Cause List
| S.No. | Case No. | Subject | Case Type | Name of Appellant | Respondent | Next Date | Details | Order / Decision | Edit |
|---|---|---|---|---|---|---|---|---|---|
| 49401 | 23/2001 | CGIT/NGP | ID | HargovindSingh | I.B.P |
08/04/2024 11/06/2024 15/07/2024 30/09/2024 13/12/2024 10/02/2025 11/03/2025 |
Award passed | ||
| 49402 | 7/2020 | 14B | EPF Appeal | Sree Services | APFC, Trichy |
07/11/2024 13/02/2025 08/05/2025 06/08/2025 15/10/2025 16/01/2026 16/04/2026 |
M/s. M. Aishwariya, the learned Counsel for the Appellant is present. M/s. R. Meenakshi, the learned Counsel on behalf of the Respondent is present. Heard the learned Counsels appearing for the Appellant and the Respondent. For Orders. | ||
| 49403 | 7/2020 | 14B | EPF Appeal | Sree Services | APFC, Trichy |
07/11/2024 13/02/2025 08/05/2025 06/08/2025 15/10/2025 16/01/2026 16/04/2026 |
M/s. M. Aishwariya, the learned Counsel for the Appellant is present. M/s. R. Meenakshi, the learned Counsel on behalf of the Respondent is present. Heard the learned Counsels appearing for the Appellant and the Respondent. For Orders. | ||
| 49404 | 7/2020 | 14B | EPF Appeal | Sree Services | APFC, Trichy |
07/11/2024 13/02/2025 08/05/2025 06/08/2025 15/10/2025 16/01/2026 16/04/2026 |
M/s. M. Aishwariya, the learned Counsel for the Appellant is present. M/s. R. Meenakshi, the learned Counsel on behalf of the Respondent is present. Heard the learned Counsels appearing for the Appellant and the Respondent. For Orders. | ||
| 49405 | 7/2020 | 14B | EPF Appeal | Sree Services | APFC, Trichy |
07/11/2024 13/02/2025 08/05/2025 06/08/2025 15/10/2025 16/01/2026 16/04/2026 |
M/s. M. Aishwariya, the learned Counsel for the Appellant is present. M/s. R. Meenakshi, the learned Counsel on behalf of the Respondent is present. Heard the learned Counsels appearing for the Appellant and the Respondent. For Orders. | ||
| 49406 | 7/2020 | 14B | EPF Appeal | Sree Services | APFC, Trichy |
07/11/2024 13/02/2025 08/05/2025 06/08/2025 15/10/2025 16/01/2026 16/04/2026 |
M/s. M. Aishwariya, the learned Counsel for the Appellant is present. M/s. R. Meenakshi, the learned Counsel on behalf of the Respondent is present. Heard the learned Counsels appearing for the Appellant and the Respondent. For Orders. | ||
| 49407 | 7/2020 | 14B | EPF Appeal | Sree Services | APFC, Trichy |
07/11/2024 13/02/2025 08/05/2025 06/08/2025 15/10/2025 16/01/2026 16/04/2026 |
M/s. M. Aishwariya, the learned Counsel for the Appellant is present. M/s. R. Meenakshi, the learned Counsel on behalf of the Respondent is present. Heard the learned Counsels appearing for the Appellant and the Respondent. For Orders. | ||
| 49408 | 7/2020 | 14B | EPF Appeal | Sree Services | APFC, Trichy |
07/11/2024 13/02/2025 08/05/2025 06/08/2025 15/10/2025 16/01/2026 16/04/2026 |
M/s. M. Aishwariya, the learned Counsel for the Appellant is present. M/s. R. Meenakshi, the learned Counsel on behalf of the Respondent is present. Heard the learned Counsels appearing for the Appellant and the Respondent. For Orders. | ||
| 49409 | 6/2020 | 14B | EPF Appeal | Good Shepherd College of Education | APFC, Nagercoil |
