Cause List

E.g., 05/06/2026
S.No. Case No. Subject Case Type Name of Appellant Respondent Next Date Details Order / Decision Edit
75601 459/2018 14B-7Q EPF Appeal Kwality Spinning Mills Pvt. Ltd. APFC, Coimbatore 10/12/2024
24/01/2025
25/04/2025
24/07/2025
24/09/2025
31/12/2025
02/04/2026
Final Order - 30% of the assessed amount passed by the Respondent order dated 11.02.2016 is waived. The Respondent will recover remaining 70% of the assessed amount from the Appellant establishment in accordance with law.
75602 459/2018 14B-7Q EPF Appeal Kwality Spinning Mills Pvt. Ltd. APFC, Coimbatore 10/12/2024
24/01/2025
25/04/2025
24/07/2025
24/09/2025
31/12/2025
02/04/2026
Final Order - 30% of the assessed amount passed by the Respondent order dated 11.02.2016 is waived. The Respondent will recover remaining 70% of the assessed amount from the Appellant establishment in accordance with law.
75603 459/2018 14B-7Q EPF Appeal Kwality Spinning Mills Pvt. Ltd. APFC, Coimbatore 10/12/2024
24/01/2025
25/04/2025
24/07/2025
24/09/2025
31/12/2025
02/04/2026
Final Order - 30% of the assessed amount passed by the Respondent order dated 11.02.2016 is waived. The Respondent will recover remaining 70% of the assessed amount from the Appellant establishment in accordance with law.
75604 541/2017 8F EPF Appeal Trippur Surya Hi-Tech Apparel Pvt. Ltd. APFC, Coimbatore 05/04/2019
15/05/2019
Admission/Compliance
75605 541/2017 8F EPF Appeal Trippur Surya Hi-Tech Apparel Pvt. Ltd. APFC, Coimbatore 05/04/2019
15/05/2019
Admission/Compliance
75606 252/2017 14B EPF Appeal R.R. Infraa Constructions APFC, Madurai 29/01/2025
19/03/2025
15/05/2025
02/07/2025
01/09/2025
10/10/2025
09/01/2026
05/02/2026
(Special Campaign) Final Order - The Appeal is partly allowed. 35% of the assessed amount is waived off. The Respondent is directed to recover only 65% of the assessed amount of damages u/s. 14B of the Act.
75607 252/2017 14B EPF Appeal R.R. Infraa Constructions APFC, Madurai 29/01/2025
19/03/2025
15/05/2025
02/07/2025
01/09/2025
10/10/2025
09/01/2026
05/02/2026
(Special Campaign) Final Order - The Appeal is partly allowed. 35% of the assessed amount is waived off. The Respondent is directed to recover only 65% of the assessed amount of damages u/s. 14B of the Act.
75608 252/2017 14B EPF Appeal R.R. Infraa Constructions APFC, Madurai 29/01/2025
19/03/2025
15/05/2025
02/07/2025
01/09/2025
10/10/2025
09/01/2026
05/02/2026
(Special Campaign) Final Order - The Appeal is partly allowed. 35% of the assessed amount is waived off. The Respondent is directed to recover only 65% of the assessed amount of damages u/s. 14B of the Act.
75609 252/2017 14B EPF Appeal R.R. Infraa Constructions APFC, Madurai 29/01/2025
19/03/2025
15/05/2025
02/07/2025
01/09/2025
10/10/2025
09/01/2026
05/02/2026
(Special Campaign) Final Order - The Appeal is partly allowed. 35% of the assessed amount is waived off. The Respondent is directed to recover only 65% of the assessed amount of damages u/s. 14B of the Act.
75610 252/2017 14B EPF Appeal R.R. Infraa Constructions APFC, Madurai 29/01/2025
19/03/2025
15/05/2025
02/07/2025
01/09/2025
10/10/2025
09/01/2026
05/02/2026
(Special Campaign) Final Order - The Appeal is partly allowed. 35% of the assessed amount is waived off. The Respondent is directed to recover only 65% of the assessed amount of damages u/s. 14B of the Act.
75611 252/2017 14B EPF Appeal R.R. Infraa Constructions APFC, Madurai 29/01/2025
19/03/2025
15/05/2025
02/07/2025
01/09/2025
10/10/2025
09/01/2026
05/02/2026
(Special Campaign) Final Order - The Appeal is partly allowed. 35% of the assessed amount is waived off. The Respondent is directed to recover only 65% of the assessed amount of damages u/s. 14B of the Act.
