Cause List
| S.No. | Case No. | Subject | Case Type | Name of Appellant | Respondent | Next Date | Details | Order / Decision | Edit |
|---|---|---|---|---|---|---|---|---|---|
| 74201 | 308/2018 | 14B | EPF Appeal | McCoy Clothing Pvt. Ltd. | RPFC, Tambaram |
26/09/2024 27/12/2024 27/03/2025 26/06/2025 26/08/2025 20/11/2025 26/02/2026 |
(Special Campaign) Final Order - Waived 35% of assessed amount passed by Respondent order dtd 31.10.2016 Respondent will recover remaining 65% of assessed amount from Appellant in accordance with law | ||
| 74202 | 305/2018 | 14B | EPF Appeal | Adonis Manufacturing Pvt. Ltd. | APFC, Chennai |
23/10/2024 21/01/2025 22/04/2025 21/07/2025 16/09/2025 19/12/2025 03/02/2026 |
(Special Campaign) Final Order - The Appeal is partly allowed. 32% of the assessed amount is waived off. The Respondent is directed to recover only 68% of the assessed amount of damages u/s. 14B of the Act. | ||
| 74203 | 305/2018 | 14B | EPF Appeal | Adonis Manufacturing Pvt. Ltd. | APFC, Chennai |
23/10/2024 21/01/2025 22/04/2025 21/07/2025 16/09/2025 19/12/2025 03/02/2026 |
(Special Campaign) Final Order - The Appeal is partly allowed. 32% of the assessed amount is waived off. The Respondent is directed to recover only 68% of the assessed amount of damages u/s. 14B of the Act. | ||
| 74204 | 305/2018 | 14B | EPF Appeal | Adonis Manufacturing Pvt. Ltd. | APFC, Chennai |
23/10/2024 21/01/2025 22/04/2025 21/07/2025 16/09/2025 19/12/2025 03/02/2026 |
(Special Campaign) Final Order - The Appeal is partly allowed. 32% of the assessed amount is waived off. The Respondent is directed to recover only 68% of the assessed amount of damages u/s. 14B of the Act. | ||
| 74205 | 305/2018 | 14B | EPF Appeal | Adonis Manufacturing Pvt. Ltd. | APFC, Chennai |
23/10/2024 21/01/2025 22/04/2025 21/07/2025 16/09/2025 19/12/2025 03/02/2026 |
(Special Campaign) Final Order - The Appeal is partly allowed. 32% of the assessed amount is waived off. The Respondent is directed to recover only 68% of the assessed amount of damages u/s. 14B of the Act. | ||
| 74206 | 305/2018 | 14B | EPF Appeal | Adonis Manufacturing Pvt. Ltd. | APFC, Chennai |
23/10/2024 21/01/2025 22/04/2025 21/07/2025 16/09/2025 19/12/2025 03/02/2026 |
(Special Campaign) Final Order - The Appeal is partly allowed. 32% of the assessed amount is waived off. The Respondent is directed to recover only 68% of the assessed amount of damages u/s. 14B of the Act. | ||
| 74207 | 305/2018 | 14B | EPF Appeal | Adonis Manufacturing Pvt. Ltd. | APFC, Chennai |
23/10/2024 21/01/2025 22/04/2025 21/07/2025 16/09/2025 19/12/2025 03/02/2026 |
(Special Campaign) Final Order - The Appeal is partly allowed. 32% of the assessed amount is waived off. The Respondent is directed to recover only 68% of the assessed amount of damages u/s. 14B of the Act. | ||
| 74208 | 305/2018 | 14B | EPF Appeal | Adonis Manufacturing Pvt. Ltd. | APFC, Chennai |
23/10/2024 21/01/2025 22/04/2025 21/07/2025 16/09/2025 19/12/2025 03/02/2026 |
(Special Campaign) Final Order - The Appeal is partly allowed. 32% of the assessed amount is waived off. The Respondent is directed to recover only 68% of the assessed amount of damages u/s. 14B of the Act. | ||
| 74209 | 300/2018 | 7A | EPF Appeal | Hotel Aspin Inn | APFC, Chennai & Another |
09/04/2019 09/08/2019 12/09/2019 04/12/2019 31/01/2020 |
The Appeal stands dismissed as there exist no issue for adjudication. | ||
| 74210 | 300/2018 | 7A | EPF Appeal | Hotel Aspin Inn | APFC, Chennai & Another |
09/04/2019 09/08/2019 12/09/2019 04/12/2019 31/01/2020 |
The Appeal stands dismissed as there exist no issue for adjudication. | ||
