| 74201 | 294/2018 | 14B | EPF Appeal | Vinoth Builders | APFC, Ambattur |
08/05/2024 21/08/2024 22/11/2024 11/03/2025 10/06/2025 08/09/2025 19/11/2025 18/12/2025 02/02/2026 |
(Special Campaign) Final Order - The Appeal is partly allowed. 40% of the assessed amount is waived off. The Respondent is directed to recover only 60% of the assessed amount of damages u/s. 14B of the Act. | ||
| 74202 | 294/2018 | 14B | EPF Appeal | Vinoth Builders | APFC, Ambattur |
08/05/2024 21/08/2024 22/11/2024 11/03/2025 10/06/2025 08/09/2025 19/11/2025 18/12/2025 02/02/2026 |
(Special Campaign) Final Order - The Appeal is partly allowed. 40% of the assessed amount is waived off. The Respondent is directed to recover only 60% of the assessed amount of damages u/s. 14B of the Act. | ||
| 74203 | 294/2018 | 14B | EPF Appeal | Vinoth Builders | APFC, Ambattur |
08/05/2024 21/08/2024 22/11/2024 11/03/2025 10/06/2025 08/09/2025 19/11/2025 18/12/2025 02/02/2026 |
(Special Campaign) Final Order - The Appeal is partly allowed. 40% of the assessed amount is waived off. The Respondent is directed to recover only 60% of the assessed amount of damages u/s. 14B of the Act. | ||
| 74204 | 294/2018 | 14B | EPF Appeal | Vinoth Builders | APFC, Ambattur |
08/05/2024 21/08/2024 22/11/2024 11/03/2025 10/06/2025 08/09/2025 19/11/2025 18/12/2025 02/02/2026 |
(Special Campaign) Final Order - The Appeal is partly allowed. 40% of the assessed amount is waived off. The Respondent is directed to recover only 60% of the assessed amount of damages u/s. 14B of the Act. | ||
| 74205 | 294/2018 | 14B | EPF Appeal | Vinoth Builders | APFC, Ambattur |
08/05/2024 21/08/2024 22/11/2024 11/03/2025 10/06/2025 08/09/2025 19/11/2025 18/12/2025 02/02/2026 |
(Special Campaign) Final Order - The Appeal is partly allowed. 40% of the assessed amount is waived off. The Respondent is directed to recover only 60% of the assessed amount of damages u/s. 14B of the Act. | ||
| 74206 | 294/2018 | 14B | EPF Appeal | Vinoth Builders | APFC, Ambattur |
08/05/2024 21/08/2024 22/11/2024 11/03/2025 10/06/2025 08/09/2025 19/11/2025 18/12/2025 02/02/2026 |
(Special Campaign) Final Order - The Appeal is partly allowed. 40% of the assessed amount is waived off. The Respondent is directed to recover only 60% of the assessed amount of damages u/s. 14B of the Act. | ||
| 74207 | 294/2018 | 14B | EPF Appeal | Vinoth Builders | APFC, Ambattur |
08/05/2024 21/08/2024 22/11/2024 11/03/2025 10/06/2025 08/09/2025 19/11/2025 18/12/2025 02/02/2026 |
(Special Campaign) Final Order - The Appeal is partly allowed. 40% of the assessed amount is waived off. The Respondent is directed to recover only 60% of the assessed amount of damages u/s. 14B of the Act. | ||
| 74208 | 294/2018 | 14B | EPF Appeal | Vinoth Builders | APFC, Ambattur |
08/05/2024 21/08/2024 22/11/2024 11/03/2025 10/06/2025 08/09/2025 19/11/2025 18/12/2025 02/02/2026 |
(Special Campaign) Final Order - The Appeal is partly allowed. 40% of the assessed amount is waived off. The Respondent is directed to recover only 60% of the assessed amount of damages u/s. 14B of the Act. | ||
| 74209 | 249/2018 | 7A | EPF Appeal | Gokaldas Exports Ltd. | RPFC, Tambaram |
22/06/2021 25/11/2021 28/01/2022 23/02/2022 27/04/2023 10/05/2023 |
Final Orders-The Appeal stands dismissed. | ||
| 74210 | 249/2018 | 7A | EPF Appeal | Gokaldas Exports Ltd. | RPFC, Tambaram |
22/06/2021 25/11/2021 28/01/2022 23/02/2022 27/04/2023 10/05/2023 |
