| 3751 | 260/2025 | 7A | EPF Appeal | P. Ramdas Transport Contractors | APFC, Trichy |
23/10/2025 27/10/2025 19/11/2025 10/12/2025 26/12/2025 20/03/2026 10/04/2026 14/05/2026 |
(Time Bound Appeal) M/s. Pradeep Solomon Raj, the learned Counsel on behalf of the Appellant filed the Petition for adjournment. Petition allowed. M/s. P. K. PanneerSelvam, the learned Counsel on behalf of the Respondent is present. List to 14.05.2026 fo | ||
| 3752 | 260/2025 | 7A | EPF Appeal | P. Ramdas Transport Contractors | APFC, Trichy |
23/10/2025 27/10/2025 19/11/2025 10/12/2025 26/12/2025 20/03/2026 10/04/2026 14/05/2026 |
(Time Bound Appeal) M/s. Pradeep Solomon Raj, the learned Counsel on behalf of the Appellant filed the Petition for adjournment. Petition allowed. M/s. P. K. PanneerSelvam, the learned Counsel on behalf of the Respondent is present. List to 14.05.2026 fo | ||
| 3753 | 260/2025 | 7A | EPF Appeal | P. Ramdas Transport Contractors | APFC, Trichy |
23/10/2025 27/10/2025 19/11/2025 10/12/2025 26/12/2025 20/03/2026 10/04/2026 14/05/2026 |
(Time Bound Appeal) M/s. Pradeep Solomon Raj, the learned Counsel on behalf of the Appellant filed the Petition for adjournment. Petition allowed. M/s. P. K. PanneerSelvam, the learned Counsel on behalf of the Respondent is present. List to 14.05.2026 fo | ||
| 3754 | 260/2025 | 7A | EPF Appeal | P. Ramdas Transport Contractors | APFC, Trichy |
23/10/2025 27/10/2025 19/11/2025 10/12/2025 26/12/2025 20/03/2026 10/04/2026 14/05/2026 |
(Time Bound Appeal) M/s. Pradeep Solomon Raj, the learned Counsel on behalf of the Appellant filed the Petition for adjournment. Petition allowed. M/s. P. K. PanneerSelvam, the learned Counsel on behalf of the Respondent is present. List to 14.05.2026 fo | ||
| 3755 | 260/2025 | 7A | EPF Appeal | P. Ramdas Transport Contractors | APFC, Trichy |
23/10/2025 27/10/2025 19/11/2025 10/12/2025 26/12/2025 20/03/2026 10/04/2026 14/05/2026 |
(Time Bound Appeal) M/s. Pradeep Solomon Raj, the learned Counsel on behalf of the Appellant filed the Petition for adjournment. Petition allowed. M/s. P. K. PanneerSelvam, the learned Counsel on behalf of the Respondent is present. List to 14.05.2026 fo | ||
| 3756 | 260/2025 | 7A | EPF Appeal | P. Ramdas Transport Contractors | APFC, Trichy |
23/10/2025 27/10/2025 19/11/2025 10/12/2025 26/12/2025 20/03/2026 10/04/2026 14/05/2026 |
(Time Bound Appeal) M/s. Pradeep Solomon Raj, the learned Counsel on behalf of the Appellant filed the Petition for adjournment. Petition allowed. M/s. P. K. PanneerSelvam, the learned Counsel on behalf of the Respondent is present. List to 14.05.2026 fo | ||
| 3757 | 260/2025 | 7A | EPF Appeal | P. Ramdas Transport Contractors | APFC, Trichy |
23/10/2025 27/10/2025 19/11/2025 10/12/2025 26/12/2025 20/03/2026 10/04/2026 14/05/2026 |
(Time Bound Appeal) M/s. Pradeep Solomon Raj, the learned Counsel on behalf of the Appellant filed the Petition for adjournment. Petition allowed. M/s. P. K. PanneerSelvam, the learned Counsel on behalf of the Respondent is present. List to 14.05.2026 fo | ||
| 3758 | 260/2025 | 7A | EPF Appeal | P. Ramdas Transport Contractors | APFC, Trichy |
23/10/2025 27/10/2025 19/11/2025 10/12/2025 26/12/2025 20/03/2026 10/04/2026 14/05/2026 |
(Time Bound Appeal) M/s. Pradeep Solomon Raj, the learned Counsel on behalf of the Appellant filed the Petition for adjournment. Petition allowed. M/s. P. K. PanneerSelvam, the learned Counsel on behalf of the Respondent is present. List to 14.05.2026 fo | ||