12/03/2020 12/06/2020 14/08/2020 23/12/2020 24/05/2021 20/10/2021 07/02/2022 19/04/2022 12/05/2022 08/08/2023 |
Final Order-The Appeal stands dismissed on the point of limitation. | ||
| 49410 | 6/2020 | 14B | EPF Appeal | Good Shepherd College of Education | APFC, Nagercoil |
12/03/2020 12/06/2020 14/08/2020 23/12/2020 24/05/2021 20/10/2021 07/02/2022 19/04/2022 12/05/2022 08/08/2023 |
Final Order-The Appeal stands dismissed on the point of limitation. | ||
| 49411 | 6/2020 | 14B | EPF Appeal | Good Shepherd College of Education | APFC, Nagercoil |
12/03/2020 12/06/2020 14/08/2020 23/12/2020 24/05/2021 20/10/2021 07/02/2022 19/04/2022 12/05/2022 08/08/2023 |
Final Order-The Appeal stands dismissed on the point of limitation. | ||
| 49412 | 6/2020 | 14B | EPF Appeal | Good Shepherd College of Education | APFC, Nagercoil |
12/03/2020 12/06/2020 14/08/2020 23/12/2020 24/05/2021 20/10/2021 07/02/2022 19/04/2022 12/05/2022 08/08/2023 |
Final Order-The Appeal stands dismissed on the point of limitation. | ||
| 49413 | 6/2020 | 14B | EPF Appeal | Good Shepherd College of Education | APFC, Nagercoil |
12/03/2020 12/06/2020 14/08/2020 23/12/2020 24/05/2021 20/10/2021 07/02/2022 19/04/2022 12/05/2022 08/08/2023 |
Final Order-The Appeal stands dismissed on the point of limitation. | ||
| 49414 | 6/2020 | 14B | EPF Appeal | Good Shepherd College of Education | APFC, Nagercoil |
12/03/2020 12/06/2020 14/08/2020 23/12/2020 24/05/2021 20/10/2021 07/02/2022 19/04/2022 12/05/2022 08/08/2023 |
Final Order-The Appeal stands dismissed on the point of limitation. | ||
| 49415 | 6/2020 | 14B | EPF Appeal | Good Shepherd College of Education | APFC, Nagercoil |
12/03/2020 12/06/2020 14/08/2020 23/12/2020 24/05/2021 20/10/2021 07/02/2022 19/04/2022 12/05/2022 08/08/2023 |
Final Order-The Appeal stands dismissed on the point of limitation. | ||
| 49416 | 6/2020 | 14B | EPF Appeal | Good Shepherd College of Education | APFC, Nagercoil |
12/03/2020 12/06/2020 14/08/2020 23/12/2020 24/05/2021 20/10/2021 07/02/2022 19/04/2022 12/05/2022 08/08/2023 |
Final Order-The Appeal stands dismissed on the point of limitation. | ||
| 49417 | 6/2020 | 14B | EPF Appeal | Good Shepherd College of Education | APFC, Nagercoil |
12/03/2020 12/06/2020 14/08/2020 23/12/2020 24/05/2021 20/10/2021 07/02/2022 19/04/2022 12/05/2022 08/08/2023 |
Final Order-The Appeal stands dismissed on the point of limitation. | ||
| 49418 | 6/2020 | 14B | EPF Appeal | Good Shepherd College of Education | APFC, Nagercoil |
12/03/2020 12/06/2020 14/08/2020 23/12/2020 24/05/2021 20/10/2021 07/02/2022 19/04/2022 12/05/2022 08/08/2023 |
Final Order-The Appeal stands dismissed on the point of limitation. | ||
| 49419 | 5/2020 | 14B | EPF Appeal | First Man Management Services Pvt. Ltd., | RPFC-I, Trichy |
03/06/2024 09/09/2024 09/12/2024 22/01/2025 24/04/2025 23/07/2025 19/09/2025 10/10/2025 |
Final Order - The Appeal is partly allowed. The Respondent is directed to recover only 80% of assessed damages amount. | ||
| 49420 | 5/2020 | 14B | EPF Appeal | First Man Management Services Pvt. Ltd., | RPFC-I, Trichy |
03/06/2024 09/09/2024 09/12/2024 22/01/2025 24/04/2025 23/07/2025 19/09/2025 10/10/2025 |
