaining 63% of assessed amount from Appellant in accordance with law | ||
| 52621 | 646/2018 | 14B | EPF Appeal | AJC English School & Junior College | APFC, Trichy |
09/09/2024 09/12/2024 21/01/2025 23/04/2025 23/07/2025 19/09/2025 11/12/2025 18/03/2026 |
Final Order - Waived 37% of assessed amount passed by Respondent order dtd 13.04.2018. Respondent will recover remaining 63% of assessed amount from Appellant in accordance with law | ||
| 52622 | 646/2018 | 14B | EPF Appeal | AJC English School & Junior College | APFC, Trichy |
09/09/2024 09/12/2024 21/01/2025 23/04/2025 23/07/2025 19/09/2025 11/12/2025 18/03/2026 |
Final Order - Waived 37% of assessed amount passed by Respondent order dtd 13.04.2018. Respondent will recover remaining 63% of assessed amount from Appellant in accordance with law | ||
| 52623 | 646/2018 | 14B | EPF Appeal | AJC English School & Junior College | APFC, Trichy |
09/09/2024 09/12/2024 21/01/2025 23/04/2025 23/07/2025 19/09/2025 11/12/2025 18/03/2026 |
Final Order - Waived 37% of assessed amount passed by Respondent order dtd 13.04.2018. Respondent will recover remaining 63% of assessed amount from Appellant in accordance with law | ||
| 52624 | 646/2018 | 14B | EPF Appeal | AJC English School & Junior College | APFC, Trichy |
09/09/2024 09/12/2024 21/01/2025 23/04/2025 23/07/2025 19/09/2025 11/12/2025 18/03/2026 |
Final Order - Waived 37% of assessed amount passed by Respondent order dtd 13.04.2018. Respondent will recover remaining 63% of assessed amount from Appellant in accordance with law | ||
| 52625 | 419/2018 | 14B | EPF Appeal | Vignesh Leather Company | APFC, Trichy |
03/06/2024 09/09/2024 09/12/2024 21/01/2025 23/04/2025 22/07/2025 17/09/2025 10/10/2025 |
Final Order - The Appeal is partly allowed. The Respondent is directed to recover only 70% of assessed damages amount. | ||
| 52626 | 419/2018 | 14B | EPF Appeal | Vignesh Leather Company | APFC, Trichy |
03/06/2024 09/09/2024 09/12/2024 21/01/2025 23/04/2025 22/07/2025 17/09/2025 10/10/2025 |
Final Order - The Appeal is partly allowed. The Respondent is directed to recover only 70% of assessed damages amount. | ||
| 52627 | 419/2018 | 14B | EPF Appeal | Vignesh Leather Company | APFC, Trichy |
03/06/2024 09/09/2024 09/12/2024 21/01/2025 23/04/2025 22/07/2025 17/09/2025 10/10/2025 |
Final Order - The Appeal is partly allowed. The Respondent is directed to recover only 70% of assessed damages amount. | ||
| 52628 | 419/2018 | 14B | EPF Appeal | Vignesh Leather Company | APFC, Trichy |
03/06/2024 09/09/2024 09/12/2024 21/01/2025 23/04/2025 22/07/2025 17/09/2025 10/10/2025 |
Final Order - The Appeal is partly allowed. The Respondent is directed to recover only 70% of assessed damages amount. | ||
| 52629 | 419/2018 | 14B | EPF Appeal | Vignesh Leather Company | APFC, Trichy |
03/06/2024 09/09/2024 09/12/2024 21/01/2025 23/04/2025 22/07/2025 17/09/2025 10/10/2025 |
Final Order - The Appeal is partly allowed. The Respondent is directed to recover only 70% of assessed damages amount. | ||
| 52630 | 419/2018 | 14B | EPF Appeal | Vignesh Leather Company | APFC, Trichy |
03/06/2024 09/09/2024 09/12/2024 21/01/2025 23/04/2025 22/07/2025 17/09/2025 10/10/2025 |
Final Order - The Appeal is partly allowed. The Respondent is directed to recover only 70% of assessed damages amount. | ||
| 52631 | 419/2018 | 14B | EPF Appeal | Vignesh Leather Company | APFC, Trichy |
03/06/2024 09/09/2024 09/12/2024 21/01/2025 23/04/2025 22/07/2025 17/09/2025 10/10/2025 |
Final Order - The Appeal is partly allowed. The Respondent is directed to recover only 70% of assessed damages amount. | ||
