Cause List

E.g., 08/04/2026
S.No. Case No. Subject Case Type Name of Appellant Respondent Next Date Details Order / Decision Edit
75401 459/2018 14B-7Q EPF Appeal Kwality Spinning Mills Pvt. Ltd. APFC, Coimbatore 10/12/2024
24/01/2025
25/04/2025
24/07/2025
24/09/2025
31/12/2025
02/04/2026
Final Order - 30% of the assessed amount passed by the Respondent order dated 11.02.2016 is waived. The Respondent will recover remaining 70% of the assessed amount from the Appellant establishment in accordance with law.
75402 459/2018 14B-7Q EPF Appeal Kwality Spinning Mills Pvt. Ltd. APFC, Coimbatore 10/12/2024
24/01/2025
25/04/2025
24/07/2025
24/09/2025
31/12/2025
02/04/2026
Final Order - 30% of the assessed amount passed by the Respondent order dated 11.02.2016 is waived. The Respondent will recover remaining 70% of the assessed amount from the Appellant establishment in accordance with law.
75403 459/2018 14B-7Q EPF Appeal Kwality Spinning Mills Pvt. Ltd. APFC, Coimbatore 10/12/2024
24/01/2025
25/04/2025
24/07/2025
24/09/2025
31/12/2025
02/04/2026
Final Order - 30% of the assessed amount passed by the Respondent order dated 11.02.2016 is waived. The Respondent will recover remaining 70% of the assessed amount from the Appellant establishment in accordance with law.
75404 459/2018 14B-7Q EPF Appeal Kwality Spinning Mills Pvt. Ltd. APFC, Coimbatore 10/12/2024
24/01/2025
25/04/2025
24/07/2025
24/09/2025
31/12/2025
02/04/2026
Final Order - 30% of the assessed amount passed by the Respondent order dated 11.02.2016 is waived. The Respondent will recover remaining 70% of the assessed amount from the Appellant establishment in accordance with law.
75405 541/2017 8F EPF Appeal Trippur Surya Hi-Tech Apparel Pvt. Ltd. APFC, Coimbatore 05/04/2019
15/05/2019
Admission/Compliance
75406 541/2017 8F EPF Appeal Trippur Surya Hi-Tech Apparel Pvt. Ltd. APFC, Coimbatore 05/04/2019
15/05/2019
Admission/Compliance
75407 252/2017 14B EPF Appeal R.R. Infraa Constructions APFC, Madurai 29/01/2025
19/03/2025
15/05/2025
02/07/2025
01/09/2025
10/10/2025
09/01/2026
05/02/2026
(Special Campaign) Final Order - The Appeal is partly allowed. 35% of the assessed amount is waived off. The Respondent is directed to recover only 65% of the assessed amount of damages u/s. 14B of the Act.
75408 252/2017 14B EPF Appeal R.R. Infraa Constructions APFC, Madurai 29/01/2025
19/03/2025
15/05/2025
02/07/2025
01/09/2025
10/10/2025
09/01/2026
05/02/2026
(Special Campaign) Final Order - The Appeal is partly allowed. 35% of the assessed amount is waived off. The Respondent is directed to recover only 65% of the assessed amount of damages u/s. 14B of the Act.
75409 252/2017 14B EPF Appeal R.R. Infraa Constructions APFC, Madurai 29/01/2025
19/03/2025
15/05/2025
02/07/2025
01/09/2025
10/10/2025
09/01/2026
05/02/2026
(Special Campaign) Final Order - The Appeal is partly allowed. 35% of the assessed amount is waived off. The Respondent is directed to recover only 65% of the assessed amount of damages u/s. 14B of the Act.
75410 252/2017 14B EPF Appeal R.R. Infraa Constructions APFC, Madurai 29/01/2025
19/03/2025
15/05/2025
02/07/2025
01/09/2025
10/10/2025
09/01/2026
05/02/2026
(Special Campaign) Final Order - The Appeal is partly allowed. 35% of the assessed amount is waived off. The Respondent is directed to recover only 65% of the assessed amount of damages u/s. 14B of the Act.
75411 252/2017 14B EPF Appeal R.R. Infraa Constructions APFC, Madurai 29/01/2025
19/03/2025
15/05/2025
02/07/2025
01/09/2025
10/10/2025
09/01/2026
05/02/2026
(Special Campaign) Final Order - The Appeal is partly allowed. 35% of the assessed amount is waived off. The Respondent is directed to recover only 65% of the assessed amount of damages u/s. 14B of the Act.
