Cause List

E.g., 08/04/2026
S.No. Case No. Subject Case Type Name of Appellant Respondent Next Date Details Order / Decision Edit
64901 CGIT/LC/EPFA/94/2017 14B-7Q EPF Appeal NAVAI SINGH SAHAKARI SHAKKAR KARKHANA APFC, INDORE 02/09/2021
26/10/2021
DISMISS Download, Download
64902 CGIT/LC/EPFA/94/2017 14B-7Q EPF Appeal NAVAI SINGH SAHAKARI SHAKKAR KARKHANA APFC, INDORE 02/09/2021
26/10/2021
DISMISS Download, Download
64903 588/2018 14B EPF Appeal Gounder & Company Pvt. Ltd APFC, Coimbatore 24/04/2024
24/07/2024
04/11/2024
10/02/2025
05/05/2025
25/07/2025
25/09/2025
01/01/2026
04/02/2026
(Special Campaign) Final Order - The Appeal is partly allowed. 30% of the assessed amount is waived off. The Respondent is directed to recover only 70% of the assessed amount of damages u/s. 14B of the Act.
64904 588/2018 14B EPF Appeal Gounder & Company Pvt. Ltd APFC, Coimbatore 24/04/2024
24/07/2024
04/11/2024
10/02/2025
05/05/2025
25/07/2025
25/09/2025
01/01/2026
04/02/2026
(Special Campaign) Final Order - The Appeal is partly allowed. 30% of the assessed amount is waived off. The Respondent is directed to recover only 70% of the assessed amount of damages u/s. 14B of the Act.
64905 588/2018 14B EPF Appeal Gounder & Company Pvt. Ltd APFC, Coimbatore 24/04/2024
24/07/2024
04/11/2024
10/02/2025
05/05/2025
25/07/2025
25/09/2025
01/01/2026
04/02/2026
(Special Campaign) Final Order - The Appeal is partly allowed. 30% of the assessed amount is waived off. The Respondent is directed to recover only 70% of the assessed amount of damages u/s. 14B of the Act.
64906 588/2018 14B EPF Appeal Gounder & Company Pvt. Ltd APFC, Coimbatore 24/04/2024
24/07/2024
04/11/2024
10/02/2025
05/05/2025
25/07/2025
25/09/2025
01/01/2026
04/02/2026
(Special Campaign) Final Order - The Appeal is partly allowed. 30% of the assessed amount is waived off. The Respondent is directed to recover only 70% of the assessed amount of damages u/s. 14B of the Act.
64907 588/2018 14B EPF Appeal Gounder & Company Pvt. Ltd APFC, Coimbatore 24/04/2024
24/07/2024
04/11/2024
10/02/2025
05/05/2025
25/07/2025
25/09/2025
01/01/2026
04/02/2026
(Special Campaign) Final Order - The Appeal is partly allowed. 30% of the assessed amount is waived off. The Respondent is directed to recover only 70% of the assessed amount of damages u/s. 14B of the Act.
64908 588/2018 14B EPF Appeal Gounder & Company Pvt. Ltd APFC, Coimbatore 24/04/2024
24/07/2024
04/11/2024
10/02/2025
05/05/2025
25/07/2025
25/09/2025
01/01/2026
04/02/2026
(Special Campaign) Final Order - The Appeal is partly allowed. 30% of the assessed amount is waived off. The Respondent is directed to recover only 70% of the assessed amount of damages u/s. 14B of the Act.
64909 588/2018 14B EPF Appeal Gounder & Company Pvt. Ltd APFC, Coimbatore 24/04/2024
24/07/2024
04/11/2024
10/02/2025
05/05/2025
25/07/2025
25/09/2025
01/01/2026
04/02/2026
(Special Campaign) Final Order - The Appeal is partly allowed. 30% of the assessed amount is waived off. The Respondent is directed to recover only 70% of the assessed amount of damages u/s. 14B of the Act.