| 74211 | 300/2018 | 7A | EPF Appeal | Hotel Aspin Inn | APFC, Chennai & Another |
09/04/2019 09/08/2019 12/09/2019 04/12/2019 31/01/2020 |
The Appeal stands dismissed as there exist no issue for adjudication. | ||
| 74212 | 300/2018 | 7A | EPF Appeal | Hotel Aspin Inn | APFC, Chennai & Another |
09/04/2019 09/08/2019 12/09/2019 04/12/2019 31/01/2020 |
The Appeal stands dismissed as there exist no issue for adjudication. | ||
| 74213 | 300/2018 | 7A | EPF Appeal | Hotel Aspin Inn | APFC, Chennai & Another |
09/04/2019 09/08/2019 12/09/2019 04/12/2019 31/01/2020 |
The Appeal stands dismissed as there exist no issue for adjudication. | ||
| 74214 | 272/2018 | 14B-7Q | EPF Appeal | W.S. Industries (India) Ltd. | RPFC-II, Chennai |
27/02/2025 22/05/2025 21/08/2025 03/09/2025 12/09/2025 15/09/2025 26/09/2025 09/10/2025 28/10/2025 |
Final Orders - The Appeal is partly allowed. The Respondent is directed to recover only 65% of assessed damages amount. | ||
| 74215 | 272/2018 | 14B-7Q | EPF Appeal | W.S. Industries (India) Ltd. | RPFC-II, Chennai |
27/02/2025 22/05/2025 21/08/2025 03/09/2025 12/09/2025 15/09/2025 26/09/2025 09/10/2025 28/10/2025 |
Final Orders - The Appeal is partly allowed. The Respondent is directed to recover only 65% of assessed damages amount. | ||
| 74216 | 272/2018 | 14B-7Q | EPF Appeal | W.S. Industries (India) Ltd. | RPFC-II, Chennai |
27/02/2025 22/05/2025 21/08/2025 03/09/2025 12/09/2025 15/09/2025 26/09/2025 09/10/2025 28/10/2025 |
Final Orders - The Appeal is partly allowed. The Respondent is directed to recover only 65% of assessed damages amount. | ||
| 74217 | 272/2018 | 14B-7Q | EPF Appeal | W.S. Industries (India) Ltd. | RPFC-II, Chennai |
27/02/2025 22/05/2025 21/08/2025 03/09/2025 12/09/2025 15/09/2025 26/09/2025 09/10/2025 28/10/2025 |
Final Orders - The Appeal is partly allowed. The Respondent is directed to recover only 65% of assessed damages amount. | ||
| 74218 | 272/2018 | 14B-7Q | EPF Appeal | W.S. Industries (India) Ltd. | RPFC-II, Chennai |
27/02/2025 22/05/2025 21/08/2025 03/09/2025 12/09/2025 15/09/2025 26/09/2025 09/10/2025 28/10/2025 |
Final Orders - The Appeal is partly allowed. The Respondent is directed to recover only 65% of assessed damages amount. | ||
| 74219 | 272/2018 | 14B-7Q | EPF Appeal | W.S. Industries (India) Ltd. | RPFC-II, Chennai |
27/02/2025 22/05/2025 21/08/2025 03/09/2025 12/09/2025 15/09/2025 26/09/2025 09/10/2025 28/10/2025 |
Final Orders - The Appeal is partly allowed. The Respondent is directed to recover only 65% of assessed damages amount. | ||
| 74220 | 272/2018 | 14B-7Q | EPF Appeal | W.S. Industries (India) Ltd. | RPFC-II, Chennai |
27/02/2025 22/05/2025 21/08/2025 03/09/2025 12/09/2025 15/09/2025 26/09/2025 09/10/2025 28/10/2025 |
Final Orders - The Appeal is partly allowed. The Respondent is directed to recover only 65% of assessed damages amount. | ||
| 74221 | 272/2018 | 14B-7Q | EPF Appeal | W.S. Industries (India) Ltd. | RPFC-II, Chennai |
27/02/2025 22/05/2025 21/08/2025 03/09/2025 12/09/2025 15/09/2025 26/09/2025 09/10/2025 28/10/2025 |
Final Orders - The Appeal is partly allowed. The Respondent is directed to recover only 65% of assessed damages amount. | ||
| 74222 | 272/2018 | 14B-7Q | EPF Appeal | W.S. Industries (India) Ltd. | RPFC-II, Chennai |
27/02/2025 22/05/2025 21/08/2025 03/09/2025 12/09/2025 15/09/2025 26/09/2025 09/10/2025 28/10/2025 |
Final Orders - The Appeal is partly allowed. The Respondent is directed to recover only 65% of assessed damages amount. | ||
| 74223 | 91/2015 | 10 (1) (d) | ID | BAP Mazdoor Sangam(BMS) | BHEL | 09/04/2019 | Argument | ||
| 74224 | 11/2016 | 10 (1) (d) | ID | "ONGC All Employees Union " | ONGC Ltd. | 09/04/2019 | Enquiry | ||