75412 252/2017 14B EPF Appeal R.R. Infraa Constructions APFC, Madurai 29/01/2025
19/03/2025
15/05/2025
02/07/2025
01/09/2025
10/10/2025
09/01/2026
05/02/2026
(Special Campaign) Final Order - The Appeal is partly allowed. 35% of the assessed amount is waived off. The Respondent is directed to recover only 65% of the assessed amount of damages u/s. 14B of the Act.
75413 252/2017 14B EPF Appeal R.R. Infraa Constructions APFC, Madurai 29/01/2025
19/03/2025
15/05/2025
02/07/2025
01/09/2025
10/10/2025
09/01/2026
05/02/2026
(Special Campaign) Final Order - The Appeal is partly allowed. 35% of the assessed amount is waived off. The Respondent is directed to recover only 65% of the assessed amount of damages u/s. 14B of the Act.
75414 252/2017 14B EPF Appeal R.R. Infraa Constructions APFC, Madurai 29/01/2025
19/03/2025
15/05/2025
02/07/2025
01/09/2025
10/10/2025
09/01/2026
05/02/2026
(Special Campaign) Final Order - The Appeal is partly allowed. 35% of the assessed amount is waived off. The Respondent is directed to recover only 65% of the assessed amount of damages u/s. 14B of the Act.
75415 677/2018 7A EPF Appeal Vasan Medical Hall RPFC, Trichy 05/04/2019 Admission
75416 161/2018 7A EPF Appeal G.B. Engg. Enterprises Pvt. Ltd., RPFC, Trichy 29/11/2021
24/12/2021
05/01/2022
13/01/2022
18/01/2022
Final Order-The Appeal stands dismissed for non-compliance.
75417 161/2018 7A EPF Appeal G.B. Engg. Enterprises Pvt. Ltd., RPFC, Trichy 29/11/2021
24/12/2021
05/01/2022
13/01/2022
18/01/2022
Final Order-The Appeal stands dismissed for non-compliance.
75418 161/2018 7A EPF Appeal G.B. Engg. Enterprises Pvt. Ltd., RPFC, Trichy 29/11/2021
24/12/2021
05/01/2022
13/01/2022
18/01/2022
Final Order-The Appeal stands dismissed for non-compliance.
75419 161/2018 7A EPF Appeal G.B. Engg. Enterprises Pvt. Ltd., RPFC, Trichy 29/11/2021
24/12/2021
05/01/2022
13/01/2022
18/01/2022
Final Order-The Appeal stands dismissed for non-compliance.
75420 161/2018 7A EPF Appeal G.B. Engg. Enterprises Pvt. Ltd., RPFC, Trichy 29/11/2021
24/12/2021
05/01/2022
13/01/2022
18/01/2022
Final Order-The Appeal stands dismissed for non-compliance.
75421 157/2018 14B EPF Appeal Palayapalayam Association APFC, Tiruchirapalli 22/08/2023
05/12/2023
23/04/2024
23/07/2024
25/10/2024
23/01/2025
24/04/2025
23/07/2025
19/09/2025
Final Order - The Appeal stands dismissed for want of prosecution.
75422 157/2018 14B EPF Appeal Palayapalayam Association APFC, Tiruchirapalli 22/08/2023
05/12/2023
23/04/2024
23/07/2024
25/10/2024
23/01/2025
24/04/2025
23/07/2025
19/09/2025
Final Order - The Appeal stands dismissed for want of prosecution.
75423 157/2018 14B EPF Appeal Palayapalayam Association APFC, Tiruchirapalli 22/08/2023
05/12/2023
23/04/2024
23/07/2024
25/10/2024
23/01/2025
24/04/2025
23/07/2025
19/09/2025
Final Order - The Appeal stands dismissed for want of prosecution.
75424 157/2018 14B EPF Appeal Palayapalayam Association APFC, Tiruchirapalli 22/08/2023
05/12/2023
23/04/2024
23/07/2024
25/10/2024
23/01/2025
24/04/2025
23/07/2025
19/09/2025
Final Order - The Appeal stands dismissed for want of prosecution.