64910 588/2018 14B EPF Appeal Gounder & Company Pvt. Ltd APFC, Coimbatore 24/04/2024
24/07/2024
04/11/2024
10/02/2025
05/05/2025
25/07/2025
25/09/2025
01/01/2026
04/02/2026
(Special Campaign) Final Order - The Appeal is partly allowed. 30% of the assessed amount is waived off. The Respondent is directed to recover only 70% of the assessed amount of damages u/s. 14B of the Act.
64911 588/2018 14B EPF Appeal Gounder & Company Pvt. Ltd APFC, Coimbatore 24/04/2024
24/07/2024
04/11/2024
10/02/2025
05/05/2025
25/07/2025
25/09/2025
01/01/2026
04/02/2026
(Special Campaign) Final Order - The Appeal is partly allowed. 30% of the assessed amount is waived off. The Respondent is directed to recover only 70% of the assessed amount of damages u/s. 14B of the Act.
64912 132/2017 14B EPF Appeal Radha Krishna Mills Ltd. APFC, Coimbatore 10/09/2024
10/12/2024
13/02/2025
08/05/2025
06/08/2025
15/10/2025
16/01/2026
16/04/2026
None appeared on behalf of the Appellant. The Counsel on behalf of the Respondent is present. List to 16.04.2026 for hearing on Arguments/filing of written submission.
64913 132/2017 14B EPF Appeal Radha Krishna Mills Ltd. APFC, Coimbatore 10/09/2024
10/12/2024
13/02/2025
08/05/2025
06/08/2025
15/10/2025
16/01/2026
16/04/2026
None appeared on behalf of the Appellant. The Counsel on behalf of the Respondent is present. List to 16.04.2026 for hearing on Arguments/filing of written submission.
64914 132/2017 14B EPF Appeal Radha Krishna Mills Ltd. APFC, Coimbatore 10/09/2024
10/12/2024
13/02/2025
08/05/2025
06/08/2025
15/10/2025
16/01/2026
16/04/2026
None appeared on behalf of the Appellant. The Counsel on behalf of the Respondent is present. List to 16.04.2026 for hearing on Arguments/filing of written submission.
64915 132/2017 14B EPF Appeal Radha Krishna Mills Ltd. APFC, Coimbatore 10/09/2024
10/12/2024
13/02/2025
08/05/2025
06/08/2025
15/10/2025
16/01/2026
16/04/2026
None appeared on behalf of the Appellant. The Counsel on behalf of the Respondent is present. List to 16.04.2026 for hearing on Arguments/filing of written submission.
64916 132/2017 14B EPF Appeal Radha Krishna Mills Ltd. APFC, Coimbatore 10/09/2024
10/12/2024
13/02/2025
08/05/2025
06/08/2025
15/10/2025
16/01/2026
16/04/2026
None appeared on behalf of the Appellant. The Counsel on behalf of the Respondent is present. List to 16.04.2026 for hearing on Arguments/filing of written submission.
64917 132/2017 14B EPF Appeal Radha Krishna Mills Ltd. APFC, Coimbatore 10/09/2024
10/12/2024
13/02/2025
08/05/2025
06/08/2025
15/10/2025
16/01/2026
16/04/2026
None appeared on behalf of the Appellant. The Counsel on behalf of the Respondent is present. List to 16.04.2026 for hearing on Arguments/filing of written submission.
64918 132/2017 14B EPF Appeal Radha Krishna Mills Ltd. APFC, Coimbatore 10/09/2024
10/12/2024
13/02/2025
08/05/2025
06/08/2025
15/10/2025
16/01/2026
16/04/2026
None appeared on behalf of the Appellant. The Counsel on behalf of the Respondent is present. List to 16.04.2026 for hearing on Arguments/filing of written submission.
