Cause List

E.g., 09/07/2026
S.No. Case No. Subject Case Type Name of Appellant Respondent Next Date Details Order / Decision Edit
50551 286/2019 14B EPF Appeal Srirangam Zone Amma Unavagan APFC, Trichy 07/11/2024
13/02/2025
08/05/2025
06/08/2025
15/10/2025
16/01/2026
16/04/2026
13/07/2026
M/s. P. K. PanneerSelvam, the learned Counsel on behalf of the Respondent and M/s. M. Aishwariya, the learned Counsel for the Appellant pray to list the Appeal in the Special Campaign. List to 13.07.2026 for hearing in the Special Campaign.
50552 286/2019 14B EPF Appeal Srirangam Zone Amma Unavagan APFC, Trichy 07/11/2024
13/02/2025
08/05/2025
06/08/2025
15/10/2025
16/01/2026
16/04/2026
13/07/2026
M/s. P. K. PanneerSelvam, the learned Counsel on behalf of the Respondent and M/s. M. Aishwariya, the learned Counsel for the Appellant pray to list the Appeal in the Special Campaign. List to 13.07.2026 for hearing in the Special Campaign.
50553 286/2019 14B EPF Appeal Srirangam Zone Amma Unavagan APFC, Trichy 07/11/2024
13/02/2025
08/05/2025
06/08/2025
15/10/2025
16/01/2026
16/04/2026
13/07/2026
M/s. P. K. PanneerSelvam, the learned Counsel on behalf of the Respondent and M/s. M. Aishwariya, the learned Counsel for the Appellant pray to list the Appeal in the Special Campaign. List to 13.07.2026 for hearing in the Special Campaign.
50554 286/2019 14B EPF Appeal Srirangam Zone Amma Unavagan APFC, Trichy 07/11/2024
13/02/2025
08/05/2025
06/08/2025
15/10/2025
16/01/2026
16/04/2026
13/07/2026
M/s. P. K. PanneerSelvam, the learned Counsel on behalf of the Respondent and M/s. M. Aishwariya, the learned Counsel for the Appellant pray to list the Appeal in the Special Campaign. List to 13.07.2026 for hearing in the Special Campaign.
50555 254/2003 3/1/2020 ID Vijay Borkar Food Corporation of India 02/06/2026
15/06/2026
30/06/2026
07/07/2026
written notes of Argument By Both Parties
50556 254/2003 3/1/2020 ID Vijay Borkar Food Corporation of India 02/06/2026
15/06/2026
30/06/2026
07/07/2026
written notes of Argument By Both Parties
50557 254/2003 3/1/2020 ID Vijay Borkar Food Corporation of India 02/06/2026
15/06/2026
30/06/2026
07/07/2026
written notes of Argument By Both Parties
50558 254/2003 3/1/2020 ID Vijay Borkar Food Corporation of India 02/06/2026
15/06/2026
30/06/2026
07/07/2026
written notes of Argument By Both Parties
50559 Ref.CGIT-2/51 of 2019 Industrial Dispute ID Chowgule & Co. Pvt Ltd United Mine Workers Union 20/11/2025
25/02/2026
10/06/2026
10/09/2026
Arguments
50560 Ref.CGIT-2/51 of 2019 Industrial Dispute ID Chowgule & Co. Pvt Ltd United Mine Workers Union 20/11/2025
25/02/2026
10/06/2026
10/09/2026
Arguments
50561 Ref.CGIT-2/51 of 2019 Industrial Dispute ID Chowgule & Co. Pvt Ltd United Mine Workers Union 20/11/2025
25/02/2026
10/06/2026
10/09/2026
Arguments
50562 Ref.CGIT-2/51 of 2019 Industrial Dispute ID Chowgule & Co. Pvt Ltd United Mine Workers Union 20/11/2025
25/02/2026
10/06/2026
10/09/2026
Arguments
50563 CGIT/LC/R/76/2015 SECTION-10 ID SHRI RAJIV SHARMA SECL 11/04/2022
01/06/2022
20/07/2022
AWARD PASS / Notification Received
50564 CGIT/LC/R/76/2015 SECTION-10 ID SHRI RAJIV SHARMA SECL 11/04/2022
01/06/2022
20/07/2022
AWARD PASS / Notification Received
50565 CGIT/LC/R/76/2015 SECTION-10 ID SHRI RAJIV SHARMA SECL 11/04/2022
01/06/2022
20/07/2022
AWARD PASS / Notification Received
50566 CGIT/LC/EPFA/MISC/28/2019 EPFA MISC EPF Appeal SANJAY MAINTENANCE SERVICE PVT. LTD. APFC, INDORE 06/11/2025
10/03/2026
FOR HEARING Download, Download, Download, Download, Download, Download, Download
50567 CGIT/LC/EPFA/MISC/28/2019 EPFA MISC EPF Appeal SANJAY MAINTENANCE SERVICE PVT. LTD. APFC, INDORE 06/11/2025
10/03/2026
FOR HEARING Download, Download, Download, Download, Download, Download, Download
50568 CGIT/LC/R/80/2017 SECTION-10 ID SHRI ARUN KUMRAY W.C.L. 18/07/2022
23/08/2022
AWARD PASS
50569 CGIT/LC/R/80/2017 SECTION-10 ID SHRI ARUN KUMRAY W.C.L. 18/07/2022
23/08/2022
AWARD PASS
50570 148/2019 14B EPF Appeal Saraswathi Ramachandiran Vidhyalaya Matric School RPFC-II, Coimbatore 04/11/2024
10/02/2025
05/05/2025
25/07/2025
25/09/2025
01/01/2026
04/02/2026
(Special Campaign) Final Order - The Appeal is partly allowed. 35% of the assessed amount is waived off. The Respondent is directed to recover only 65% of the assessed amount of damages u/s. 14B of the Act.