Final Orders-The Appeal stands dismissed. | ||
| 74211 | 249/2018 | 7A | EPF Appeal | Gokaldas Exports Ltd. | RPFC, Tambaram |
22/06/2021 25/11/2021 28/01/2022 23/02/2022 27/04/2023 10/05/2023 |
Final Orders-The Appeal stands dismissed. | ||
| 74212 | 249/2018 | 7A | EPF Appeal | Gokaldas Exports Ltd. | RPFC, Tambaram |
22/06/2021 25/11/2021 28/01/2022 23/02/2022 27/04/2023 10/05/2023 |
Final Orders-The Appeal stands dismissed. | ||
| 74213 | 249/2018 | 7A | EPF Appeal | Gokaldas Exports Ltd. | RPFC, Tambaram |
22/06/2021 25/11/2021 28/01/2022 23/02/2022 27/04/2023 10/05/2023 |
Final Orders-The Appeal stands dismissed. | ||
| 74214 | 249/2018 | 7A | EPF Appeal | Gokaldas Exports Ltd. | RPFC, Tambaram |
22/06/2021 25/11/2021 28/01/2022 23/02/2022 27/04/2023 10/05/2023 |
Final Orders-The Appeal stands dismissed. | ||
| 74215 | 242/2018 | 7A | EPF Appeal | CIS Bureau Facility Services (P) Ltd | RPFC, Chennai |
07/04/2020 21/07/2020 07/12/2020 09/04/2021 20/09/2021 14/01/2022 04/02/2022 22/03/2022 16/09/2022 |
Final Order - The Appeal stands dismissed. | ||
| 74216 | 242/2018 | 7A | EPF Appeal | CIS Bureau Facility Services (P) Ltd | RPFC, Chennai |
07/04/2020 21/07/2020 07/12/2020 09/04/2021 20/09/2021 14/01/2022 04/02/2022 22/03/2022 16/09/2022 |
Final Order - The Appeal stands dismissed. | ||
| 74217 | 242/2018 | 7A | EPF Appeal | CIS Bureau Facility Services (P) Ltd | RPFC, Chennai |
07/04/2020 21/07/2020 07/12/2020 09/04/2021 20/09/2021 14/01/2022 04/02/2022 22/03/2022 16/09/2022 |
Final Order - The Appeal stands dismissed. | ||
| 74218 | 242/2018 | 7A | EPF Appeal | CIS Bureau Facility Services (P) Ltd | RPFC, Chennai |
07/04/2020 21/07/2020 07/12/2020 09/04/2021 20/09/2021 14/01/2022 04/02/2022 22/03/2022 16/09/2022 |
Final Order - The Appeal stands dismissed. | ||
| 74219 | 242/2018 | 7A | EPF Appeal | CIS Bureau Facility Services (P) Ltd | RPFC, Chennai |
07/04/2020 21/07/2020 07/12/2020 09/04/2021 20/09/2021 14/01/2022 04/02/2022 22/03/2022 16/09/2022 |
Final Order - The Appeal stands dismissed. | ||
| 74220 | 242/2018 | 7A | EPF Appeal | CIS Bureau Facility Services (P) Ltd | RPFC, Chennai |
07/04/2020 21/07/2020 07/12/2020 09/04/2021 20/09/2021 14/01/2022 04/02/2022 22/03/2022 16/09/2022 |
Final Order - The Appeal stands dismissed. | ||
| 74221 | 242/2018 | 7A | EPF Appeal | CIS Bureau Facility Services (P) Ltd | RPFC, Chennai |
07/04/2020 21/07/2020 07/12/2020 09/04/2021 20/09/2021 14/01/2022 04/02/2022 22/03/2022 16/09/2022 |
Final Order - The Appeal stands dismissed. | ||
| 74222 | 242/2018 | 7A | EPF Appeal | CIS Bureau Facility Services (P) Ltd | RPFC, Chennai |
07/04/2020 21/07/2020 07/12/2020 09/04/2021 20/09/2021 14/01/2022 04/02/2022 22/03/2022 16/09/2022 |
Final Order - The Appeal stands dismissed. | ||
| 74223 | 242/2018 | 7A | EPF Appeal | CIS Bureau Facility Services (P) Ltd | RPFC, Chennai |
07/04/2020 21/07/2020 07/12/2020 09/04/2021 20/09/2021 14/01/2022 04/02/2022 22/03/2022 16/09/2022 |
Final Order - The Appeal stands dismissed. | ||
| 74224 | 241/2018 | 7A | EPF Appeal | Kapil Metal Processing Industrial P Ltd | APFC, Chennai |
23/10/2024 21/01/2025 22/04/2025 21/07/2025 16/09/2025 19/12/2025 27/03/2026 11/06/2026 20/08/2026 |
The Representative Counsel on behalf of the Appellant prays time for Arguments. Time granted. M/s. R. Vishnu, the learned Counsel on behalf of the Respondent is present. List to 20.08.2026 for hearing on Arguments/filing of written submission. | ||