75425 157/2018 14B EPF Appeal Palayapalayam Association APFC, Tiruchirapalli 22/08/2023
05/12/2023
23/04/2024
23/07/2024
25/10/2024
23/01/2025
24/04/2025
23/07/2025
19/09/2025
Final Order - The Appeal stands dismissed for want of prosecution.
75426 157/2018 14B EPF Appeal Palayapalayam Association APFC, Tiruchirapalli 22/08/2023
05/12/2023
23/04/2024
23/07/2024
25/10/2024
23/01/2025
24/04/2025
23/07/2025
19/09/2025
Final Order - The Appeal stands dismissed for want of prosecution.
75427 157/2018 14B EPF Appeal Palayapalayam Association APFC, Tiruchirapalli 22/08/2023
05/12/2023
23/04/2024
23/07/2024
25/10/2024
23/01/2025
24/04/2025
23/07/2025
19/09/2025
Final Order - The Appeal stands dismissed for want of prosecution.
75428 157/2018 14B EPF Appeal Palayapalayam Association APFC, Tiruchirapalli 22/08/2023
05/12/2023
23/04/2024
23/07/2024
25/10/2024
23/01/2025
24/04/2025
23/07/2025
19/09/2025
Final Order - The Appeal stands dismissed for want of prosecution.
75429 157/2018 14B EPF Appeal Palayapalayam Association APFC, Tiruchirapalli 22/08/2023
05/12/2023
23/04/2024
23/07/2024
25/10/2024
23/01/2025
24/04/2025
23/07/2025
19/09/2025
Final Order - The Appeal stands dismissed for want of prosecution.
75430 152/2018 14B EPF Appeal Vinay Bakery Product Pvt. Ltd. APFC, Tiruchirapalli 23/04/2024
23/07/2024
25/10/2024
23/01/2025
24/04/2025
23/07/2025
19/09/2025
10/10/2025
Final Order - The Appeal is dismissed.
75431 152/2018 14B EPF Appeal Vinay Bakery Product Pvt. Ltd. APFC, Tiruchirapalli 23/04/2024
23/07/2024
25/10/2024
23/01/2025
24/04/2025
23/07/2025
19/09/2025
10/10/2025
Final Order - The Appeal is dismissed.
75432 152/2018 14B EPF Appeal Vinay Bakery Product Pvt. Ltd. APFC, Tiruchirapalli 23/04/2024
23/07/2024
25/10/2024
23/01/2025
24/04/2025
23/07/2025
19/09/2025
10/10/2025
Final Order - The Appeal is dismissed.
75433 152/2018 14B EPF Appeal Vinay Bakery Product Pvt. Ltd. APFC, Tiruchirapalli 23/04/2024
23/07/2024
25/10/2024
23/01/2025
24/04/2025
23/07/2025
19/09/2025
10/10/2025
Final Order - The Appeal is dismissed.
75434 152/2018 14B EPF Appeal Vinay Bakery Product Pvt. Ltd. APFC, Tiruchirapalli 23/04/2024
23/07/2024
25/10/2024
23/01/2025
24/04/2025
23/07/2025
19/09/2025
10/10/2025
Final Order - The Appeal is dismissed.
75435 152/2018 14B EPF Appeal Vinay Bakery Product Pvt. Ltd. APFC, Tiruchirapalli 23/04/2024
23/07/2024
25/10/2024
23/01/2025
24/04/2025
23/07/2025
19/09/2025
10/10/2025
Final Order - The Appeal is dismissed.
75436 152/2018 14B EPF Appeal Vinay Bakery Product Pvt. Ltd. APFC, Tiruchirapalli 23/04/2024
23/07/2024
25/10/2024
23/01/2025
24/04/2025
23/07/2025
19/09/2025
10/10/2025
Final Order - The Appeal is dismissed.
75437 152/2018 14B EPF Appeal Vinay Bakery Product Pvt. Ltd. APFC, Tiruchirapalli 23/04/2024
23/07/2024
25/10/2024
23/01/2025
24/04/2025
23/07/2025
19/09/2025
10/10/2025
Final Order - The Appeal is dismissed.
75438 149/2018 14B-7Q EPF Appeal Irudaya Andavan Teacher Training Institute APFC, Trichy 22/06/2023
08/08/2023
19/12/2023
12/03/2024
19/06/2024
26/09/2024
27/12/2024
27/03/2025
26/06/2025
25/08/2025
Final Order - The Appeal Stands dismissed for want of prosecution.