| 3759 | Cause List CGIT 02 Delhi-ID Matters, dated-25.08.2025 Before P.O. Hearing Time 11:00 A.M. Onward | ID | 25/08/2025 | Download | |||||
| 3760 | Cause List CGIT 02 Delhi-ID Matters, dated-21.08.2025 with next date of hearing | ID | 21/08/2025 | Download | |||||
| 3761 | EPFA No.10/2024 | EPF & MP Act 1952 | EPF Appeal | M/s. Jamshedpur Notified Area Committee Sakchi JNAC Sakchi Jamshedpur | The RPFC-II, Jamshedpur | 14/05/2026 | For hearing on admission | ||
| 3762 | EPFA. No. 8/2024 | EPF & MP Act 1952 | EPF Appeal | M/s. Tenughat Vidyut nigam Ltd. | The RPFC, Ranchi | 21/04/2026 | For final disposal of the appeal | ||
| 3763 | EPFA No.7/2024 | EPF & MP Act 1952 | EPF Appeal | M/s. Aashiana Housing Ltd. | The RPFC, Jamshedpur | 15/05/2026 | For hearing on admission | ||
| 3764 | EPFA No.6/2024 | EPF & MP Act 1952 | EPF Appeal | M/s. Laxmi Enterprises Chakardharpur W. Singhbhum | The RPFC, Ranchi | 13/05/2026 | For Further Proceeding | ||
| 3765 | Cause List CGIT-2 Delhi on 25.08.2025 EPF matters in Room no. 208, Time 02:00 P.M | EPF Appeal | 25/08/2025 | Download | |||||
| 3766 | Cause List Cause List CGIT-I Delhi on 25.08.2025 EPF matters in Room no. 208, Time 02:00 P.M | EPF Appeal | 25/08/2025 | Download | |||||
| 3767 | EPFA No. 4/2024 | EPF & MP Act 1952 | EPF Appeal | M/s. K.D. Singh Poultries Pvt.Ltd. | The RPFC, Ranchi | 19/06/2026 | For hearing on admision | ||
| 3768 | EPFA No.3/2024 | EPF & MP Act 1952 | EPF Appeal | M/s. Xavier Labour Relation Institute, Jamshedpur | The APFC, Jamshedpur | 08/05/2026 | For hearing of the appeal | ||
| 3769 | CGIT/NGP/Misc./Appl./EPFA/24/2025, CGIT/NGP/EPFA/12/23-24 | CGIT NAGPUR | EPF Appeal | M/s Dwarkadas Mantri Nagari Sahkari Bank Ltd. Jalna | APFC Aurangabad |
05/02/2026 06/05/2026 |
Reply/Objections from the side of respondent | ||
| 3770 | CGIT/NGP/Misc./Appl./EPFA/24/2025, CGIT/NGP/EPFA/12/23-24 | CGIT NAGPUR | EPF Appeal | M/s Dwarkadas Mantri Nagari Sahkari Bank Ltd. Jalna | APFC Aurangabad |
05/02/2026 06/05/2026 |
Reply/Objections from the side of respondent | ||
| 3771 | CGIT/NGP/Misc./Appl./EPFA/22/2025, CGIT/NGP/EPFA/05/21-22 | CGIT NAGPUR | EPF Appeal | M/s Bhandara District Central Cooperative Bank Ltd., Bhandara | RPFC-II, Nagpur |
27/01/2026 12/06/2026 |
Reply/Objections from the side of respondent | ||
| 3772 | CGIT/NGP/Misc./Appl./EPFA/22/2025, CGIT/NGP/EPFA/05/21-22 | CGIT NAGPUR | EPF Appeal | M/s Bhandara District Central Cooperative Bank Ltd., Bhandara | RPFC-II, Nagpur |
27/01/2026 12/06/2026 |
Reply/Objections from the side of respondent | ||
| 3773 | CGIT/NGP/Misc./Appl./EPFA/23/2025, CGIT/NGP/EPFA/11/21-22 | CGIT NAGPUR | EPF Appeal | Shri Suryaprakash Tekchand Demda | EPFO Aurangabad & 2 Others |
30/01/2026 22/06/2026 |
Reply by the respondent | ||
| 3774 | CGIT/NGP/Misc./Appl./EPFA/23/2025, CGIT/NGP/EPFA/11/21-22 | CGIT NAGPUR | EPF Appeal | Shri Suryaprakash Tekchand Demda | EPFO Aurangabad & 2 Others |
30/01/2026 22/06/2026 |
Reply by the respondent | ||
| 3775 | EPFA No. 2/2024 | EPF & MP Act 1952 | EPF Appeal | M/s. Chaudhary Construction Argora Ranchi | The RPFC, Ranchi | 23/04/2026 | For hearing on admission | ||
| 3776 | EPFA No. 13/2025 | Under Section 7-A, EPF & MP Act 1952 | EPF Appeal | M/s. Jharkhand Rajya Gramin Bank | The RPFC, Ranchi | 21/04/2026 | For hearing on final disposal | ||
