52851 646/2018 14B EPF Appeal AJC English School & Junior College APFC, Trichy 09/09/2024
09/12/2024
21/01/2025
23/04/2025
23/07/2025
19/09/2025
11/12/2025
18/03/2026
Final Order - Waived 37% of assessed amount passed by Respondent order dtd 13.04.2018. Respondent will recover remaining 63% of assessed amount from Appellant in accordance with law
52852 646/2018 14B EPF Appeal AJC English School & Junior College APFC, Trichy 09/09/2024
09/12/2024
21/01/2025
23/04/2025
23/07/2025
19/09/2025
11/12/2025
18/03/2026
Final Order - Waived 37% of assessed amount passed by Respondent order dtd 13.04.2018. Respondent will recover remaining 63% of assessed amount from Appellant in accordance with law
52853 646/2018 14B EPF Appeal AJC English School & Junior College APFC, Trichy 09/09/2024
09/12/2024
21/01/2025
23/04/2025
23/07/2025
19/09/2025
11/12/2025
18/03/2026
Final Order - Waived 37% of assessed amount passed by Respondent order dtd 13.04.2018. Respondent will recover remaining 63% of assessed amount from Appellant in accordance with law
52854 646/2018 14B EPF Appeal AJC English School & Junior College APFC, Trichy 09/09/2024
09/12/2024
21/01/2025
23/04/2025
23/07/2025
19/09/2025
11/12/2025
18/03/2026
Final Order - Waived 37% of assessed amount passed by Respondent order dtd 13.04.2018. Respondent will recover remaining 63% of assessed amount from Appellant in accordance with law
52855 646/2018 14B EPF Appeal AJC English School & Junior College APFC, Trichy 09/09/2024
09/12/2024
21/01/2025
23/04/2025
23/07/2025
19/09/2025
11/12/2025
18/03/2026
Final Order - Waived 37% of assessed amount passed by Respondent order dtd 13.04.2018. Respondent will recover remaining 63% of assessed amount from Appellant in accordance with law
52856 419/2018 14B EPF Appeal Vignesh Leather Company APFC, Trichy 03/06/2024
09/09/2024
09/12/2024
21/01/2025
23/04/2025
22/07/2025
17/09/2025
10/10/2025
Final Order - The Appeal is partly allowed. The Respondent is directed to recover only 70% of assessed damages amount.
52857 419/2018 14B EPF Appeal Vignesh Leather Company APFC, Trichy 03/06/2024
09/09/2024
09/12/2024
21/01/2025
23/04/2025
22/07/2025
17/09/2025
10/10/2025
Final Order - The Appeal is partly allowed. The Respondent is directed to recover only 70% of assessed damages amount.
52858 419/2018 14B EPF Appeal Vignesh Leather Company APFC, Trichy 03/06/2024
09/09/2024
09/12/2024
21/01/2025
23/04/2025
22/07/2025
17/09/2025
10/10/2025
Final Order - The Appeal is partly allowed. The Respondent is directed to recover only 70% of assessed damages amount.
52859 419/2018 14B EPF Appeal Vignesh Leather Company APFC, Trichy 03/06/2024
09/09/2024
09/12/2024
21/01/2025
23/04/2025
22/07/2025
17/09/2025
10/10/2025
Final Order - The Appeal is partly allowed. The Respondent is directed to recover only 70% of assessed damages amount.
52860 419/2018 14B EPF Appeal Vignesh Leather Company APFC, Trichy 03/06/2024
09/09/2024
09/12/2024
21/01/2025
23/04/2025
22/07/2025
17/09/2025
10/10/2025
Final Order - The Appeal is partly allowed. The Respondent is directed to recover only 70% of assessed damages amount.
52861 419/2018 14B EPF Appeal Vignesh Leather Company APFC, Trichy 03/06/2024
09/09/2024
09/12/2024
21/01/2025
23/04/2025
22/07/2025
17/09/2025
10/10/2025
Final Order - The Appeal is partly allowed. The Respondent is directed to recover only 70% of assessed damages amount.
