Cause List

E.g., 05/04/2026
S.No. Case No. Subject Case Type Name of Appellant Respondent Next Date Details Order / Decision Edit
49501 150/2019 14B EPF Appeal Indroyal Crafts Pvt. Ltd., APFC, Tirunelveli 08/09/2021
12/01/2022
21/04/2022
26/12/2024
07/02/2025
15/04/2025
04/06/2025
30/07/2025
09/10/2025
Final Order - The Appeal is partly allowed. The Respondent is directed to recover only 75% of assessed damages and remaining 25% of damages is waived off.
49502 150/2019 14B EPF Appeal Indroyal Crafts Pvt. Ltd., APFC, Tirunelveli 08/09/2021
12/01/2022
21/04/2022
26/12/2024
07/02/2025
15/04/2025
04/06/2025
30/07/2025
09/10/2025
Final Order - The Appeal is partly allowed. The Respondent is directed to recover only 75% of assessed damages and remaining 25% of damages is waived off.
49503 150/2019 14B EPF Appeal Indroyal Crafts Pvt. Ltd., APFC, Tirunelveli 08/09/2021
12/01/2022
21/04/2022
26/12/2024
07/02/2025
15/04/2025
04/06/2025
30/07/2025
09/10/2025
Final Order - The Appeal is partly allowed. The Respondent is directed to recover only 75% of assessed damages and remaining 25% of damages is waived off.
49504 152/2019 7A EPF Appeal Pollachi Municipality RPFC-II, Coimbatore 24/07/2024
04/11/2024
10/02/2025
05/05/2025
25/07/2025
25/09/2025
01/01/2026
10/04/2026
None appeared on behalf of the Appellant. The Representative Counsel on behalf of the Respondent is present. List to 10.04.2026 for hearing on Arguments/filing of written submission.
49505 152/2019 7A EPF Appeal Pollachi Municipality RPFC-II, Coimbatore 24/07/2024
04/11/2024
10/02/2025
05/05/2025
25/07/2025
25/09/2025
01/01/2026
10/04/2026
None appeared on behalf of the Appellant. The Representative Counsel on behalf of the Respondent is present. List to 10.04.2026 for hearing on Arguments/filing of written submission.
49506 152/2019 7A EPF Appeal Pollachi Municipality RPFC-II, Coimbatore 24/07/2024
04/11/2024
10/02/2025
05/05/2025
25/07/2025
25/09/2025
01/01/2026
10/04/2026
None appeared on behalf of the Appellant. The Representative Counsel on behalf of the Respondent is present. List to 10.04.2026 for hearing on Arguments/filing of written submission.
49507 152/2019 7A EPF Appeal Pollachi Municipality RPFC-II, Coimbatore 24/07/2024
04/11/2024
10/02/2025
05/05/2025
25/07/2025
25/09/2025
01/01/2026
10/04/2026
None appeared on behalf of the Appellant. The Representative Counsel on behalf of the Respondent is present. List to 10.04.2026 for hearing on Arguments/filing of written submission.
49508 152/2019 7A EPF Appeal Pollachi Municipality RPFC-II, Coimbatore 24/07/2024
04/11/2024
10/02/2025
05/05/2025
25/07/2025
25/09/2025
01/01/2026
10/04/2026
None appeared on behalf of the Appellant. The Representative Counsel on behalf of the Respondent is present. List to 10.04.2026 for hearing on Arguments/filing of written submission.
49509 152/2019 7A EPF Appeal Pollachi Municipality RPFC-II, Coimbatore 24/07/2024
04/11/2024
10/02/2025
05/05/2025
25/07/2025
25/09/2025
01/01/2026
10/04/2026
None appeared on behalf of the Appellant. The Representative Counsel on behalf of the Respondent is present. List to 10.04.2026 for hearing on Arguments/filing of written submission.
49510 152/2019 7A EPF Appeal Pollachi Municipality RPFC-II, Coimbatore 24/07/2024
04/11/2024
10/02/2025
05/05/2025
25/07/2025
25/09/2025
01/01/2026
10/04/2026
None appeared on behalf of the Appellant. The Representative Counsel on behalf of the Respondent is present. List to 10.04.2026 for hearing on Arguments/filing of written submission.