| 3777 | EPFA No. 11/2025 | Under Section 7-A, EPF & MP Act 1952 | EPF Appeal | M/S. ICAR-CRRI-Central Rainfed Upland Rice Research Station | The APFC, Ranchi | 24/04/2026 | For hearing on admission | ||
| 3778 | CGIT-1/EPFA - 77 OF 2025 | 7A & 7B | EPF Appeal | M/s Jaswant And Company | APFC, Kandivali |
24/12/2025 27/02/2026 21/05/2026 |
Six Week counter two weeks rejoinder thereafter | ||
| 3779 | CGIT-1/EPFA - 77 OF 2025 | 7A & 7B | EPF Appeal | M/s Jaswant And Company | APFC, Kandivali |
24/12/2025 27/02/2026 21/05/2026 |
Six Week counter two weeks rejoinder thereafter | ||
| 3780 | CGIT-1/EPFA - 77 OF 2025 | 7A & 7B | EPF Appeal | M/s Jaswant And Company | APFC, Kandivali |
24/12/2025 27/02/2026 21/05/2026 |
Six Week counter two weeks rejoinder thereafter | ||
| 3781 | Cause List CGIT-I Delhi on 22.08.2025 ID matters. | ID | 22/08/2025 | Download | |||||
| 3782 | Cause List CGIT-I Delhi on 21.08.2025 ID matters. With Updated Next Date of Hearing. | ID | 21/08/2025 | Download | |||||
| 3783 | Cause List Cause List CGIT-I Delhi on 22.08.2025 EPF matters in Room no. 208, Time 02:00 P.M | EPF Appeal | 22/08/2025 | Download | |||||
| 3784 | MA No. 10/2025 | u/s 7 I | EPF Appeal | FCI, Ludhiana | RPFC-II, Ludhiana | 23/05/2025 | Disposed Off | ||
| 3785 | MA No.09/2025 | u/s 7 I | EPF Appeal | A.B. Wines | EPFO, Ludhiana | 28/04/2025 | decided | ||
| 3786 | MA No.08/2025 | u/s 7 I | EPF Appeal | FCI, Sangrur. | RPFC, Bathinda | 23/07/2025 | decided | ||
| 3787 | MA No.07/2025 | u/s 7 I | EPF Appeal | FCI Category and employees Union | RPFC, Bathinda | 23/07/2025 | decided | ||
| 3788 | MA No.16/2025 | u/s 7 I | EPF Appeal | M/S Rainbow Environments Pvt. Ltd. | RPFC, Chandigarh | 28/07/2025 | Disposed Off | ||
| 3789 | LCA No. 05/2025 | U/S 33-C(2) | Dan Singh | Pb. & Sind Bank | 21/07/2026 | ||||
| 3790 | ID. No. 26/2025 | U/S 2A | ID | Harjinder Singh | Ambuja Cement | 06/07/2026 | |||
| 3791 | Cause List CGIT-I Delhi on 21.08.2025 ID matters. | ID | 21/08/2025 | Download | |||||
| 3792 | Cause List CGIT-I Delhi on 20.08.2025 ID matters. With Updated Next Date of Hearing. | ID | 20/08/2025 | Download | |||||
| 3793 | Cause List CGIT-2 Delhi on 21.08.2025 EPF matters in Room no. 208, Time 02:00 P.M | EPF Appeal | 21/08/2025 | Download | |||||
| 3794 | Cause List Cause List CGIT-I Delhi on 21.08.2025 EPF matters in Room no. 208, Time 02:00 P.M | EPF Appeal | 21/08/2025 | Download | |||||
| 3795 | Cause List CGIT 02 Delhi-ID Matters, dated-21.08.2025 Before P.O. Hearing Time 11:00 A.M. Onward | ID | 21/08/2025 | Download | |||||
| 3796 | 284/2025 | 7Q | EPF Appeal | Asian House | RPFC-II, Puducherry | 26/09/2025 | Final Order - The Appeal stands dismissed. | ||
| 3797 | 283/2025 | 7A | EPF Appeal | P. Radhakrishnan | APFC(C&R), Ambattur |
26/09/2025 13/11/2025 17/11/2025 19/12/2025 22/12/2025 |
Final Order - The Appeal stands dismissed on point of limitation. | ||
| 3798 | 283/2025 | 7A | EPF Appeal | P. Radhakrishnan | APFC(C&R), Ambattur |
26/09/2025 13/11/2025 17/11/2025 19/12/2025 22/12/2025 |
Final Order - The Appeal stands dismissed on point of limitation. | ||
| 3799 | 283/2025 | 7A | EPF Appeal | P. Radhakrishnan | APFC(C&R), Ambattur |
26/09/2025 13/11/2025 17/11/2025 19/12/2025 22/12/2025 |
Final Order - The Appeal stands dismissed on point of limitation. | ||
| 3800 | 283/2025 | 7A | EPF Appeal | P. Radhakrishnan | APFC(C&R), Ambattur |
26/09/2025 13/11/2025 17/11/2025 19/12/2025 22/12/2025 |
Final Order - The Appeal stands dismissed on point of limitation. |