50571 148/2019 14B EPF Appeal Saraswathi Ramachandiran Vidhyalaya Matric School RPFC-II, Coimbatore 04/11/2024
10/02/2025
05/05/2025
25/07/2025
25/09/2025
01/01/2026
04/02/2026
(Special Campaign) Final Order - The Appeal is partly allowed. 35% of the assessed amount is waived off. The Respondent is directed to recover only 65% of the assessed amount of damages u/s. 14B of the Act.
50572 148/2019 14B EPF Appeal Saraswathi Ramachandiran Vidhyalaya Matric School RPFC-II, Coimbatore 04/11/2024
10/02/2025
05/05/2025
25/07/2025
25/09/2025
01/01/2026
04/02/2026
(Special Campaign) Final Order - The Appeal is partly allowed. 35% of the assessed amount is waived off. The Respondent is directed to recover only 65% of the assessed amount of damages u/s. 14B of the Act.
50573 148/2019 14B EPF Appeal Saraswathi Ramachandiran Vidhyalaya Matric School RPFC-II, Coimbatore 04/11/2024
10/02/2025
05/05/2025
25/07/2025
25/09/2025
01/01/2026
04/02/2026
(Special Campaign) Final Order - The Appeal is partly allowed. 35% of the assessed amount is waived off. The Respondent is directed to recover only 65% of the assessed amount of damages u/s. 14B of the Act.
50574 148/2019 14B EPF Appeal Saraswathi Ramachandiran Vidhyalaya Matric School RPFC-II, Coimbatore 04/11/2024
10/02/2025
05/05/2025
25/07/2025
25/09/2025
01/01/2026
04/02/2026
(Special Campaign) Final Order - The Appeal is partly allowed. 35% of the assessed amount is waived off. The Respondent is directed to recover only 65% of the assessed amount of damages u/s. 14B of the Act.
50575 148/2019 14B EPF Appeal Saraswathi Ramachandiran Vidhyalaya Matric School RPFC-II, Coimbatore 04/11/2024
10/02/2025
05/05/2025
25/07/2025
25/09/2025
01/01/2026
04/02/2026
(Special Campaign) Final Order - The Appeal is partly allowed. 35% of the assessed amount is waived off. The Respondent is directed to recover only 65% of the assessed amount of damages u/s. 14B of the Act.
50576 148/2019 14B EPF Appeal Saraswathi Ramachandiran Vidhyalaya Matric School RPFC-II, Coimbatore 04/11/2024
10/02/2025
05/05/2025
25/07/2025
25/09/2025
01/01/2026
04/02/2026
(Special Campaign) Final Order - The Appeal is partly allowed. 35% of the assessed amount is waived off. The Respondent is directed to recover only 65% of the assessed amount of damages u/s. 14B of the Act.
50577 149/2019 14B EPF Appeal Indroyal Furniture Company Pvt. Ltd., APFC, Tirunelveli 08/09/2021
12/01/2022
21/04/2022
26/12/2024
07/02/2025
15/04/2025
04/06/2025
30/07/2025
09/10/2025
Final Order - The Appeal is partly allowed. The Respondent is directed to recover only 75% of assessed damages and remaining 25% of damages is waived off.
50578 149/2019 14B EPF Appeal Indroyal Furniture Company Pvt. Ltd., APFC, Tirunelveli 08/09/2021
12/01/2022
21/04/2022
26/12/2024
07/02/2025
15/04/2025
04/06/2025
30/07/2025
09/10/2025
Final Order - The Appeal is partly allowed. The Respondent is directed to recover only 75% of assessed damages and remaining 25% of damages is waived off.