| 74225 | 241/2018 | 7A | EPF Appeal | Kapil Metal Processing Industrial P Ltd | APFC, Chennai |
23/10/2024 21/01/2025 22/04/2025 21/07/2025 16/09/2025 19/12/2025 27/03/2026 11/06/2026 20/08/2026 |
The Representative Counsel on behalf of the Appellant prays time for Arguments. Time granted. M/s. R. Vishnu, the learned Counsel on behalf of the Respondent is present. List to 20.08.2026 for hearing on Arguments/filing of written submission. | ||
| 74226 | 241/2018 | 7A | EPF Appeal | Kapil Metal Processing Industrial P Ltd | APFC, Chennai |
23/10/2024 21/01/2025 22/04/2025 21/07/2025 16/09/2025 19/12/2025 27/03/2026 11/06/2026 20/08/2026 |
The Representative Counsel on behalf of the Appellant prays time for Arguments. Time granted. M/s. R. Vishnu, the learned Counsel on behalf of the Respondent is present. List to 20.08.2026 for hearing on Arguments/filing of written submission. | ||
| 74227 | 241/2018 | 7A | EPF Appeal | Kapil Metal Processing Industrial P Ltd | APFC, Chennai |
23/10/2024 21/01/2025 22/04/2025 21/07/2025 16/09/2025 19/12/2025 27/03/2026 11/06/2026 20/08/2026 |
The Representative Counsel on behalf of the Appellant prays time for Arguments. Time granted. M/s. R. Vishnu, the learned Counsel on behalf of the Respondent is present. List to 20.08.2026 for hearing on Arguments/filing of written submission. | ||
| 74228 | 241/2018 | 7A | EPF Appeal | Kapil Metal Processing Industrial P Ltd | APFC, Chennai |
23/10/2024 21/01/2025 22/04/2025 21/07/2025 16/09/2025 19/12/2025 27/03/2026 11/06/2026 20/08/2026 |
The Representative Counsel on behalf of the Appellant prays time for Arguments. Time granted. M/s. R. Vishnu, the learned Counsel on behalf of the Respondent is present. List to 20.08.2026 for hearing on Arguments/filing of written submission. | ||
| 74229 | 241/2018 | 7A | EPF Appeal | Kapil Metal Processing Industrial P Ltd | APFC, Chennai |
23/10/2024 21/01/2025 22/04/2025 21/07/2025 16/09/2025 19/12/2025 27/03/2026 11/06/2026 20/08/2026 |
The Representative Counsel on behalf of the Appellant prays time for Arguments. Time granted. M/s. R. Vishnu, the learned Counsel on behalf of the Respondent is present. List to 20.08.2026 for hearing on Arguments/filing of written submission. | ||
| 74230 | 241/2018 | 7A | EPF Appeal | Kapil Metal Processing Industrial P Ltd | APFC, Chennai |
23/10/2024 21/01/2025 22/04/2025 21/07/2025 16/09/2025 19/12/2025 27/03/2026 11/06/2026 20/08/2026 |
The Representative Counsel on behalf of the Appellant prays time for Arguments. Time granted. M/s. R. Vishnu, the learned Counsel on behalf of the Respondent is present. List to 20.08.2026 for hearing on Arguments/filing of written submission. | ||
| 74231 | 241/2018 | 7A | EPF Appeal | Kapil Metal Processing Industrial P Ltd | APFC, Chennai |
23/10/2024 21/01/2025 22/04/2025 21/07/2025 16/09/2025 19/12/2025 27/03/2026 11/06/2026 20/08/2026 |
The Representative Counsel on behalf of the Appellant prays time for Arguments. Time granted. M/s. R. Vishnu, the learned Counsel on behalf of the Respondent is present. List to 20.08.2026 for hearing on Arguments/filing of written submission. | ||
| 74232 | 241/2018 | 7A | EPF Appeal | Kapil Metal Processing Industrial P Ltd | APFC, Chennai |
23/10/2024 21/01/2025 22/04/2025 21/07/2025 16/09/2025 19/12/2025 27/03/2026 11/06/2026 20/08/2026 |