| 74225 | 70/2017 | 2A2 | ID | K.Balasubramanian | IOB | 09/04/2019 | Enquiry | ||
| 74226 | 14/2017 | 2A2 | ID | S.Anbarasu | ONGC Ltd. | 09/04/2019 | Enquiry | ||
| 74227 | 47/2016 | 10 (1) (d) | ID | Indian Bank Employees Union | Indian Bank | 09/04/2019 | Enquiry | ||
| 74228 | 10/2016 | 10 (1) (d) | ID | B.Velayutham | Indian Overseas Bank | 09/04/2019 | Enquiry | ||
| 74229 | 308/2001 batch & 349/2001 batch | 10 (1) (d) | ID | Sh.V.Dharani & 30 others | Batch Of Garrison | 09/04/2019 | Enquiry | ||
| 74230 | 47/2018 | 2A2 | ID | Sh.M.BalaSubramanian | State Bank of India | 09/04/2019 | Counter | ||
| 74231 | 46/2018 | 2A2 | ID | Smt.M.Muthulakshmi | Central Bank of India | 09/04/2019 | Counter | ||
| 74232 | 45/2018 | 2A2 | ID | Smt.R.Lakshmi | The Br. Manager, BOB | 09/04/2019 | Counter | ||
| 74233 | Ref. 1/2019 | Denying Upgradation | ID | From Unskilled worker to skilled worker | The GM SAIL, Bokaro | 07/05/2026 | WS by the management | ||
| 74234 | Ref. 17/2018 | ID Act 2A 1947 | ID | Sri Prakash Bhuia | The GM Bastacolla Area of M/s BCCL | 15/04/2026 | For appearance and argument | ||
| 74235 | Ref. 16/2018 | ID Act 2A 1947 | ID | Sri Arjun BP | The GM, Barora Area No.1 of M/s. BCCL | 09/04/2026 | For appearance | ||
| 74236 | Application No. LC 1/2012 | claim of wages | ID | Shri Pelu Kora and 24 others | The GM, Govinpur Area of M/s BCCL | 08/04/2026 | Evidence of worman | ||
| 74237 | Ref. 6/2019 | Under Ground Allowance | ID | Sri Kumar Ch. Mahato & 36 others | The GM , Mugma Area of M/s ECL | 01/10/2019 | WS of workman | ||
| 74238 | Ref. 14/2018 | Rgularisation | ID | Sri Jai Mangal Singh | The GM, Barora Area No.1 of M/s. BCCL | 26/09/2019 | W.S by workman | ||
| 74239 | Ref. 19/2018 | IDAct U/s 2-A 1947 | ID | Sri Paresh Kumar Ravidas | The GM Bastacolla Area of M/s BCCL | 26/09/2019 | WS. By management | ||
| 74240 | Application No. LC 4/2013 | claim of wages | Shri Narayan Singh & Ors. | The GM, Bhurkunda Area of M/s CCL | 29/08/2019 | filing documents by Management | |||
| 74241 | Application No. LC 5/2013 | claim of wages | Shri Pradeep Kr. Roy | Sri J.K. Sagar, Welfare and Cess Commiss.Labour Welfare Org. Ministry of Labour, Ranchi | 29/08/2019 | Cross-examination of WW-I | |||
| 74242 | Application No. LC 2/2011 | claim of wages | Smt. Kamli Kamin and Sri Karmu Rawani | The GM, Barora Area of M/s BCCL of M/s. BCCL | 28/08/2019 | Evidence of worman | |||
| 74243 | Application No.LC.1/2007 | claim of wages | Ranjit Singh | Project Officer Muraidih Project of M/S B.C.CL | 27/08/2019 | Filling W.O by OP Management | |||
| 74244 | Application No. LC 1/2011 | claim of wages | Smt. Subh Laxmi Devi | Diretor Peersonnel M/s BCCL Koyla Bhawan, Koyla Nagar Dhanbad. | 27/08/2019 | Hearing Petition | |||
| 74245 | Application No.LC.2/2006 | claim of wages | Doula Miya | GM Moonidih Area Of M/S B.C.C.L | 22/08/2019 | Evidence of OP Management | |||
| 74246 | Application No.LC.3/2006 | claim of wages | Rajrani Devi | GM Katrash area of M/S B.C.C.L | 22/08/2019 | Evidence of Management | |||
| 74247 | Application No LC.1/2005 | claim of wages | Karu Das | Project Offoce Ramkanali | 21/08/2019 | Evidence of petitioner | |||
| 74248 | Applicaton No.LC.1/2004 | claim of wages | Shankar Mahato | ProjectOfficer,nudkhurkee,Colly of M/S B.C.C.L | 20/08/2019 | Hearing Arguement | |||
| 74249 | Application No.LC.2/2004 | claim of wages | Sukhdev Bhuiya | Project Officer Katrash Colly. | 20/08/2019 | Evidence of petitioner | |||
| 74250 | Application No.LC. 9/2002 | claim of wages | Mahangu Ram | The GM Sijua Area,M/SB.C.C.L | 14/08/2019 | Evidence of petitioner |