52862 419/2018 14B EPF Appeal Vignesh Leather Company APFC, Trichy 03/06/2024
09/09/2024
09/12/2024
21/01/2025
23/04/2025
22/07/2025
17/09/2025
10/10/2025
Final Order - The Appeal is partly allowed. The Respondent is directed to recover only 70% of assessed damages amount.
52863 419/2018 14B EPF Appeal Vignesh Leather Company APFC, Trichy 03/06/2024
09/09/2024
09/12/2024
21/01/2025
23/04/2025
22/07/2025
17/09/2025
10/10/2025
Final Order - The Appeal is partly allowed. The Respondent is directed to recover only 70% of assessed damages amount.
52864 418/2018 14B EPF Appeal Sri Kanchi Sankara APFC, Trichy 06/08/2024
07/11/2024
13/02/2025
08/05/2025
06/08/2025
15/10/2025
16/01/2026
16/04/2026
Final Order - 32% of the assessed amount passed by the Respondent order dated 23.12.2015 is waived. The Respondent will recover remaining 68% of the assessed amount from the Appellant establishment in accordance with law.
52865 418/2018 14B EPF Appeal Sri Kanchi Sankara APFC, Trichy 06/08/2024
07/11/2024
13/02/2025
08/05/2025
06/08/2025
15/10/2025
16/01/2026
16/04/2026
Final Order - 32% of the assessed amount passed by the Respondent order dated 23.12.2015 is waived. The Respondent will recover remaining 68% of the assessed amount from the Appellant establishment in accordance with law.
52866 418/2018 14B EPF Appeal Sri Kanchi Sankara APFC, Trichy 06/08/2024
07/11/2024
13/02/2025
08/05/2025
06/08/2025
15/10/2025
16/01/2026
16/04/2026
Final Order - 32% of the assessed amount passed by the Respondent order dated 23.12.2015 is waived. The Respondent will recover remaining 68% of the assessed amount from the Appellant establishment in accordance with law.
52867 418/2018 14B EPF Appeal Sri Kanchi Sankara APFC, Trichy 06/08/2024
07/11/2024
13/02/2025
08/05/2025
06/08/2025
15/10/2025
16/01/2026
16/04/2026
Final Order - 32% of the assessed amount passed by the Respondent order dated 23.12.2015 is waived. The Respondent will recover remaining 68% of the assessed amount from the Appellant establishment in accordance with law.
52868 418/2018 14B EPF Appeal Sri Kanchi Sankara APFC, Trichy 06/08/2024
07/11/2024
13/02/2025
08/05/2025
06/08/2025
15/10/2025
16/01/2026
16/04/2026
Final Order - 32% of the assessed amount passed by the Respondent order dated 23.12.2015 is waived. The Respondent will recover remaining 68% of the assessed amount from the Appellant establishment in accordance with law.
52869 418/2018 14B EPF Appeal Sri Kanchi Sankara APFC, Trichy 06/08/2024
07/11/2024
13/02/2025
08/05/2025
06/08/2025
15/10/2025
16/01/2026
16/04/2026
Final Order - 32% of the assessed amount passed by the Respondent order dated 23.12.2015 is waived. The Respondent will recover remaining 68% of the assessed amount from the Appellant establishment in accordance with law.
52870 418/2018 14B EPF Appeal Sri Kanchi Sankara APFC, Trichy 06/08/2024
07/11/2024
13/02/2025
08/05/2025
06/08/2025
15/10/2025
16/01/2026
16/04/2026
Final Order - 32% of the assessed amount passed by the Respondent order dated 23.12.2015 is waived. The Respondent will recover remaining 68% of the assessed amount from the Appellant establishment in accordance with law.