50579 149/2019 14B EPF Appeal Indroyal Furniture Company Pvt. Ltd., APFC, Tirunelveli 08/09/2021
12/01/2022
21/04/2022
26/12/2024
07/02/2025
15/04/2025
04/06/2025
30/07/2025
09/10/2025
Final Order - The Appeal is partly allowed. The Respondent is directed to recover only 75% of assessed damages and remaining 25% of damages is waived off.
50580 149/2019 14B EPF Appeal Indroyal Furniture Company Pvt. Ltd., APFC, Tirunelveli 08/09/2021
12/01/2022
21/04/2022
26/12/2024
07/02/2025
15/04/2025
04/06/2025
30/07/2025
09/10/2025
Final Order - The Appeal is partly allowed. The Respondent is directed to recover only 75% of assessed damages and remaining 25% of damages is waived off.
50581 149/2019 14B EPF Appeal Indroyal Furniture Company Pvt. Ltd., APFC, Tirunelveli 08/09/2021
12/01/2022
21/04/2022
26/12/2024
07/02/2025
15/04/2025
04/06/2025
30/07/2025
09/10/2025
Final Order - The Appeal is partly allowed. The Respondent is directed to recover only 75% of assessed damages and remaining 25% of damages is waived off.
50582 149/2019 14B EPF Appeal Indroyal Furniture Company Pvt. Ltd., APFC, Tirunelveli 08/09/2021
12/01/2022
21/04/2022
26/12/2024
07/02/2025
15/04/2025
04/06/2025
30/07/2025
09/10/2025
Final Order - The Appeal is partly allowed. The Respondent is directed to recover only 75% of assessed damages and remaining 25% of damages is waived off.
50583 149/2019 14B EPF Appeal Indroyal Furniture Company Pvt. Ltd., APFC, Tirunelveli 08/09/2021
12/01/2022
21/04/2022
26/12/2024
07/02/2025
15/04/2025
04/06/2025
30/07/2025
09/10/2025
Final Order - The Appeal is partly allowed. The Respondent is directed to recover only 75% of assessed damages and remaining 25% of damages is waived off.
50584 149/2019 14B EPF Appeal Indroyal Furniture Company Pvt. Ltd., APFC, Tirunelveli 08/09/2021
12/01/2022
21/04/2022
26/12/2024
07/02/2025
15/04/2025
04/06/2025
30/07/2025
09/10/2025
Final Order - The Appeal is partly allowed. The Respondent is directed to recover only 75% of assessed damages and remaining 25% of damages is waived off.
50585 149/2019 14B EPF Appeal Indroyal Furniture Company Pvt. Ltd., APFC, Tirunelveli 08/09/2021
12/01/2022
21/04/2022
26/12/2024
07/02/2025
15/04/2025
04/06/2025
30/07/2025
09/10/2025
Final Order - The Appeal is partly allowed. The Respondent is directed to recover only 75% of assessed damages and remaining 25% of damages is waived off.
50586 150/2019 14B EPF Appeal Indroyal Crafts Pvt. Ltd., APFC, Tirunelveli 08/09/2021
12/01/2022
21/04/2022
26/12/2024
07/02/2025
15/04/2025
04/06/2025
30/07/2025
09/10/2025
Final Order - The Appeal is partly allowed. The Respondent is directed to recover only 75% of assessed damages and remaining 25% of damages is waived off.
50587 150/2019 14B EPF Appeal Indroyal Crafts Pvt. Ltd., APFC, Tirunelveli 08/09/2021
12/01/2022
21/04/2022
26/12/2024
07/02/2025
15/04/2025
04/06/2025
30/07/2025
09/10/2025
Final Order - The Appeal is partly allowed. The Respondent is directed to recover only 75% of assessed damages and remaining 25% of damages is waived off.
50588 150/2019 14B EPF Appeal Indroyal Crafts Pvt. Ltd., APFC, Tirunelveli 08/09/2021
12/01/2022
21/04/2022
26/12/2024
07/02/2025
15/04/2025
04/06/2025
30/07/2025
09/10/2025
Final Order - The Appeal is partly allowed. The Respondent is directed to recover only 75% of assessed damages and remaining 25% of damages is waived off.
50589 150/2019 14B EPF Appeal Indroyal Crafts Pvt. Ltd., APFC, Tirunelveli 08/09/2021
12/01/2022
21/04/2022
26/12/2024
07/02/2025
15/04/2025
04/06/2025
30/07/2025
09/10/2025
Final Order - The Appeal is partly allowed. The Respondent is directed to recover only 75% of assessed damages and remaining 25% of damages is waived off.