49511 152/2019 7A EPF Appeal Pollachi Municipality RPFC-II, Coimbatore 24/07/2024
04/11/2024
10/02/2025
05/05/2025
25/07/2025
25/09/2025
01/01/2026
10/04/2026
None appeared on behalf of the Appellant. The Representative Counsel on behalf of the Respondent is present. List to 10.04.2026 for hearing on Arguments/filing of written submission.
49512 CGIT-2/EPFA/120 of 2019 EPFA EPF Appeal M/s Sheetal Manufacturing Co Pvt Ltd APFC, EPFO Bandra 28/04/2025
18/08/2025
23/12/2025
27/04/2026
Final Arguments
49513 CGIT-2/EPFA/120 of 2019 EPFA EPF Appeal M/s Sheetal Manufacturing Co Pvt Ltd APFC, EPFO Bandra 28/04/2025
18/08/2025
23/12/2025
27/04/2026
Final Arguments
49514 CGIT-2/EPFA/120 of 2019 EPFA EPF Appeal M/s Sheetal Manufacturing Co Pvt Ltd APFC, EPFO Bandra 28/04/2025
18/08/2025
23/12/2025
27/04/2026
Final Arguments
49515 CGIT-2/EPFA/120 of 2019 EPFA EPF Appeal M/s Sheetal Manufacturing Co Pvt Ltd APFC, EPFO Bandra 28/04/2025
18/08/2025
23/12/2025
27/04/2026
Final Arguments
49516 EPFA No. 04/2019 14-B & 7-Q EPF Appeal Pioneer Electrical APFC, Durgapur 14/03/2024 Disposed of on being withdrawn
49517 CR 16/2019 Regular Employment ID President ATC Telecom Infrastructure Closed
49518 CR 08/2019 Demand ID General Secretary BEL closed on 12/02/2026
49519 CR 07/2019 two increments ID Manjunath BMRCL 29/04/2026 Counter Statement
49520 Ref. No. 39/2019 Violation of Natural Justice ID Koyala Mazdoor Congress (H.M.S.) Khas Kajora Colliery of M/s. ECL 03/06/2025 Award Reserved
49521 CGIT/LC/EPFA/MISC/20/2019 EPFFA MISC EPF Appeal M/S. INDRA EXPORTS PVT. LTD. [ E.220.2017 ] APPFC, INDORE 23/03/2022
23/09/2022
15/12/2022
RESTORED TO ORIGNAL CASE NO. AS PER MPHC ORDER Download, Download, Download, Download, Download, Download, Download
49522 CGIT/LC/EPFA/MISC/20/2019 EPFFA MISC EPF Appeal M/S. INDRA EXPORTS PVT. LTD. [ E.220.2017 ] APPFC, INDORE 23/03/2022
23/09/2022
15/12/2022
RESTORED TO ORIGNAL CASE NO. AS PER MPHC ORDER Download, Download, Download, Download, Download, Download, Download
49523 CGIT/LC/EPFA/MISC/20/2019 EPFFA MISC EPF Appeal M/S. INDRA EXPORTS PVT. LTD. [ E.220.2017 ] APPFC, INDORE 23/03/2022
23/09/2022
15/12/2022
RESTORED TO ORIGNAL CASE NO. AS PER MPHC ORDER Download, Download, Download, Download, Download, Download, Download
49524 143/2019 7Q EPF Appeal East Coast Constructions and Industries Ltd., APFC, Chennai 03/01/2020
06/01/2020
07/01/2020
Appeal Stands Dismissed
49525 143/2019 7Q EPF Appeal East Coast Constructions and Industries Ltd., APFC, Chennai 03/01/2020
06/01/2020
07/01/2020
Appeal Stands Dismissed
49526 143/2019 7Q EPF Appeal East Coast Constructions and Industries Ltd., APFC, Chennai 03/01/2020
06/01/2020
07/01/2020
Appeal Stands Dismissed
49527 144/2019 14B EPF Appeal Ganga Foundations Ltd., RPFC-II,Chennai 23/01/2025
24/04/2025
23/07/2025
19/09/2025
26/12/2025
03/02/2026
(Special Campaign) Final Order - The Appeal is partly allowed. 30% of the assessed amount is waived off. The Deposited amount shall be adjusted subject to verification.