64919 132/2017 14B EPF Appeal Radha Krishna Mills Ltd. APFC, Coimbatore 10/09/2024
10/12/2024
13/02/2025
08/05/2025
06/08/2025
15/10/2025
16/01/2026
16/04/2026
None appeared on behalf of the Appellant. The Counsel on behalf of the Respondent is present. List to 16.04.2026 for hearing on Arguments/filing of written submission.
64920 149/2017 7Q EPF Appeal Radha Krishna Mills Ltd. APFC, Coimbatore 04/03/2025
02/05/2025
20/06/2025
13/08/2025
24/10/2025
16/02/2026
Final Order - The Appeal stands dismissed for want of prosecution.
64921 149/2017 7Q EPF Appeal Radha Krishna Mills Ltd. APFC, Coimbatore 04/03/2025
02/05/2025
20/06/2025
13/08/2025
24/10/2025
16/02/2026
Final Order - The Appeal stands dismissed for want of prosecution.
64922 149/2017 7Q EPF Appeal Radha Krishna Mills Ltd. APFC, Coimbatore 04/03/2025
02/05/2025
20/06/2025
13/08/2025
24/10/2025
16/02/2026
Final Order - The Appeal stands dismissed for want of prosecution.
64923 149/2017 7Q EPF Appeal Radha Krishna Mills Ltd. APFC, Coimbatore 04/03/2025
02/05/2025
20/06/2025
13/08/2025
24/10/2025
16/02/2026
Final Order - The Appeal stands dismissed for want of prosecution.
64924 149/2017 7Q EPF Appeal Radha Krishna Mills Ltd. APFC, Coimbatore 04/03/2025
02/05/2025
20/06/2025
13/08/2025
24/10/2025
16/02/2026
Final Order - The Appeal stands dismissed for want of prosecution.
64925 149/2017 7Q EPF Appeal Radha Krishna Mills Ltd. APFC, Coimbatore 04/03/2025
02/05/2025
20/06/2025
13/08/2025
24/10/2025
16/02/2026
Final Order - The Appeal stands dismissed for want of prosecution.
64926 CGIT/LC/EPFA/93/2017 SECTION-7A EPF Appeal ROCA BATHROOM PRODUCT APFC, INDORE 03/09/2025
13/01/2026
18/02/2026
04/05/2026
FOR ARGUMENT Download, Download, Download, Download, Download, Download
64927 CGIT/LC/EPFA/93/2017 SECTION-7A EPF Appeal ROCA BATHROOM PRODUCT APFC, INDORE 03/09/2025
13/01/2026
18/02/2026
04/05/2026
FOR ARGUMENT Download, Download, Download, Download, Download, Download
64928 CGIT/LC/EPFA/93/2017 SECTION-7A EPF Appeal ROCA BATHROOM PRODUCT APFC, INDORE 03/09/2025
13/01/2026
18/02/2026
04/05/2026
FOR ARGUMENT Download, Download, Download, Download, Download, Download
64929 CGIT/LC/EPFA/93/2017 SECTION-7A EPF Appeal ROCA BATHROOM PRODUCT APFC, INDORE 03/09/2025
13/01/2026
18/02/2026
04/05/2026
FOR ARGUMENT Download, Download, Download, Download, Download, Download
64930 285/2018 7A EPF Appeal Carolyn Estate RPFC, Coimbatore 10/12/2024
13/02/2025
08/05/2025
06/08/2025
15/10/2025
16/01/2026
16/04/2026
The Counsel on behalf of the Appellant prays time for Arguments. Time granted. The learned Counsel on behalf of the Respondent is present. List to 16.04.2026 for hearing on Arguments/filing of written submission.
64931 285/2018 7A EPF Appeal Carolyn Estate RPFC, Coimbatore 10/12/2024
13/02/2025
08/05/2025
06/08/2025
15/10/2025
16/01/2026
16/04/2026
The Counsel on behalf of the Appellant prays time for Arguments. Time granted. The learned Counsel on behalf of the Respondent is present. List to 16.04.2026 for hearing on Arguments/filing of written submission.