50590 150/2019 14B EPF Appeal Indroyal Crafts Pvt. Ltd., APFC, Tirunelveli 08/09/2021
12/01/2022
21/04/2022
26/12/2024
07/02/2025
15/04/2025
04/06/2025
30/07/2025
09/10/2025
Final Order - The Appeal is partly allowed. The Respondent is directed to recover only 75% of assessed damages and remaining 25% of damages is waived off.
50591 150/2019 14B EPF Appeal Indroyal Crafts Pvt. Ltd., APFC, Tirunelveli 08/09/2021
12/01/2022
21/04/2022
26/12/2024
07/02/2025
15/04/2025
04/06/2025
30/07/2025
09/10/2025
Final Order - The Appeal is partly allowed. The Respondent is directed to recover only 75% of assessed damages and remaining 25% of damages is waived off.
50592 150/2019 14B EPF Appeal Indroyal Crafts Pvt. Ltd., APFC, Tirunelveli 08/09/2021
12/01/2022
21/04/2022
26/12/2024
07/02/2025
15/04/2025
04/06/2025
30/07/2025
09/10/2025
Final Order - The Appeal is partly allowed. The Respondent is directed to recover only 75% of assessed damages and remaining 25% of damages is waived off.
50593 150/2019 14B EPF Appeal Indroyal Crafts Pvt. Ltd., APFC, Tirunelveli 08/09/2021
12/01/2022
21/04/2022
26/12/2024
07/02/2025
15/04/2025
04/06/2025
30/07/2025
09/10/2025
Final Order - The Appeal is partly allowed. The Respondent is directed to recover only 75% of assessed damages and remaining 25% of damages is waived off.
50594 150/2019 14B EPF Appeal Indroyal Crafts Pvt. Ltd., APFC, Tirunelveli 08/09/2021
12/01/2022
21/04/2022
26/12/2024
07/02/2025
15/04/2025
04/06/2025
30/07/2025
09/10/2025
Final Order - The Appeal is partly allowed. The Respondent is directed to recover only 75% of assessed damages and remaining 25% of damages is waived off.
50595 152/2019 7A EPF Appeal Pollachi Municipality RPFC-II, Coimbatore 10/02/2025
05/05/2025
25/07/2025
25/09/2025
01/01/2026
10/04/2026
19/06/2026
20/07/2026
M/s. P. Dhamodharan, the learned Counsel on behalf of the Appellant and the Representative Counsel on behalf of the Respondent pray to list the Appeal in the Special Campaign. List to 20.07.2026 for hearing in the Special Campaign.
50596 152/2019 7A EPF Appeal Pollachi Municipality RPFC-II, Coimbatore 10/02/2025
05/05/2025
25/07/2025
25/09/2025
01/01/2026
10/04/2026
19/06/2026
20/07/2026
M/s. P. Dhamodharan, the learned Counsel on behalf of the Appellant and the Representative Counsel on behalf of the Respondent pray to list the Appeal in the Special Campaign. List to 20.07.2026 for hearing in the Special Campaign.
50597 152/2019 7A EPF Appeal Pollachi Municipality RPFC-II, Coimbatore 10/02/2025
05/05/2025
25/07/2025
25/09/2025
01/01/2026
10/04/2026
19/06/2026
20/07/2026
M/s. P. Dhamodharan, the learned Counsel on behalf of the Appellant and the Representative Counsel on behalf of the Respondent pray to list the Appeal in the Special Campaign. List to 20.07.2026 for hearing in the Special Campaign.
50598 152/2019 7A EPF Appeal Pollachi Municipality RPFC-II, Coimbatore 10/02/2025
05/05/2025
25/07/2025
25/09/2025
01/01/2026
10/04/2026
19/06/2026
20/07/2026
M/s. P. Dhamodharan, the learned Counsel on behalf of the Appellant and the Representative Counsel on behalf of the Respondent pray to list the Appeal in the Special Campaign. List to 20.07.2026 for hearing in the Special Campaign.
50599 152/2019 7A EPF Appeal Pollachi Municipality RPFC-II, Coimbatore 10/02/2025
05/05/2025
25/07/2025
25/09/2025
01/01/2026
10/04/2026
19/06/2026
20/07/2026
M/s. P. Dhamodharan, the learned Counsel on behalf of the Appellant and the Representative Counsel on behalf of the Respondent pray to list the Appeal in the Special Campaign. List to 20.07.2026 for hearing in the Special Campaign.
50600 152/2019 7A EPF Appeal Pollachi Municipality RPFC-II, Coimbatore 10/02/2025
05/05/2025
25/07/2025
25/09/2025
01/01/2026
10/04/2026
19/06/2026
20/07/2026
M/s. P. Dhamodharan, the learned Counsel on behalf of the Appellant and the Representative Counsel on behalf of the Respondent pray to list the Appeal in the Special Campaign. List to 20.07.2026 for hearing in the Special Campaign.