| 52632 | 419/2018 | 14B | EPF Appeal | Vignesh Leather Company | APFC, Trichy |
03/06/2024 09/09/2024 09/12/2024 21/01/2025 23/04/2025 22/07/2025 17/09/2025 10/10/2025 |
Final Order - The Appeal is partly allowed. The Respondent is directed to recover only 70% of assessed damages amount. | ||
| 52633 | 418/2018 | 14B | EPF Appeal | Sri Kanchi Sankara | APFC, Trichy |
06/08/2024 07/11/2024 13/02/2025 08/05/2025 06/08/2025 15/10/2025 16/01/2026 16/04/2026 |
Final Order - 32% of the assessed amount passed by the Respondent order dated 23.12.2015 is waived. The Respondent will recover remaining 68% of the assessed amount from the Appellant establishment in accordance with law. | ||
| 52634 | 418/2018 | 14B | EPF Appeal | Sri Kanchi Sankara | APFC, Trichy |
06/08/2024 07/11/2024 13/02/2025 08/05/2025 06/08/2025 15/10/2025 16/01/2026 16/04/2026 |
Final Order - 32% of the assessed amount passed by the Respondent order dated 23.12.2015 is waived. The Respondent will recover remaining 68% of the assessed amount from the Appellant establishment in accordance with law. | ||
| 52635 | 418/2018 | 14B | EPF Appeal | Sri Kanchi Sankara | APFC, Trichy |
06/08/2024 07/11/2024 13/02/2025 08/05/2025 06/08/2025 15/10/2025 16/01/2026 16/04/2026 |
Final Order - 32% of the assessed amount passed by the Respondent order dated 23.12.2015 is waived. The Respondent will recover remaining 68% of the assessed amount from the Appellant establishment in accordance with law. | ||
| 52636 | 418/2018 | 14B | EPF Appeal | Sri Kanchi Sankara | APFC, Trichy |
06/08/2024 07/11/2024 13/02/2025 08/05/2025 06/08/2025 15/10/2025 16/01/2026 16/04/2026 |
Final Order - 32% of the assessed amount passed by the Respondent order dated 23.12.2015 is waived. The Respondent will recover remaining 68% of the assessed amount from the Appellant establishment in accordance with law. | ||
| 52637 | 418/2018 | 14B | EPF Appeal | Sri Kanchi Sankara | APFC, Trichy |
06/08/2024 07/11/2024 13/02/2025 08/05/2025 06/08/2025 15/10/2025 16/01/2026 16/04/2026 |
Final Order - 32% of the assessed amount passed by the Respondent order dated 23.12.2015 is waived. The Respondent will recover remaining 68% of the assessed amount from the Appellant establishment in accordance with law. | ||
| 52638 | 418/2018 | 14B | EPF Appeal | Sri Kanchi Sankara | APFC, Trichy |
06/08/2024 07/11/2024 13/02/2025 08/05/2025 06/08/2025 15/10/2025 16/01/2026 16/04/2026 |
Final Order - 32% of the assessed amount passed by the Respondent order dated 23.12.2015 is waived. The Respondent will recover remaining 68% of the assessed amount from the Appellant establishment in accordance with law. | ||
| 52639 | 418/2018 | 14B | EPF Appeal | Sri Kanchi Sankara | APFC, Trichy |
06/08/2024 07/11/2024 13/02/2025 08/05/2025 06/08/2025 15/10/2025 16/01/2026 16/04/2026 |
Final Order - 32% of the assessed amount passed by the Respondent order dated 23.12.2015 is waived. The Respondent will recover remaining 68% of the assessed amount from the Appellant establishment in accordance with law. | ||
| 52640 | 418/2018 | 14B | EPF Appeal | Sri Kanchi Sankara | APFC, Trichy |
06/08/2024 07/11/2024 13/02/2025 08/05/2025 06/08/2025 15/10/2025 16/01/2026 16/04/2026 |
Final Order - 32% of the assessed amount passed by the Respondent order dated 23.12.2015 is waived. The Respondent will recover remaining 68% of the assessed amount from the Appellant establishment in accordance with law. | ||
| 52641 | 417/2018 | 14B | EPF Appeal | Modern Associate Contract | APFC, Trichy |
20/08/2024 21/11/2024 28/02/2025 23/05/2025 20/08/2025 07/11/2025 13/02/2026 |