The Representative Counsel on behalf of the Appellant prays time for Arguments. Time granted. M/s. R. Vishnu, the learned Counsel on behalf of the Respondent is present. List to 20.08.2026 for hearing on Arguments/filing of written submission. | ||
| 74233 | 240/2018 | 7A | EPF Appeal | VST Service Station (Vellore) | APFC, Chennai |
23/10/2024 21/01/2025 22/04/2025 21/07/2025 16/09/2025 19/12/2025 27/03/2026 11/06/2026 20/08/2026 |
The Representative Counsel on behalf of the Appellant prays time for Arguments. Time granted. M/s. R. Vishnu, the learned Counsel on behalf of the Respondent is present. List to 20.08.2026 for hearing on Arguments/filing of written submission. | ||
| 74234 | 240/2018 | 7A | EPF Appeal | VST Service Station (Vellore) | APFC, Chennai |
23/10/2024 21/01/2025 22/04/2025 21/07/2025 16/09/2025 19/12/2025 27/03/2026 11/06/2026 20/08/2026 |
The Representative Counsel on behalf of the Appellant prays time for Arguments. Time granted. M/s. R. Vishnu, the learned Counsel on behalf of the Respondent is present. List to 20.08.2026 for hearing on Arguments/filing of written submission. | ||
| 74235 | 240/2018 | 7A | EPF Appeal | VST Service Station (Vellore) | APFC, Chennai |
23/10/2024 21/01/2025 22/04/2025 21/07/2025 16/09/2025 19/12/2025 27/03/2026 11/06/2026 20/08/2026 |
The Representative Counsel on behalf of the Appellant prays time for Arguments. Time granted. M/s. R. Vishnu, the learned Counsel on behalf of the Respondent is present. List to 20.08.2026 for hearing on Arguments/filing of written submission. | ||
| 74236 | 240/2018 | 7A | EPF Appeal | VST Service Station (Vellore) | APFC, Chennai |
23/10/2024 21/01/2025 22/04/2025 21/07/2025 16/09/2025 19/12/2025 27/03/2026 11/06/2026 20/08/2026 |
The Representative Counsel on behalf of the Appellant prays time for Arguments. Time granted. M/s. R. Vishnu, the learned Counsel on behalf of the Respondent is present. List to 20.08.2026 for hearing on Arguments/filing of written submission. | ||
| 74237 | 240/2018 | 7A | EPF Appeal | VST Service Station (Vellore) | APFC, Chennai |
23/10/2024 21/01/2025 22/04/2025 21/07/2025 16/09/2025 19/12/2025 27/03/2026 11/06/2026 20/08/2026 |
The Representative Counsel on behalf of the Appellant prays time for Arguments. Time granted. M/s. R. Vishnu, the learned Counsel on behalf of the Respondent is present. List to 20.08.2026 for hearing on Arguments/filing of written submission. | ||
| 74238 | 240/2018 | 7A | EPF Appeal | VST Service Station (Vellore) | APFC, Chennai |
23/10/2024 21/01/2025 22/04/2025 21/07/2025 16/09/2025 19/12/2025 27/03/2026 11/06/2026 20/08/2026 |
The Representative Counsel on behalf of the Appellant prays time for Arguments. Time granted. M/s. R. Vishnu, the learned Counsel on behalf of the Respondent is present. List to 20.08.2026 for hearing on Arguments/filing of written submission. | ||
| 74239 | 240/2018 | 7A | EPF Appeal | VST Service Station (Vellore) | APFC, Chennai |
23/10/2024 21/01/2025 22/04/2025 21/07/2025 16/09/2025 19/12/2025 27/03/2026 11/06/2026 20/08/2026 |
The Representative Counsel on behalf of the Appellant prays time for Arguments. Time granted. M/s. R. Vishnu, the learned Counsel on behalf of the Respondent is present. List to 20.08.2026 for hearing on Arguments/filing of written submission. | ||
| 74240 | 240/2018 | 7A | EPF Appeal | VST Service Station (Vellore) | APFC, Chennai |
23/10/2024 21/01/2025 22/04/2025 21/07/2025 16/09/2025 19/12/2025 27/03/2026 11/06/2026 20/08/2026 |