75439 149/2018 14B-7Q EPF Appeal Irudaya Andavan Teacher Training Institute APFC, Trichy 22/06/2023
08/08/2023
19/12/2023
12/03/2024
19/06/2024
26/09/2024
27/12/2024
27/03/2025
26/06/2025
25/08/2025
Final Order - The Appeal Stands dismissed for want of prosecution.
75440 149/2018 14B-7Q EPF Appeal Irudaya Andavan Teacher Training Institute APFC, Trichy 22/06/2023
08/08/2023
19/12/2023
12/03/2024
19/06/2024
26/09/2024
27/12/2024
27/03/2025
26/06/2025
25/08/2025
Final Order - The Appeal Stands dismissed for want of prosecution.
75441 149/2018 14B-7Q EPF Appeal Irudaya Andavan Teacher Training Institute APFC, Trichy 22/06/2023
08/08/2023
19/12/2023
12/03/2024
19/06/2024
26/09/2024
27/12/2024
27/03/2025
26/06/2025
25/08/2025
Final Order - The Appeal Stands dismissed for want of prosecution.
75442 149/2018 14B-7Q EPF Appeal Irudaya Andavan Teacher Training Institute APFC, Trichy 22/06/2023
08/08/2023
19/12/2023
12/03/2024
19/06/2024
26/09/2024
27/12/2024
27/03/2025
26/06/2025
25/08/2025
Final Order - The Appeal Stands dismissed for want of prosecution.
75443 149/2018 14B-7Q EPF Appeal Irudaya Andavan Teacher Training Institute APFC, Trichy 22/06/2023
08/08/2023
19/12/2023
12/03/2024
19/06/2024
26/09/2024
27/12/2024
27/03/2025
26/06/2025
25/08/2025
Final Order - The Appeal Stands dismissed for want of prosecution.
75444 149/2018 14B-7Q EPF Appeal Irudaya Andavan Teacher Training Institute APFC, Trichy 22/06/2023
08/08/2023
19/12/2023
12/03/2024
19/06/2024
26/09/2024
27/12/2024
27/03/2025
26/06/2025
25/08/2025
Final Order - The Appeal Stands dismissed for want of prosecution.
75445 149/2018 14B-7Q EPF Appeal Irudaya Andavan Teacher Training Institute APFC, Trichy 22/06/2023
08/08/2023
19/12/2023
12/03/2024
19/06/2024
26/09/2024
27/12/2024
27/03/2025
26/06/2025
25/08/2025
Final Order - The Appeal Stands dismissed for want of prosecution.
75446 149/2018 14B-7Q EPF Appeal Irudaya Andavan Teacher Training Institute APFC, Trichy 22/06/2023
08/08/2023
19/12/2023
12/03/2024
19/06/2024
26/09/2024
27/12/2024
27/03/2025
26/06/2025
25/08/2025
Final Order - The Appeal Stands dismissed for want of prosecution.
75447 149/2018 14B-7Q EPF Appeal Irudaya Andavan Teacher Training Institute APFC, Trichy 22/06/2023
08/08/2023
19/12/2023
12/03/2024
19/06/2024
26/09/2024
27/12/2024
27/03/2025
26/06/2025
25/08/2025
Final Order - The Appeal Stands dismissed for want of prosecution.
75448 146/2018 14B-7Q EPF Appeal Balaji Bhaavan APFC, Trichy 25/10/2024
23/01/2025
24/04/2025
23/07/2025
19/09/2025
31/12/2025
04/02/2026
(Special Campaign) Final Order - The Appeal u/s. 14B of the Act is dismissed. The Appeal u/s. 7Q of the Act is not maintainable.
75449 146/2018 14B-7Q EPF Appeal Balaji Bhaavan APFC, Trichy 25/10/2024
23/01/2025
24/04/2025
23/07/2025
19/09/2025
31/12/2025
04/02/2026
(Special Campaign) Final Order - The Appeal u/s. 14B of the Act is dismissed. The Appeal u/s. 7Q of the Act is not maintainable.
75450 146/2018 14B-7Q EPF Appeal Balaji Bhaavan APFC, Trichy 25/10/2024
23/01/2025
24/04/2025
23/07/2025
19/09/2025
31/12/2025
04/02/2026
(Special Campaign) Final Order - The Appeal u/s. 14B of the Act is dismissed. The Appeal u/s. 7Q of the Act is not maintainable.