64932 285/2018 7A EPF Appeal Carolyn Estate RPFC, Coimbatore 10/12/2024
13/02/2025
08/05/2025
06/08/2025
15/10/2025
16/01/2026
16/04/2026
The Counsel on behalf of the Appellant prays time for Arguments. Time granted. The learned Counsel on behalf of the Respondent is present. List to 16.04.2026 for hearing on Arguments/filing of written submission.
64933 285/2018 7A EPF Appeal Carolyn Estate RPFC, Coimbatore 10/12/2024
13/02/2025
08/05/2025
06/08/2025
15/10/2025
16/01/2026
16/04/2026
The Counsel on behalf of the Appellant prays time for Arguments. Time granted. The learned Counsel on behalf of the Respondent is present. List to 16.04.2026 for hearing on Arguments/filing of written submission.
64934 285/2018 7A EPF Appeal Carolyn Estate RPFC, Coimbatore 10/12/2024
13/02/2025
08/05/2025
06/08/2025
15/10/2025
16/01/2026
16/04/2026
The Counsel on behalf of the Appellant prays time for Arguments. Time granted. The learned Counsel on behalf of the Respondent is present. List to 16.04.2026 for hearing on Arguments/filing of written submission.
64935 285/2018 7A EPF Appeal Carolyn Estate RPFC, Coimbatore 10/12/2024
13/02/2025
08/05/2025
06/08/2025
15/10/2025
16/01/2026
16/04/2026
The Counsel on behalf of the Appellant prays time for Arguments. Time granted. The learned Counsel on behalf of the Respondent is present. List to 16.04.2026 for hearing on Arguments/filing of written submission.
64936 285/2018 7A EPF Appeal Carolyn Estate RPFC, Coimbatore 10/12/2024
13/02/2025
08/05/2025
06/08/2025
15/10/2025
16/01/2026
16/04/2026
The Counsel on behalf of the Appellant prays time for Arguments. Time granted. The learned Counsel on behalf of the Respondent is present. List to 16.04.2026 for hearing on Arguments/filing of written submission.
64937 599/2018 14B EPF Appeal Niranjan Enterprises APFC, Coimbatore 03/02/2025
02/04/2025
28/05/2025
16/07/2025
12/09/2025
26/12/2025
25/02/2026
(Special Campaign) Final Order - Waived 30% of assessed amount passed by Respondent order dtd 09.02.2018. Respondent will recover remaining 70% of assessed amount from Appellant in accordance with law
64938 599/2018 14B EPF Appeal Niranjan Enterprises APFC, Coimbatore 03/02/2025
02/04/2025
28/05/2025
16/07/2025
12/09/2025
26/12/2025
25/02/2026
(Special Campaign) Final Order - Waived 30% of assessed amount passed by Respondent order dtd 09.02.2018. Respondent will recover remaining 70% of assessed amount from Appellant in accordance with law
64939 599/2018 14B EPF Appeal Niranjan Enterprises APFC, Coimbatore 03/02/2025
02/04/2025
28/05/2025
16/07/2025
12/09/2025
26/12/2025
25/02/2026
(Special Campaign) Final Order - Waived 30% of assessed amount passed by Respondent order dtd 09.02.2018. Respondent will recover remaining 70% of assessed amount from Appellant in accordance with law
64940 599/2018 14B EPF Appeal Niranjan Enterprises APFC, Coimbatore 03/02/2025
02/04/2025
28/05/2025
16/07/2025
12/09/2025
26/12/2025
25/02/2026
(Special Campaign) Final Order - Waived 30% of assessed amount passed by Respondent order dtd 09.02.2018. Respondent will recover remaining 70% of assessed amount from Appellant in accordance with law
64941 599/2018 14B EPF Appeal Niranjan Enterprises APFC, Coimbatore 03/02/2025
02/04/2025
28/05/2025
16/07/2025
12/09/2025
26/12/2025