52871 418/2018 14B EPF Appeal Sri Kanchi Sankara APFC, Trichy 06/08/2024
07/11/2024
13/02/2025
08/05/2025
06/08/2025
15/10/2025
16/01/2026
16/04/2026
Final Order - 32% of the assessed amount passed by the Respondent order dated 23.12.2015 is waived. The Respondent will recover remaining 68% of the assessed amount from the Appellant establishment in accordance with law.
52872 417/2018 14B EPF Appeal Modern Associate Contract APFC, Trichy 20/08/2024
21/11/2024
28/02/2025
23/05/2025
20/08/2025
07/11/2025
13/02/2026
Final Order - 32% of the assessed amount passed by the Respondent order dated 03.11.2015 is waived. The Respondent will recover remaining 68% of the assessed amount from the Appellant establishment in accordance with law.
52873 417/2018 14B EPF Appeal Modern Associate Contract APFC, Trichy 20/08/2024
21/11/2024
28/02/2025
23/05/2025
20/08/2025
07/11/2025
13/02/2026
Final Order - 32% of the assessed amount passed by the Respondent order dated 03.11.2015 is waived. The Respondent will recover remaining 68% of the assessed amount from the Appellant establishment in accordance with law.
52874 417/2018 14B EPF Appeal Modern Associate Contract APFC, Trichy 20/08/2024
21/11/2024
28/02/2025
23/05/2025
20/08/2025
07/11/2025
13/02/2026
Final Order - 32% of the assessed amount passed by the Respondent order dated 03.11.2015 is waived. The Respondent will recover remaining 68% of the assessed amount from the Appellant establishment in accordance with law.
52875 417/2018 14B EPF Appeal Modern Associate Contract APFC, Trichy 20/08/2024
21/11/2024
28/02/2025
23/05/2025
20/08/2025
07/11/2025
13/02/2026
Final Order - 32% of the assessed amount passed by the Respondent order dated 03.11.2015 is waived. The Respondent will recover remaining 68% of the assessed amount from the Appellant establishment in accordance with law.
52876 417/2018 14B EPF Appeal Modern Associate Contract APFC, Trichy 20/08/2024
21/11/2024
28/02/2025
23/05/2025
20/08/2025
07/11/2025
13/02/2026
Final Order - 32% of the assessed amount passed by the Respondent order dated 03.11.2015 is waived. The Respondent will recover remaining 68% of the assessed amount from the Appellant establishment in accordance with law.
52877 417/2018 14B EPF Appeal Modern Associate Contract APFC, Trichy 20/08/2024
21/11/2024
28/02/2025
23/05/2025
20/08/2025
07/11/2025
13/02/2026
Final Order - 32% of the assessed amount passed by the Respondent order dated 03.11.2015 is waived. The Respondent will recover remaining 68% of the assessed amount from the Appellant establishment in accordance with law.
52878 417/2018 14B EPF Appeal Modern Associate Contract APFC, Trichy 20/08/2024
21/11/2024
28/02/2025
23/05/2025
20/08/2025
07/11/2025
13/02/2026
Final Order - 32% of the assessed amount passed by the Respondent order dated 03.11.2015 is waived. The Respondent will recover remaining 68% of the assessed amount from the Appellant establishment in accordance with law.
52879 416/2018 14B EPF Appeal The Professional Couriers APFC, Trichy 13/03/2025
12/06/2025
20/06/2025
02/07/2025
01/09/2025
07/11/2025
13/02/2026
Final Order - 30% of the assessed amount passed by the Respondent order dated 13.01.2016 is waived. The Respondent will recover remaining 70% of the assessed amount from the Appellant establishment in accordance with law.
52880 416/2018 14B EPF Appeal The Professional Couriers APFC, Trichy 13/03/2025
12/06/2025
20/06/2025
02/07/2025
01/09/2025
07/11/2025
13/02/2026
Final Order - 30% of the assessed amount passed by the Respondent order dated 13.01.2016 is waived. The Respondent will recover remaining 70% of the assessed amount from the Appellant establishment in accordance with law.