Final Order - 32% of the assessed amount passed by the Respondent order dated 03.11.2015 is waived. The Respondent will recover remaining 68% of the assessed amount from the Appellant establishment in accordance with law. | ||
| 52642 | 417/2018 | 14B | EPF Appeal | Modern Associate Contract | APFC, Trichy |
20/08/2024 21/11/2024 28/02/2025 23/05/2025 20/08/2025 07/11/2025 13/02/2026 |
Final Order - 32% of the assessed amount passed by the Respondent order dated 03.11.2015 is waived. The Respondent will recover remaining 68% of the assessed amount from the Appellant establishment in accordance with law. | ||
| 52643 | 417/2018 | 14B | EPF Appeal | Modern Associate Contract | APFC, Trichy |
20/08/2024 21/11/2024 28/02/2025 23/05/2025 20/08/2025 07/11/2025 13/02/2026 |
Final Order - 32% of the assessed amount passed by the Respondent order dated 03.11.2015 is waived. The Respondent will recover remaining 68% of the assessed amount from the Appellant establishment in accordance with law. | ||
| 52644 | 417/2018 | 14B | EPF Appeal | Modern Associate Contract | APFC, Trichy |
20/08/2024 21/11/2024 28/02/2025 23/05/2025 20/08/2025 07/11/2025 13/02/2026 |
Final Order - 32% of the assessed amount passed by the Respondent order dated 03.11.2015 is waived. The Respondent will recover remaining 68% of the assessed amount from the Appellant establishment in accordance with law. | ||
| 52645 | 417/2018 | 14B | EPF Appeal | Modern Associate Contract | APFC, Trichy |
20/08/2024 21/11/2024 28/02/2025 23/05/2025 20/08/2025 07/11/2025 13/02/2026 |
Final Order - 32% of the assessed amount passed by the Respondent order dated 03.11.2015 is waived. The Respondent will recover remaining 68% of the assessed amount from the Appellant establishment in accordance with law. | ||
| 52646 | 417/2018 | 14B | EPF Appeal | Modern Associate Contract | APFC, Trichy |
20/08/2024 21/11/2024 28/02/2025 23/05/2025 20/08/2025 07/11/2025 13/02/2026 |
Final Order - 32% of the assessed amount passed by the Respondent order dated 03.11.2015 is waived. The Respondent will recover remaining 68% of the assessed amount from the Appellant establishment in accordance with law. | ||
| 52647 | 417/2018 | 14B | EPF Appeal | Modern Associate Contract | APFC, Trichy |
20/08/2024 21/11/2024 28/02/2025 23/05/2025 20/08/2025 07/11/2025 13/02/2026 |
Final Order - 32% of the assessed amount passed by the Respondent order dated 03.11.2015 is waived. The Respondent will recover remaining 68% of the assessed amount from the Appellant establishment in accordance with law. | ||
| 52648 | 416/2018 | 14B | EPF Appeal | The Professional Couriers | APFC, Trichy |
13/03/2025 12/06/2025 20/06/2025 02/07/2025 01/09/2025 07/11/2025 13/02/2026 |
Final Order - 30% of the assessed amount passed by the Respondent order dated 13.01.2016 is waived. The Respondent will recover remaining 70% of the assessed amount from the Appellant establishment in accordance with law. | ||
| 52649 | 416/2018 | 14B | EPF Appeal | The Professional Couriers | APFC, Trichy |
13/03/2025 12/06/2025 20/06/2025 02/07/2025 01/09/2025 07/11/2025 13/02/2026 |
Final Order - 30% of the assessed amount passed by the Respondent order dated 13.01.2016 is waived. The Respondent will recover remaining 70% of the assessed amount from the Appellant establishment in accordance with law. | ||
| 52650 | 416/2018 | 14B | EPF Appeal | The Professional Couriers | APFC, Trichy |
13/03/2025 12/06/2025 20/06/2025 02/07/2025 01/09/2025 07/11/2025 13/02/2026 |
Final Order - 30% of the assessed amount passed by the Respondent order dated 13.01.2016 is waived. The Respondent will recover remaining 70% of the assessed amount from the Appellant establishment in accordance with law. |