49528 144/2019 14B EPF Appeal Ganga Foundations Ltd., RPFC-II,Chennai 23/01/2025
24/04/2025
23/07/2025
19/09/2025
26/12/2025
03/02/2026
(Special Campaign) Final Order - The Appeal is partly allowed. 30% of the assessed amount is waived off. The Deposited amount shall be adjusted subject to verification.
49529 144/2019 14B EPF Appeal Ganga Foundations Ltd., RPFC-II,Chennai 23/01/2025
24/04/2025
23/07/2025
19/09/2025
26/12/2025
03/02/2026
(Special Campaign) Final Order - The Appeal is partly allowed. 30% of the assessed amount is waived off. The Deposited amount shall be adjusted subject to verification.
49530 144/2019 14B EPF Appeal Ganga Foundations Ltd., RPFC-II,Chennai 23/01/2025
24/04/2025
23/07/2025
19/09/2025
26/12/2025
03/02/2026
(Special Campaign) Final Order - The Appeal is partly allowed. 30% of the assessed amount is waived off. The Deposited amount shall be adjusted subject to verification.
49531 144/2019 14B EPF Appeal Ganga Foundations Ltd., RPFC-II,Chennai 23/01/2025
24/04/2025
23/07/2025
19/09/2025
26/12/2025
03/02/2026
(Special Campaign) Final Order - The Appeal is partly allowed. 30% of the assessed amount is waived off. The Deposited amount shall be adjusted subject to verification.
49532 144/2019 14B EPF Appeal Ganga Foundations Ltd., RPFC-II,Chennai 23/01/2025
24/04/2025
23/07/2025
19/09/2025
26/12/2025
03/02/2026
(Special Campaign) Final Order - The Appeal is partly allowed. 30% of the assessed amount is waived off. The Deposited amount shall be adjusted subject to verification.
49533 145/2019 7A EPF Appeal AMRL Hightech City Ltd., APFC, Chennai 24/01/2025
08/01/2025
20/02/2025
17/03/2025
15/04/2025
27/05/2025
14/07/2025
28/07/2025
Final Order - The Appeal stands dismissed for want of prosection.
49534 145/2019 7A EPF Appeal AMRL Hightech City Ltd., APFC, Chennai 24/01/2025
08/01/2025
20/02/2025
17/03/2025
15/04/2025
27/05/2025
14/07/2025
28/07/2025
Final Order - The Appeal stands dismissed for want of prosection.
49535 145/2019 7A EPF Appeal AMRL Hightech City Ltd., APFC, Chennai 24/01/2025
08/01/2025
20/02/2025
17/03/2025
15/04/2025
27/05/2025
14/07/2025
28/07/2025
Final Order - The Appeal stands dismissed for want of prosection.
49536 145/2019 7A EPF Appeal AMRL Hightech City Ltd., APFC, Chennai 24/01/2025
08/01/2025
20/02/2025
17/03/2025
15/04/2025
27/05/2025
14/07/2025
28/07/2025
Final Order - The Appeal stands dismissed for want of prosection.
49537 145/2019 7A EPF Appeal AMRL Hightech City Ltd., APFC, Chennai 24/01/2025
08/01/2025
20/02/2025
17/03/2025
15/04/2025
27/05/2025
14/07/2025
28/07/2025
Final Order - The Appeal stands dismissed for want of prosection.
49538 145/2019 7A EPF Appeal AMRL Hightech City Ltd., APFC, Chennai 24/01/2025
08/01/2025
20/02/2025
17/03/2025
15/04/2025
27/05/2025
14/07/2025
28/07/2025
Final Order - The Appeal stands dismissed for want of prosection.
49539 145/2019 7A EPF Appeal AMRL Hightech City Ltd., APFC, Chennai 24/01/2025
08/01/2025
20/02/2025
17/03/2025
15/04/2025
27/05/2025
14/07/2025
28/07/2025
Final Order - The Appeal stands dismissed for want of prosection.