Final Order - The Appeal is partly allowed. The Respondent is directed to recover only 80% of assessed damages amount. | ||
| 49421 | 5/2020 | 14B | EPF Appeal | First Man Management Services Pvt. Ltd., | RPFC-I, Trichy |
03/06/2024 09/09/2024 09/12/2024 22/01/2025 24/04/2025 23/07/2025 19/09/2025 10/10/2025 |
Final Order - The Appeal is partly allowed. The Respondent is directed to recover only 80% of assessed damages amount. | ||
| 49422 | 5/2020 | 14B | EPF Appeal | First Man Management Services Pvt. Ltd., | RPFC-I, Trichy |
03/06/2024 09/09/2024 09/12/2024 22/01/2025 24/04/2025 23/07/2025 19/09/2025 10/10/2025 |
Final Order - The Appeal is partly allowed. The Respondent is directed to recover only 80% of assessed damages amount. | ||
| 49423 | 5/2020 | 14B | EPF Appeal | First Man Management Services Pvt. Ltd., | RPFC-I, Trichy |
03/06/2024 09/09/2024 09/12/2024 22/01/2025 24/04/2025 23/07/2025 19/09/2025 10/10/2025 |
Final Order - The Appeal is partly allowed. The Respondent is directed to recover only 80% of assessed damages amount. | ||
| 49424 | 5/2020 | 14B | EPF Appeal | First Man Management Services Pvt. Ltd., | RPFC-I, Trichy |
03/06/2024 09/09/2024 09/12/2024 22/01/2025 24/04/2025 23/07/2025 19/09/2025 10/10/2025 |
Final Order - The Appeal is partly allowed. The Respondent is directed to recover only 80% of assessed damages amount. | ||
| 49425 | 5/2020 | 14B | EPF Appeal | First Man Management Services Pvt. Ltd., | RPFC-I, Trichy |
03/06/2024 09/09/2024 09/12/2024 22/01/2025 24/04/2025 23/07/2025 19/09/2025 10/10/2025 |
Final Order - The Appeal is partly allowed. The Respondent is directed to recover only 80% of assessed damages amount. | ||
| 49426 | 5/2020 | 14B | EPF Appeal | First Man Management Services Pvt. Ltd., | RPFC-I, Trichy |
03/06/2024 09/09/2024 09/12/2024 22/01/2025 24/04/2025 23/07/2025 19/09/2025 10/10/2025 |
Final Order - The Appeal is partly allowed. The Respondent is directed to recover only 80% of assessed damages amount. | ||
| 49427 | 4/2020 | 14B | EPF Appeal | Raju Spinning Mills Pvt. Ltd., | APFC, Madurai |
12/10/2023 14/03/2024 21/06/2024 07/10/2024 06/01/2025 07/04/2025 07/07/2025 02/09/2025 27/11/2025 05/03/2026 |
Final Order - Waived 32% of assessed amount passed by Respondent order dtd 12.12.2019. Respondent will recover remaining 68% of assessed amount from Appellant in accordance with law. | ||
| 49428 | 4/2020 | 14B | EPF Appeal | Raju Spinning Mills Pvt. Ltd., | APFC, Madurai |
12/10/2023 14/03/2024 21/06/2024 07/10/2024 06/01/2025 07/04/2025 07/07/2025 02/09/2025 27/11/2025 05/03/2026 |
Final Order - Waived 32% of assessed amount passed by Respondent order dtd 12.12.2019. Respondent will recover remaining 68% of assessed amount from Appellant in accordance with law. | ||
| 49429 | 4/2020 | 14B | EPF Appeal | Raju Spinning Mills Pvt. Ltd., | APFC, Madurai |
12/10/2023 14/03/2024 21/06/2024 07/10/2024 06/01/2025 07/04/2025 07/07/2025 02/09/2025 27/11/2025 05/03/2026 |
Final Order - Waived 32% of assessed amount passed by Respondent order dtd 12.12.2019. Respondent will recover remaining 68% of assessed amount from Appellant in accordance with law. | ||
| 49430 | 4/2020 | 14B | EPF Appeal | Raju Spinning Mills Pvt. Ltd., | APFC, Madurai |