52881 416/2018 14B EPF Appeal The Professional Couriers APFC, Trichy 13/03/2025
12/06/2025
20/06/2025
02/07/2025
01/09/2025
07/11/2025
13/02/2026
Final Order - 30% of the assessed amount passed by the Respondent order dated 13.01.2016 is waived. The Respondent will recover remaining 70% of the assessed amount from the Appellant establishment in accordance with law.
52882 416/2018 14B EPF Appeal The Professional Couriers APFC, Trichy 13/03/2025
12/06/2025
20/06/2025
02/07/2025
01/09/2025
07/11/2025
13/02/2026
Final Order - 30% of the assessed amount passed by the Respondent order dated 13.01.2016 is waived. The Respondent will recover remaining 70% of the assessed amount from the Appellant establishment in accordance with law.
52883 416/2018 14B EPF Appeal The Professional Couriers APFC, Trichy 13/03/2025
12/06/2025
20/06/2025
02/07/2025
01/09/2025
07/11/2025
13/02/2026
Final Order - 30% of the assessed amount passed by the Respondent order dated 13.01.2016 is waived. The Respondent will recover remaining 70% of the assessed amount from the Appellant establishment in accordance with law.
52884 416/2018 14B EPF Appeal The Professional Couriers APFC, Trichy 13/03/2025
12/06/2025
20/06/2025
02/07/2025
01/09/2025
07/11/2025
13/02/2026
Final Order - 30% of the assessed amount passed by the Respondent order dated 13.01.2016 is waived. The Respondent will recover remaining 70% of the assessed amount from the Appellant establishment in accordance with law.
52885 416/2018 14B EPF Appeal The Professional Couriers APFC, Trichy 13/03/2025
12/06/2025
20/06/2025
02/07/2025
01/09/2025
07/11/2025
13/02/2026
Final Order - 30% of the assessed amount passed by the Respondent order dated 13.01.2016 is waived. The Respondent will recover remaining 70% of the assessed amount from the Appellant establishment in accordance with law.
52886 415/2018 14B EPF Appeal S. Saravana Contractor APFC, Trichy 09/12/2024
21/01/2025
23/04/2025
22/07/2025
17/09/2025
19/12/2025
03/02/2026
(Special Campaign) Final Order - The Appeal is partly allowed. 30% of the assessed amount is waived off. The Respondent is directed to recover only 70% of the assessed amount of damages u/s. 14B of the Act. The appeal u/s. 7Q of the Act is dismissed.
52887 415/2018 14B EPF Appeal S. Saravana Contractor APFC, Trichy 09/12/2024
21/01/2025
23/04/2025
22/07/2025
17/09/2025
19/12/2025
03/02/2026
(Special Campaign) Final Order - The Appeal is partly allowed. 30% of the assessed amount is waived off. The Respondent is directed to recover only 70% of the assessed amount of damages u/s. 14B of the Act. The appeal u/s. 7Q of the Act is dismissed.
52888 415/2018 14B EPF Appeal S. Saravana Contractor APFC, Trichy 09/12/2024
21/01/2025
23/04/2025
22/07/2025
17/09/2025
19/12/2025
03/02/2026
(Special Campaign) Final Order - The Appeal is partly allowed. 30% of the assessed amount is waived off. The Respondent is directed to recover only 70% of the assessed amount of damages u/s. 14B of the Act. The appeal u/s. 7Q of the Act is dismissed.
52889 415/2018 14B EPF Appeal S. Saravana Contractor APFC, Trichy 09/12/2024
21/01/2025
23/04/2025
22/07/2025
17/09/2025
19/12/2025
03/02/2026
(Special Campaign) Final Order - The Appeal is partly allowed. 30% of the assessed amount is waived off. The Respondent is directed to recover only 70% of the assessed amount of damages u/s. 14B of the Act. The appeal u/s. 7Q of the Act is dismissed.