49540 145/2019 7A EPF Appeal AMRL Hightech City Ltd., APFC, Chennai 24/01/2025
08/01/2025
20/02/2025
17/03/2025
15/04/2025
27/05/2025
14/07/2025
28/07/2025
Final Order - The Appeal stands dismissed for want of prosection.
49541 146/2019 14B EPF Appeal Teknoturf Info Services Pvt. Ltd., RPFC-II, Coimbatore 04/11/2024
10/02/2025
05/05/2025
25/07/2025
25/09/2025
01/01/2026
04/02/2026
(Special Campaign) Final Order - The Appeal is partly allowed. 30% of the assessed damages amount is waived off.
49542 146/2019 14B EPF Appeal Teknoturf Info Services Pvt. Ltd., RPFC-II, Coimbatore 04/11/2024
10/02/2025
05/05/2025
25/07/2025
25/09/2025
01/01/2026
04/02/2026
(Special Campaign) Final Order - The Appeal is partly allowed. 30% of the assessed damages amount is waived off.
49543 146/2019 14B EPF Appeal Teknoturf Info Services Pvt. Ltd., RPFC-II, Coimbatore 04/11/2024
10/02/2025
05/05/2025
25/07/2025
25/09/2025
01/01/2026
04/02/2026
(Special Campaign) Final Order - The Appeal is partly allowed. 30% of the assessed damages amount is waived off.
49544 146/2019 14B EPF Appeal Teknoturf Info Services Pvt. Ltd., RPFC-II, Coimbatore 04/11/2024
10/02/2025
05/05/2025
25/07/2025
25/09/2025
01/01/2026
04/02/2026
(Special Campaign) Final Order - The Appeal is partly allowed. 30% of the assessed damages amount is waived off.
49545 146/2019 14B EPF Appeal Teknoturf Info Services Pvt. Ltd., RPFC-II, Coimbatore 04/11/2024
10/02/2025
05/05/2025
25/07/2025
25/09/2025
01/01/2026
04/02/2026
(Special Campaign) Final Order - The Appeal is partly allowed. 30% of the assessed damages amount is waived off.
49546 146/2019 14B EPF Appeal Teknoturf Info Services Pvt. Ltd., RPFC-II, Coimbatore 04/11/2024
10/02/2025
05/05/2025
25/07/2025
25/09/2025
01/01/2026
04/02/2026
(Special Campaign) Final Order - The Appeal is partly allowed. 30% of the assessed damages amount is waived off.
49547 146/2019 14B EPF Appeal Teknoturf Info Services Pvt. Ltd., RPFC-II, Coimbatore 04/11/2024
10/02/2025
05/05/2025
25/07/2025
25/09/2025
01/01/2026
04/02/2026
(Special Campaign) Final Order - The Appeal is partly allowed. 30% of the assessed damages amount is waived off.
49548 147/2019 14B EPF Appeal Barnas International Pvt. Ltd., APFC, Chennai 10/02/2025
05/05/2025
25/07/2025
25/09/2025
01/01/2026
04/02/2026
(Special Campaign) Final Order - The Appeal is partly allowed. 25% of the assessed amount is waived off. The Respondent is directed to recover only 75% of the assessed amount of damages u/s. 14B of the Act.
49549 147/2019 14B EPF Appeal Barnas International Pvt. Ltd., APFC, Chennai 10/02/2025
05/05/2025
25/07/2025
25/09/2025
01/01/2026
04/02/2026
(Special Campaign) Final Order - The Appeal is partly allowed. 25% of the assessed amount is waived off. The Respondent is directed to recover only 75% of the assessed amount of damages u/s. 14B of the Act.
49550 147/2019 14B EPF Appeal Barnas International Pvt. Ltd., APFC, Chennai 10/02/2025
05/05/2025
25/07/2025
25/09/2025
01/01/2026
04/02/2026
(Special Campaign) Final Order - The Appeal is partly allowed. 25% of the assessed amount is waived off. The Respondent is directed to recover only 75% of the assessed amount of damages u/s. 14B of the Act.