12/10/2023 14/03/2024 21/06/2024 07/10/2024 06/01/2025 07/04/2025 07/07/2025 02/09/2025 27/11/2025 05/03/2026 |
Final Order - Waived 32% of assessed amount passed by Respondent order dtd 12.12.2019. Respondent will recover remaining 68% of assessed amount from Appellant in accordance with law. | ||
| 49431 | 4/2020 | 14B | EPF Appeal | Raju Spinning Mills Pvt. Ltd., | APFC, Madurai |
12/10/2023 14/03/2024 21/06/2024 07/10/2024 06/01/2025 07/04/2025 07/07/2025 02/09/2025 27/11/2025 05/03/2026 |
Final Order - Waived 32% of assessed amount passed by Respondent order dtd 12.12.2019. Respondent will recover remaining 68% of assessed amount from Appellant in accordance with law. | ||
| 49432 | 4/2020 | 14B | EPF Appeal | Raju Spinning Mills Pvt. Ltd., | APFC, Madurai |
12/10/2023 14/03/2024 21/06/2024 07/10/2024 06/01/2025 07/04/2025 07/07/2025 02/09/2025 27/11/2025 05/03/2026 |
Final Order - Waived 32% of assessed amount passed by Respondent order dtd 12.12.2019. Respondent will recover remaining 68% of assessed amount from Appellant in accordance with law. | ||
| 49433 | 4/2020 | 14B | EPF Appeal | Raju Spinning Mills Pvt. Ltd., | APFC, Madurai |
12/10/2023 14/03/2024 21/06/2024 07/10/2024 06/01/2025 07/04/2025 07/07/2025 02/09/2025 27/11/2025 05/03/2026 |
Final Order - Waived 32% of assessed amount passed by Respondent order dtd 12.12.2019. Respondent will recover remaining 68% of assessed amount from Appellant in accordance with law. | ||
| 49434 | 4/2020 | 14B | EPF Appeal | Raju Spinning Mills Pvt. Ltd., | APFC, Madurai |
12/10/2023 14/03/2024 21/06/2024 07/10/2024 06/01/2025 07/04/2025 07/07/2025 02/09/2025 27/11/2025 05/03/2026 |
Final Order - Waived 32% of assessed amount passed by Respondent order dtd 12.12.2019. Respondent will recover remaining 68% of assessed amount from Appellant in accordance with law. | ||
| 49435 | 4/2020 | 14B | EPF Appeal | Raju Spinning Mills Pvt. Ltd., | APFC, Madurai |
12/10/2023 14/03/2024 21/06/2024 07/10/2024 06/01/2025 07/04/2025 07/07/2025 02/09/2025 27/11/2025 05/03/2026 |
Final Order - Waived 32% of assessed amount passed by Respondent order dtd 12.12.2019. Respondent will recover remaining 68% of assessed amount from Appellant in accordance with law. | ||
| 49436 | 4/2020 | 14B | EPF Appeal | Raju Spinning Mills Pvt. Ltd., | APFC, Madurai |
12/10/2023 14/03/2024 21/06/2024 07/10/2024 06/01/2025 07/04/2025 07/07/2025 02/09/2025 27/11/2025 05/03/2026 |
Final Order - Waived 32% of assessed amount passed by Respondent order dtd 12.12.2019. Respondent will recover remaining 68% of assessed amount from Appellant in accordance with law. | ||
| 49437 | 3/2020 | 7A | EPF Appeal | Fahim Tanning | APFC, Vellore |
09/04/2021 10/09/2021 23/11/2021 24/01/2022 11/02/2022 11/03/2022 22/03/2022 24/03/2022 28/03/2022 |
Final Order - The Appeal stands dismissed. | ||
| 49438 | 3/2020 | 7A | EPF Appeal | Fahim Tanning | APFC, Vellore |
09/04/2021 10/09/2021 23/11/2021 24/01/2022 11/02/2022 11/03/2022 22/03/2022 24/03/2022 28/03/2022 |
Final Order - The Appeal stands dismissed. | ||
| 49439 | 3/2020 | 7A | EPF Appeal | Fahim Tanning | APFC, Vellore |