75612 252/2017 14B EPF Appeal R.R. Infraa Constructions APFC, Madurai 29/01/2025
19/03/2025
15/05/2025
02/07/2025
01/09/2025
10/10/2025
09/01/2026
05/02/2026
(Special Campaign) Final Order - The Appeal is partly allowed. 35% of the assessed amount is waived off. The Respondent is directed to recover only 65% of the assessed amount of damages u/s. 14B of the Act.
75613 252/2017 14B EPF Appeal R.R. Infraa Constructions APFC, Madurai 29/01/2025
19/03/2025
15/05/2025
02/07/2025
01/09/2025
10/10/2025
09/01/2026
05/02/2026
(Special Campaign) Final Order - The Appeal is partly allowed. 35% of the assessed amount is waived off. The Respondent is directed to recover only 65% of the assessed amount of damages u/s. 14B of the Act.
75614 677/2018 7A EPF Appeal Vasan Medical Hall RPFC, Trichy 05/04/2019 Admission
75615 161/2018 7A EPF Appeal G.B. Engg. Enterprises Pvt. Ltd., RPFC, Trichy 29/11/2021
24/12/2021
05/01/2022
13/01/2022
18/01/2022
Final Order-The Appeal stands dismissed for non-compliance.
75616 161/2018 7A EPF Appeal G.B. Engg. Enterprises Pvt. Ltd., RPFC, Trichy 29/11/2021
24/12/2021
05/01/2022
13/01/2022
18/01/2022
Final Order-The Appeal stands dismissed for non-compliance.
75617 161/2018 7A EPF Appeal G.B. Engg. Enterprises Pvt. Ltd., RPFC, Trichy 29/11/2021
24/12/2021
05/01/2022
13/01/2022
18/01/2022
Final Order-The Appeal stands dismissed for non-compliance.
75618 161/2018 7A EPF Appeal G.B. Engg. Enterprises Pvt. Ltd., RPFC, Trichy 29/11/2021
24/12/2021
05/01/2022
13/01/2022
18/01/2022
Final Order-The Appeal stands dismissed for non-compliance.
75619 161/2018 7A EPF Appeal G.B. Engg. Enterprises Pvt. Ltd., RPFC, Trichy 29/11/2021
24/12/2021
05/01/2022
13/01/2022
18/01/2022
Final Order-The Appeal stands dismissed for non-compliance.
75620 157/2018 14B EPF Appeal Palayapalayam Association APFC, Tiruchirapalli 22/08/2023
05/12/2023
23/04/2024
23/07/2024
25/10/2024
23/01/2025
24/04/2025
23/07/2025
19/09/2025
Final Order - The Appeal stands dismissed for want of prosecution.
75621 157/2018 14B EPF Appeal Palayapalayam Association APFC, Tiruchirapalli 22/08/2023
05/12/2023
23/04/2024
23/07/2024
25/10/2024
23/01/2025
24/04/2025
23/07/2025
19/09/2025
Final Order - The Appeal stands dismissed for want of prosecution.
75622 157/2018 14B EPF Appeal Palayapalayam Association APFC, Tiruchirapalli 22/08/2023
05/12/2023
23/04/2024
23/07/2024
25/10/2024
23/01/2025
24/04/2025
23/07/2025
19/09/2025
Final Order - The Appeal stands dismissed for want of prosecution.
75623 157/2018 14B EPF Appeal Palayapalayam Association APFC, Tiruchirapalli 22/08/2023
05/12/2023
23/04/2024
23/07/2024
25/10/2024
23/01/2025
24/04/2025
23/07/2025
19/09/2025
Final Order - The Appeal stands dismissed for want of prosecution.
75624 157/2018 14B EPF Appeal Palayapalayam Association APFC, Tiruchirapalli 22/08/2023
05/12/2023
23/04/2024
23/07/2024
25/10/2024
23/01/2025
24/04/2025
23/07/2025
19/09/2025
Final Order - The Appeal stands dismissed for want of prosecution.
75625 157/2018 14B EPF Appeal Palayapalayam Association APFC, Tiruchirapalli 22/08/2023
05/12/2023
23/04/2024
23/07/2024
25/10/2024
23/01/2025
24/04/2025
23/07/2025
19/09/2025
Final Order - The Appeal stands dismissed for want of prosecution.