52890 415/2018 14B EPF Appeal S. Saravana Contractor APFC, Trichy 09/12/2024
21/01/2025
23/04/2025
22/07/2025
17/09/2025
19/12/2025
03/02/2026
(Special Campaign) Final Order - The Appeal is partly allowed. 30% of the assessed amount is waived off. The Respondent is directed to recover only 70% of the assessed amount of damages u/s. 14B of the Act. The appeal u/s. 7Q of the Act is dismissed.
52891 415/2018 14B EPF Appeal S. Saravana Contractor APFC, Trichy 09/12/2024
21/01/2025
23/04/2025
22/07/2025
17/09/2025
19/12/2025
03/02/2026
(Special Campaign) Final Order - The Appeal is partly allowed. 30% of the assessed amount is waived off. The Respondent is directed to recover only 70% of the assessed amount of damages u/s. 14B of the Act. The appeal u/s. 7Q of the Act is dismissed.
52892 415/2018 14B EPF Appeal S. Saravana Contractor APFC, Trichy 09/12/2024
21/01/2025
23/04/2025
22/07/2025
17/09/2025
19/12/2025
03/02/2026
(Special Campaign) Final Order - The Appeal is partly allowed. 30% of the assessed amount is waived off. The Respondent is directed to recover only 70% of the assessed amount of damages u/s. 14B of the Act. The appeal u/s. 7Q of the Act is dismissed.
52893 414/2018 14B EPF Appeal Dr.Samuel A Mathenan Nursing Home APFC, Trichy 20/11/2019
27/01/2020
12/03/2020
11/06/2020
09/09/2020
18/01/2021
21/06/2021
24/11/2021
08/03/2022
11/03/2022
Final Order-The Appeal stands dismissed.
52894 414/2018 14B EPF Appeal Dr.Samuel A Mathenan Nursing Home APFC, Trichy 20/11/2019
27/01/2020
12/03/2020
11/06/2020
09/09/2020
18/01/2021
21/06/2021
24/11/2021
08/03/2022
11/03/2022
Final Order-The Appeal stands dismissed.
52895 414/2018 14B EPF Appeal Dr.Samuel A Mathenan Nursing Home APFC, Trichy 20/11/2019
27/01/2020
12/03/2020
11/06/2020
09/09/2020
18/01/2021
21/06/2021
24/11/2021
08/03/2022
11/03/2022
Final Order-The Appeal stands dismissed.
52896 414/2018 14B EPF Appeal Dr.Samuel A Mathenan Nursing Home APFC, Trichy 20/11/2019
27/01/2020
12/03/2020
11/06/2020
09/09/2020
18/01/2021
21/06/2021
24/11/2021
08/03/2022
11/03/2022
Final Order-The Appeal stands dismissed.
52897 414/2018 14B EPF Appeal Dr.Samuel A Mathenan Nursing Home APFC, Trichy 20/11/2019
27/01/2020
12/03/2020
11/06/2020
09/09/2020
18/01/2021
21/06/2021
24/11/2021
08/03/2022
11/03/2022
Final Order-The Appeal stands dismissed.
52898 414/2018 14B EPF Appeal Dr.Samuel A Mathenan Nursing Home APFC, Trichy 20/11/2019
27/01/2020
12/03/2020
11/06/2020
09/09/2020
18/01/2021
21/06/2021
24/11/2021
08/03/2022
11/03/2022
Final Order-The Appeal stands dismissed.
52899 414/2018 14B EPF Appeal Dr.Samuel A Mathenan Nursing Home APFC, Trichy 20/11/2019
27/01/2020
12/03/2020
11/06/2020
09/09/2020
18/01/2021
21/06/2021
24/11/2021
08/03/2022
11/03/2022
Final Order-The Appeal stands dismissed.
52900 414/2018 14B EPF Appeal Dr.Samuel A Mathenan Nursing Home APFC, Trichy 20/11/2019
27/01/2020
12/03/2020
11/06/2020
09/09/2020
18/01/2021
21/06/2021
24/11/2021
08/03/2022
11/03/2022
Final Order-The Appeal stands dismissed.