09/04/2021 10/09/2021 23/11/2021 24/01/2022 11/02/2022 11/03/2022 22/03/2022 24/03/2022 28/03/2022 |
Final Order - The Appeal stands dismissed. | ||
| 49440 | 3/2020 | 7A | EPF Appeal | Fahim Tanning | APFC, Vellore |
09/04/2021 10/09/2021 23/11/2021 24/01/2022 11/02/2022 11/03/2022 22/03/2022 24/03/2022 28/03/2022 |
Final Order - The Appeal stands dismissed. | ||
| 49441 | 3/2020 | 7A | EPF Appeal | Fahim Tanning | APFC, Vellore |
09/04/2021 10/09/2021 23/11/2021 24/01/2022 11/02/2022 11/03/2022 22/03/2022 24/03/2022 28/03/2022 |
Final Order - The Appeal stands dismissed. | ||
| 49442 | 3/2020 | 7A | EPF Appeal | Fahim Tanning | APFC, Vellore |
09/04/2021 10/09/2021 23/11/2021 24/01/2022 11/02/2022 11/03/2022 22/03/2022 24/03/2022 28/03/2022 |
Final Order - The Appeal stands dismissed. | ||
| 49443 | 3/2020 | 7A | EPF Appeal | Fahim Tanning | APFC, Vellore |
09/04/2021 10/09/2021 23/11/2021 24/01/2022 11/02/2022 11/03/2022 22/03/2022 24/03/2022 28/03/2022 |
Final Order - The Appeal stands dismissed. | ||
| 49444 | 3/2020 | 7A | EPF Appeal | Fahim Tanning | APFC, Vellore |
09/04/2021 10/09/2021 23/11/2021 24/01/2022 11/02/2022 11/03/2022 22/03/2022 24/03/2022 28/03/2022 |
Final Order - The Appeal stands dismissed. | ||
| 49445 | 3/2020 | 7A | EPF Appeal | Fahim Tanning | APFC, Vellore |
09/04/2021 10/09/2021 23/11/2021 24/01/2022 11/02/2022 11/03/2022 22/03/2022 24/03/2022 28/03/2022 |
Final Order - The Appeal stands dismissed. | ||
| 49446 | 2/2020 | 14B | EPF Appeal | Sahana Textiles | RPFC-II, Madurai |
18/11/2024 25/02/2025 20/05/2025 18/08/2025 31/10/2025 02/02/2026 |
(Special Campaign) Final Order - The Appeal is partly allowed. 30% of the assessed amount is waived off. The Respondent is directed to recover only 70% of the assessed amount of damages u/s. 14B of the Act. | ||
| 49447 | 2/2020 | 14B | EPF Appeal | Sahana Textiles | RPFC-II, Madurai |
18/11/2024 25/02/2025 20/05/2025 18/08/2025 31/10/2025 02/02/2026 |
(Special Campaign) Final Order - The Appeal is partly allowed. 30% of the assessed amount is waived off. The Respondent is directed to recover only 70% of the assessed amount of damages u/s. 14B of the Act. | ||
| 49448 | 2/2020 | 14B | EPF Appeal | Sahana Textiles | RPFC-II, Madurai |
18/11/2024 25/02/2025 20/05/2025 18/08/2025 31/10/2025 02/02/2026 |
(Special Campaign) Final Order - The Appeal is partly allowed. 30% of the assessed amount is waived off. The Respondent is directed to recover only 70% of the assessed amount of damages u/s. 14B of the Act. | ||
| 49449 | 2/2020 | 14B | EPF Appeal | Sahana Textiles | RPFC-II, Madurai |
18/11/2024 25/02/2025 20/05/2025 18/08/2025 31/10/2025 02/02/2026 |
(Special Campaign) Final Order - The Appeal is partly allowed. 30% of the assessed amount is waived off. The Respondent is directed to recover only 70% of the assessed amount of damages u/s. 14B of the Act. | ||
| 49450 | 2/2020 | 14B | EPF Appeal | Sahana Textiles | RPFC-II, Madurai |
18/11/2024 25/02/2025 20/05/2025 18/08/2025 31/10/2025 02/02/2026 |
(Special Campaign) Final Order - The Appeal is partly allowed. 30% of the assessed amount is waived off. The Respondent is directed to recover only 70% of the assessed amount of damages u/s. 14B of the Act. |