25/02/2026
(Special Campaign) Final Order - Waived 30% of assessed amount passed by Respondent order dtd 09.02.2018. Respondent will recover remaining 70% of assessed amount from Appellant in accordance with law
64942 599/2018 14B EPF Appeal Niranjan Enterprises APFC, Coimbatore 03/02/2025
02/04/2025
28/05/2025
16/07/2025
12/09/2025
26/12/2025
25/02/2026
(Special Campaign) Final Order - Waived 30% of assessed amount passed by Respondent order dtd 09.02.2018. Respondent will recover remaining 70% of assessed amount from Appellant in accordance with law
64943 599/2018 14B EPF Appeal Niranjan Enterprises APFC, Coimbatore 03/02/2025
02/04/2025
28/05/2025
16/07/2025
12/09/2025
26/12/2025
25/02/2026
(Special Campaign) Final Order - Waived 30% of assessed amount passed by Respondent order dtd 09.02.2018. Respondent will recover remaining 70% of assessed amount from Appellant in accordance with law
64944 612/2018 14B EPF Appeal Palani Andavar Cotton & Synthetic Spinners Ltd. APFC, Coimbatore 30/12/2024
28/03/2025
27/06/2025
28/08/2025
21/11/2025
06/02/2026
(Special Campaign) Final Order - The Appeal is partly allowed. 30% of the assessed amount is waived off. The Respondent is directed to recover only 70% of the assessed amount of damages u/s. 14B of the Act.
64945 612/2018 14B EPF Appeal Palani Andavar Cotton & Synthetic Spinners Ltd. APFC, Coimbatore 30/12/2024
28/03/2025
27/06/2025
28/08/2025
21/11/2025
06/02/2026
(Special Campaign) Final Order - The Appeal is partly allowed. 30% of the assessed amount is waived off. The Respondent is directed to recover only 70% of the assessed amount of damages u/s. 14B of the Act.
64946 612/2018 14B EPF Appeal Palani Andavar Cotton & Synthetic Spinners Ltd. APFC, Coimbatore 30/12/2024
28/03/2025
27/06/2025
28/08/2025
21/11/2025
06/02/2026
(Special Campaign) Final Order - The Appeal is partly allowed. 30% of the assessed amount is waived off. The Respondent is directed to recover only 70% of the assessed amount of damages u/s. 14B of the Act.
64947 612/2018 14B EPF Appeal Palani Andavar Cotton & Synthetic Spinners Ltd. APFC, Coimbatore 30/12/2024
28/03/2025
27/06/2025
28/08/2025
21/11/2025
06/02/2026
(Special Campaign) Final Order - The Appeal is partly allowed. 30% of the assessed amount is waived off. The Respondent is directed to recover only 70% of the assessed amount of damages u/s. 14B of the Act.
64948 612/2018 14B EPF Appeal Palani Andavar Cotton & Synthetic Spinners Ltd. APFC, Coimbatore 30/12/2024
28/03/2025
27/06/2025
28/08/2025
21/11/2025
06/02/2026
(Special Campaign) Final Order - The Appeal is partly allowed. 30% of the assessed amount is waived off. The Respondent is directed to recover only 70% of the assessed amount of damages u/s. 14B of the Act.
64949 612/2018 14B EPF Appeal Palani Andavar Cotton & Synthetic Spinners Ltd. APFC, Coimbatore 30/12/2024
28/03/2025
27/06/2025
28/08/2025
21/11/2025
06/02/2026
(Special Campaign) Final Order - The Appeal is partly allowed. 30% of the assessed amount is waived off. The Respondent is directed to recover only 70% of the assessed amount of damages u/s. 14B of the Act.
64950 CGIT/LC/EPFA/91/2017 SECTION-7A EPF Appeal SACHIDANAND STEEL SALES INDIA PVT.LTD. APFC, INDORE 02/09/2021
26/10/2021
DISMISS Download, Download

Pages