The Representative Counsel on behalf of the Appellant prays time for Arguments. Time granted. M/s. R. Vishnu, the learned Counsel on behalf of the Respondent is present. List to 20.08.2026 for hearing on Arguments/filing of written submission. | ||
| 74241 | 240/2018 | 7A | EPF Appeal | VST Service Station (Vellore) | APFC, Chennai |
23/10/2024 21/01/2025 22/04/2025 21/07/2025 16/09/2025 19/12/2025 27/03/2026 11/06/2026 20/08/2026 |
The Representative Counsel on behalf of the Appellant prays time for Arguments. Time granted. M/s. R. Vishnu, the learned Counsel on behalf of the Respondent is present. List to 20.08.2026 for hearing on Arguments/filing of written submission. | ||
| 74242 | 18/2017 | 14B | EPF Appeal | Thangavel Textiles Mills Pvt. Ltd. | APFC, Salem |
08/08/2019 19/09/2019 30/09/2019 |
Final Order-Appeal stands dismissed. | ||
| 74243 | 18/2017 | 14B | EPF Appeal | Thangavel Textiles Mills Pvt. Ltd. | APFC, Salem |
08/08/2019 19/09/2019 30/09/2019 |
Final Order-Appeal stands dismissed. | ||
| 74244 | 18/2017 | 14B | EPF Appeal | Thangavel Textiles Mills Pvt. Ltd. | APFC, Salem |
08/08/2019 19/09/2019 30/09/2019 |
Final Order-Appeal stands dismissed. | ||
| 74245 | 308/2018 | 14B | EPF Appeal | McCoy Clothing Pvt. Ltd. | RPFC, Tambaram |
26/09/2024 27/12/2024 27/03/2025 26/06/2025 26/08/2025 20/11/2025 26/02/2026 |
(Special Campaign) Final Order - Waived 35% of assessed amount passed by Respondent order dtd 31.10.2016 Respondent will recover remaining 65% of assessed amount from Appellant in accordance with law | ||
| 74246 | 308/2018 | 14B | EPF Appeal | McCoy Clothing Pvt. Ltd. | RPFC, Tambaram |
26/09/2024 27/12/2024 27/03/2025 26/06/2025 26/08/2025 20/11/2025 26/02/2026 |
(Special Campaign) Final Order - Waived 35% of assessed amount passed by Respondent order dtd 31.10.2016 Respondent will recover remaining 65% of assessed amount from Appellant in accordance with law | ||
| 74247 | 308/2018 | 14B | EPF Appeal | McCoy Clothing Pvt. Ltd. | RPFC, Tambaram |
26/09/2024 27/12/2024 27/03/2025 26/06/2025 26/08/2025 20/11/2025 26/02/2026 |
(Special Campaign) Final Order - Waived 35% of assessed amount passed by Respondent order dtd 31.10.2016 Respondent will recover remaining 65% of assessed amount from Appellant in accordance with law | ||
| 74248 | 308/2018 | 14B | EPF Appeal | McCoy Clothing Pvt. Ltd. | RPFC, Tambaram |
26/09/2024 27/12/2024 27/03/2025 26/06/2025 26/08/2025 20/11/2025 26/02/2026 |
(Special Campaign) Final Order - Waived 35% of assessed amount passed by Respondent order dtd 31.10.2016 Respondent will recover remaining 65% of assessed amount from Appellant in accordance with law | ||
| 74249 | 308/2018 | 14B | EPF Appeal | McCoy Clothing Pvt. Ltd. | RPFC, Tambaram |
26/09/2024 27/12/2024 27/03/2025 26/06/2025 26/08/2025 20/11/2025 26/02/2026 |
(Special Campaign) Final Order - Waived 35% of assessed amount passed by Respondent order dtd 31.10.2016 Respondent will recover remaining 65% of assessed amount from Appellant in accordance with law | ||
| 74250 | 308/2018 | 14B | EPF Appeal | McCoy Clothing Pvt. Ltd. | RPFC, Tambaram |
26/09/2024 27/12/2024 27/03/2025 26/06/2025 26/08/2025 20/11/2025 26/02/2026 |
(Special Campaign) Final Order - Waived 35% of assessed amount passed by Respondent order dtd 31.10.2016 Respondent will recover remaining 65% of assessed amount from Appellant in accordance with law |