75626 157/2018 14B EPF Appeal Palayapalayam Association APFC, Tiruchirapalli 22/08/2023
05/12/2023
23/04/2024
23/07/2024
25/10/2024
23/01/2025
24/04/2025
23/07/2025
19/09/2025
Final Order - The Appeal stands dismissed for want of prosecution.
75627 157/2018 14B EPF Appeal Palayapalayam Association APFC, Tiruchirapalli 22/08/2023
05/12/2023
23/04/2024
23/07/2024
25/10/2024
23/01/2025
24/04/2025
23/07/2025
19/09/2025
Final Order - The Appeal stands dismissed for want of prosecution.
75628 157/2018 14B EPF Appeal Palayapalayam Association APFC, Tiruchirapalli 22/08/2023
05/12/2023
23/04/2024
23/07/2024
25/10/2024
23/01/2025
24/04/2025
23/07/2025
19/09/2025
Final Order - The Appeal stands dismissed for want of prosecution.
75629 152/2018 14B EPF Appeal Vinay Bakery Product Pvt. Ltd. APFC, Tiruchirapalli 23/04/2024
23/07/2024
25/10/2024
23/01/2025
24/04/2025
23/07/2025
19/09/2025
10/10/2025
Final Order - The Appeal is dismissed.
75630 152/2018 14B EPF Appeal Vinay Bakery Product Pvt. Ltd. APFC, Tiruchirapalli 23/04/2024
23/07/2024
25/10/2024
23/01/2025
24/04/2025
23/07/2025
19/09/2025
10/10/2025
Final Order - The Appeal is dismissed.
75631 152/2018 14B EPF Appeal Vinay Bakery Product Pvt. Ltd. APFC, Tiruchirapalli 23/04/2024
23/07/2024
25/10/2024
23/01/2025
24/04/2025
23/07/2025
19/09/2025
10/10/2025
Final Order - The Appeal is dismissed.
75632 152/2018 14B EPF Appeal Vinay Bakery Product Pvt. Ltd. APFC, Tiruchirapalli 23/04/2024
23/07/2024
25/10/2024
23/01/2025
24/04/2025
23/07/2025
19/09/2025
10/10/2025
Final Order - The Appeal is dismissed.
75633 152/2018 14B EPF Appeal Vinay Bakery Product Pvt. Ltd. APFC, Tiruchirapalli 23/04/2024
23/07/2024
25/10/2024
23/01/2025
24/04/2025
23/07/2025
19/09/2025
10/10/2025
Final Order - The Appeal is dismissed.
75634 152/2018 14B EPF Appeal Vinay Bakery Product Pvt. Ltd. APFC, Tiruchirapalli 23/04/2024
23/07/2024
25/10/2024
23/01/2025
24/04/2025
23/07/2025
19/09/2025
10/10/2025
Final Order - The Appeal is dismissed.
75635 152/2018 14B EPF Appeal Vinay Bakery Product Pvt. Ltd. APFC, Tiruchirapalli 23/04/2024
23/07/2024
25/10/2024
23/01/2025
24/04/2025
23/07/2025
19/09/2025
10/10/2025
Final Order - The Appeal is dismissed.
75636 152/2018 14B EPF Appeal Vinay Bakery Product Pvt. Ltd. APFC, Tiruchirapalli 23/04/2024
23/07/2024
25/10/2024
23/01/2025
24/04/2025
23/07/2025
19/09/2025
10/10/2025
Final Order - The Appeal is dismissed.
75637 149/2018 14B-7Q EPF Appeal Irudaya Andavan Teacher Training Institute APFC, Trichy 22/06/2023
08/08/2023
19/12/2023
12/03/2024
19/06/2024
26/09/2024
27/12/2024
27/03/2025
26/06/2025
25/08/2025
Final Order - The Appeal Stands dismissed for want of prosecution.
75638 149/2018 14B-7Q EPF Appeal Irudaya Andavan Teacher Training Institute APFC, Trichy 22/06/2023
08/08/2023
19/12/2023
12/03/2024
19/06/2024
26/09/2024
27/12/2024
27/03/2025
26/06/2025
25/08/2025
Final Order - The Appeal Stands dismissed for want of prosecution.
75639 149/2018 14B-7Q EPF Appeal Irudaya Andavan Teacher Training Institute APFC, Trichy 22/06/2023
08/08/2023
19/12/2023
12/03/2024
19/06/2024
26/09/2024
27/12/2024
27/03/2025
26/06/2025
25/08/2025
Final Order - The Appeal Stands dismissed for want of prosecution.
75640 149/2018 14B-7Q EPF Appeal Irudaya Andavan Teacher Training Institute APFC, Trichy 22/06/2023
08/08/2023
19/12/2023
12/03/2024
19/06/2024
26/09/2024
27/12/2024
27/03/2025
26/06/2025
25/08/2025
Final Order - The Appeal Stands dismissed for want of prosecution.
75641 149/2018 14B-7Q EPF Appeal Irudaya Andavan Teacher Training Institute APFC, Trichy 22/06/2023
08/08/2023
19/12/2023
12/03/2024
19/06/2024
26/09/2024
27/12/2024
27/03/2025
26/06/2025
25/08/2025
Final Order - The Appeal Stands dismissed for want of prosecution.
75642 149/2018 14B-7Q EPF Appeal Irudaya Andavan Teacher Training Institute APFC, Trichy 22/06/2023
08/08/2023
19/12/2023
12/03/2024
19/06/2024
26/09/2024
27/12/2024
27/03/2025
26/06/2025
25/08/2025
Final Order - The Appeal Stands dismissed for want of prosecution.
75643 149/2018 14B-7Q EPF Appeal Irudaya Andavan Teacher Training Institute APFC, Trichy 22/06/2023
08/08/2023
19/12/2023
12/03/2024
19/06/2024
26/09/2024
27/12/2024
27/03/2025
26/06/2025
25/08/2025
Final Order - The Appeal Stands dismissed for want of prosecution.
75644 149/2018 14B-7Q EPF Appeal Irudaya Andavan Teacher Training Institute APFC, Trichy 22/06/2023
08/08/2023
19/12/2023
12/03/2024
19/06/2024
26/09/2024
27/12/2024
27/03/2025
26/06/2025
25/08/2025
Final Order - The Appeal Stands dismissed for want of prosecution.
75645 149/2018 14B-7Q EPF Appeal Irudaya Andavan Teacher Training Institute APFC, Trichy 22/06/2023
08/08/2023
19/12/2023
12/03/2024
19/06/2024
26/09/2024
27/12/2024
27/03/2025
26/06/2025
25/08/2025
Final Order - The Appeal Stands dismissed for want of prosecution.
75646 149/2018 14B-7Q EPF Appeal Irudaya Andavan Teacher Training Institute APFC, Trichy 22/06/2023
08/08/2023
19/12/2023
12/03/2024
19/06/2024
26/09/2024
27/12/2024
27/03/2025
26/06/2025
25/08/2025
Final Order - The Appeal Stands dismissed for want of prosecution.
75647 146/2018 14B-7Q EPF Appeal Balaji Bhaavan APFC, Trichy 25/10/2024
23/01/2025
24/04/2025
23/07/2025
19/09/2025
31/12/2025
04/02/2026
(Special Campaign) Final Order - The Appeal u/s. 14B of the Act is dismissed. The Appeal u/s. 7Q of the Act is not maintainable.
75648 146/2018 14B-7Q EPF Appeal Balaji Bhaavan APFC, Trichy 25/10/2024
23/01/2025
24/04/2025
23/07/2025
19/09/2025
31/12/2025
04/02/2026
(Special Campaign) Final Order - The Appeal u/s. 14B of the Act is dismissed. The Appeal u/s. 7Q of the Act is not maintainable.
75649 146/2018 14B-7Q EPF Appeal Balaji Bhaavan APFC, Trichy 25/10/2024
23/01/2025
24/04/2025
23/07/2025
19/09/2025
31/12/2025
04/02/2026
(Special Campaign) Final Order - The Appeal u/s. 14B of the Act is dismissed. The Appeal u/s. 7Q of the Act is not maintainable.
75650 146/2018 14B-7Q EPF Appeal Balaji Bhaavan APFC, Trichy 25/10/2024
23/01/2025
24/04/2025
23/07/2025
19/09/2025
31/12/2025
04/02/2026
(Special Campaign) Final Order - The Appeal u/s. 14B of the Act is dismissed. The Appeal u/s. 7Q of the Act is not maintainable.